The Department for Environment, Food and Rural Affairs: oversight of three PFI waste projects - Public Accounts Committee Contents


1  The Department's waste infrastructure programme

1. On the basis of a Report by the Comptroller and Auditor General, we took evidence from the Department for the Environment Food and Rural Affairs (the Department) on its oversight of three PFI waste projects run by Norfolk County Council, Surrey County Council and a joint project managed by Herefordshire Council and Worcestershire County Council.[1]

2. In 1999, the European Union introduced a Directive requiring all member states to reduce the amount of biodegradable municipal waste sent to landfill. The Department has overall responsibility for ensuring that England diverts sufficient waste from landfill to enable the UK to meet its target under this Directive of sending less than 10.2 million tonnes of waste to landfill a year by 2020.[2]

3. The Department established the Waste Infrastructure Delivery Programme (the programme) in July 2006 to help it meet England's contribution towards the EU 2020 target. The aim of the programme is to encourage and support local authorities to develop new waste infrastructure by providing support, guidance and funding. Through the programme, the Department allocates funding for some local authority PFI projects and scrutinises local authorities' plans. The Department also provides funding to a number of PFI projects that pre-date the programme, reaching as far back as 1997-98.[3] Local authorities are the signatories to the PFI contracts and are responsible for ensuring that their waste contracts represent value for money.[4] The programme only provides funding support for local authorities that are entering into PFI contracts to construct waste management assets. This incentivises councils to use PFI over other options for diverting waste from landfill. PFI contracts are long-term undertakings, typically running for 25 to 30 years. The Department is currently providing PFI credits for a range of waste management projects, which include integrated recycling facilities as well as energy-from-waste incinerators.[5]

4. When deciding whether to fund these PFI projects, the Department had to forecast the amount of waste that would be produced. The Department told us that future levels of waste are difficult to predict. Notably, recycling rates are higher now than was predicted when some of the older projects were approved and there are new technologies available for disposing of waste.[6] There are also opportunities to sell waste to European countries where energy-from waste plants have been built to provide municipal heat and power, and there is a substantial demand for waste to burn.[7] The Department noted that it had highlighted to local authorities that selling waste is an option, but it had not incentivized this approach.[8]

5. The Department told us that despite higher recycling rates and new waste-management technologies, it still thought that it was right to provide long-term funding for waste incineration plants. The Department argued that the provision of long-term funding for infrastructure projects from the 1990s onwards was essential as 'in order to get a marketplace to deliver these things, we had to give a degree of certainty'.[9] The Department also told us that the incinerators that it had been funding were still needed to meet the EU targets for 2020 and form part of a package of different types of facility to reduce the use of landfill. The Department conceded, however, that new waste infrastructure needs to generate both electricity and heat to be environmentally viable and stated that it had no plans to provide PFI credits for any new incinerator schemes.[10]

6. Early PFI waste contracts tended to be for integrated waste management contracts, under which contractors provide a range of waste services. By contrast, more recent PFI waste management contracts provide for the construction of specific infrastructure. The early funding agreements for PFI waste management projects that the Department inherited from its predecessor, the Department for the Environment, Transport and the Regions, differ from those signed more recently. The early funding agreements under which the Department for the Environment, Transport and the Regions had agreed to provide funding to local authorities had looser terms which typically committed the Department to start paying grants to the local authorities as soon as the latter began to make payments to the contractors under the contracts. The payments were based on services delivered rather than infrastructure built and the agreements contained no provision for the Department to halt or modify payments without the agreement of the local authority when individual capital assets were not delivered.[11]

7. The funding agreements signed with Surrey County Council and with Herefordshire and Worcestershire Councils highlight the shortcomings of these early agreements to fund PFI projects. In both cases, the Department's payments to the local authorities were aligned with the payments being made by the local authorities to the contractors. The grant payments therefore began as soon as the local authorities began to pay their contractors and the Department has been legally committed to making grant payments to these councils ever since, even though key assets have still not been built.[12] This occurred because the underlying PFI contracts, which dictated the payments owed by the local authorities to the contractors, related to a range of services and committed the local authorities to pay the contractor provided that it achieved certain targets in recycling and waste recovery and did not require all of the expected assets to be constructed before payments started.[13]

8. The Department and its predecessor began making payments to Surrey County Council in 1999 and, by the end of March 2014, had paid £124 million under this funding agreement. The contract that Surrey signed had originally provided for the construction of two energy-from-waste plants, but these have yet to be built.[14] Payments to Herefordshire and Worcestershire County Councils began in December 1998 and totalled £89.5 million by 31 March 2014. Again, the planned energy-from-waste plant has not been built.[15]

9. The Department told us that "[we] have changed the way that we do these contracts, so there are much tighter conditions on the local authority about what happens to the money and what triggers penalties or payments".[16]

10. PFI contracts are complex and specialised instruments that require skilled handling to achieve value for money. Individual local authorities are only likely to enter into such contracts once in a generation. However, there is greater experience and expertise in handling them within central government such as in the Department and HM Treasury. The Department has provided support to local authorities since the start of the programme to help them handle complex PFI projects. In addition to providing local authorities with guidance on planning issues, technology, and procurement options, the Department has funded Partnerships UK to act as 'transactors' to provide expert support and advice to councils. The Department also told us that, when dealing with specialist areas such as hedging, it pointed authorities to external organisations who could provide support.[17] Norfolk County Council in their evidence said that the Department examined and vetted all details of the proposed contracts.[18]


1   C&AG's Report, Oversight of three PFI waste projects, Session 2014-15, HC 264, 17 June 2014, Back

2   C&AG's Report, Oversight of three PFI waste projects, Session 2014-15, HC 264, 17 June 2014, Appendix Four, para 1 to 4. Back

3   Q 2 Back

4   C&AG's Report, Oversight of three PFI waste projects, Session 2014-15, HC 264, 17 June 2014, paragraphs 1.1 to 1.7. Back

5   Q 13 Back

6   Qq 6, 29 Back

7   Qq 31, 33, 119 Back

8   Qq 31,119-121 Back

9   Q 33 Back

10   Qq 6,16 Back

11   C&AG's Report, Oversight of three PFI waste projects, paragraphs 2.21 to 2.26 Back

12   Qq 21, 23 Back

13   Q 22 Back

14   C&AG's Report, Oversight of three PFI waste projects, paragraphs 1.10 to 1.13 Back

15   C&AG's Report, Oversight of three PFI waste projects, paragraphs 1.14 to 1.17 Back

16   Q 111 Back

17   Qq 62-6 Back

18   Evidence from Norfolk County Council to the PAC, 23 June 2014, p 1 Back


 
previous page contents next page


© Parliamentary copyright 2014
Prepared 17 September 2014