Major Projects Report 2014 and the Equipment Plan 2014 to 2024, and reforming defence acquisition - Public Accounts Contents


2  Improving DE&S's skills to deliver the Equipment Plan to cost and time

11. The Department has long wrestled with problems in defence acquisition. The need for change has been widely acknowledged and made in a number of our reports and those of the Department. Department-wide changes to ensure the affordability and stability of equipment projects depend on tackling long-standing skills gaps in DE&S, including airworthiness, engineering roles, commercial, logistics and project and programme management. Skills gaps had emerged primarily because DE&S could not recruit and retain enough skilled staff.[14]

12. The Department's preferred option for securing change in DE&S was through a Government-owned, Contractor-operated (GoCo) model—a company where the government controls the assets, but that would be operated on a for-profit basis by a private company. However, this model proved undeliverable, and was halted in 2013, by which point the Department had spent £33 million and two and a half years trying to implement reform at DE&S. In April 2014 the Department changed DE&S into a bespoke trading entity. Under this concept, DE&S remains in the public sector but with freedoms from and flexibilities over civil service pay rules.[15]

13. The National Audit Office found that DE&S had reduced permanent staff numbers by nearly half between 2007 and 2014 to try to reduce operating costs. Potential savings, however, had been offset by employing contractors who, on average, cost between three and four times more than permanent DE&S staff. The overall costs of DE&S's permanent staff and contractors fell by £9 million between 2008-09 (£1,290 million) and 2013-14 (£1,281 million) (Figure 3). The National Audit Office estimated that in 2013-14 contractors' costs comprised 37% (£481 million) of overall operating costs.[16]

14. The Department told us that the freedoms that DE&S now enjoyed as a bespoke trading entity enabled it to offer higher salaries and set its own bonus arrangements to attract and retain skilled staff and to mirror the private sector in how it develops its people. The Department noted that DE&S spent about £550 million a year on civilian staff and £450 million a year on contractors which it considered was the wrong balance, which was why it was trying to push down the amount spent on contractors. However, there was not yet a detailed plan on how the secured freedoms will be used to deliver the skills needed, whilst reducing overall costs.[17]

15. DE&S has contracted with Bechtel and CH2M Hill at a cost of £215 million to strengthen project and programme management and with PWC at a cost of £43 million to determine appropriate human resource structures for DE&S. The Department told us that these managed service provider contracts, each lasting some three and a half years were expected to save some £400 million to £450 million over this period. The Department also told us that it expected these large companies to introduce better processes and systems into DE&S, thus reducing its reliance on contractors to deliver equipment projects.[18]

16. The Department noted that it had agreed with the Treasury that the costs of running DE&S which were £1,290 million in 2014-15 would reduce to £1,079 million by 2017-18, including the cost of the managed service providers. Overall, the Department expected cumulative savings of £392 million over the period, including savings measures devised and delivered by the managed service providers. The Department had set initial performance milestones for the providers to achieve over the first six months of the contract, but had not yet set detailed plans on how it expected them to deliver the savings agreed with the Treasury, nor how it intended to ensure skills were transferred from contractors to permanent staff.[19]


14   C&AG's report, Reforming defence acquisition, paras 1.4, 2.1, 2.2 Back

15   C&AG's report, Reforming defence acquisition, paras 1.15-1.21 Back

16   Q 90; C&AG's report, Reforming defence acquisition, para 1.3, 2.4, 2.2 Back

17   Qq 67, 113; C&AG's Report, Reforming defence acquisition, para 2.7 Back

18   Qq 75, 79, 85; C&AG's Report, Reforming defence acquisition, paras 2.8, 2.13 Back

19   Qq 85, 89; C&AG's Report, Reforming defence acquisition, paras 2.8, 2.13 Back


 
previous page contents next page


© Parliamentary copyright 2015
Prepared 20 March 2015