The Department for Environment, Food and Rural Affairs: oversight of three PFI waste projects - Public Accounts Committee Contents


2  The Department's oversight of three PFI waste projects

11. The Department for the Environment, Transport and the Regions signed a funding agreement with Surrey County Council in June 1999 for £204.7 million of PFI grant and with Herefordshire Council and Worcestershire County Councils in December 1998 for £143 million.[19] Payment of these grants to the local authorities began shortly after. The terms of the original funding agreements did not allow central government to unilaterally halt or alter the payment terms in the event that key capital assets were not delivered.[20] Although the Department has had responsibility for overseeing these grants since it was created in 2001, it did not review these agreements until 2011, and did not successfully renegotiate the terms with Surrey and with Herefordshire and Worcestershire councils until 2013.[21] As a result, grant payments of £213.5 million were made over fifteen years to Surrey and to Herefordshire and Worcestershire councils even though key facilities were not built. The process of renegotiation was time-consuming. In the case of the Herefordshire and Worcestershire negotiations, Defra confirmed that it took them six months to approve the new funding approach that the local authorities were proposing.[22]

12. The renegotiations with Surrey did not alter the total amount of funding that the Department will provide, but 're-profiled' the schedule of payments. Surrey is expecting a new waste management facility, including a gasifier to produce fuel from waste, to be operational by 2016-17. Under the renegotiated terms, the Department's payments to Surrey has been reduced for the three years beginning 2013-14 and will continue to be lower until the gasifier starts processing waste.[23]

13. The Department's negotiations with Herefordshire and Worcestershire concluded with it reducing the total funding it will provide by £30 million. The planned energy-from-waste plant experienced serious delays in getting planning permission and, by the time permission had been obtained, the contractor could not arrange the necessary financing. The local authorities ultimately decided to build and finance the plant outside the PFI contract, without the PFI credits provided by the Department for a lesser sum, with risks being transferred back to the public sector.[24]

14. The Department signed a funding agreement with Norfolk County Council in February 2012 to contribute £91 million of PFI credits towards a 25-year contract to build an energy-from-waste facility. Norfolk County Council estimate that this would have equated to £169 million in grant payments. However, the planning application to build this facility near King's Lynn was called in by the Secretary of State for Communities and Local Government, and as a result the Council missed the deadline in its funding agreement with the Department to obtain planning permission by 10 June 2013. The Department subsequently revoked its funding in October 2013 and, after initially deciding to proceed without central government funding, Norfolk County Council terminated the PFI contract in April 2014. The contract Norfolk County Council had signed with its contractor included compensation clauses relating to securing finance and foreign exchange hedging and the decision to cancel the contract means that Norfolk County Council is expected to pay the contractor an estimated £33.7 million.[25] The bulk of this compensation relates to contractor costs (£20.3 million) which include fees paid for arranging finance, and fees for unwinding hedging arrangements that were intended to mitigate against foreign exchange risk (£11.8 million).[26]

15. The Department told us that such compensation clauses are standard in the PFI contracts in the programme. Of the eleven bank-funded projects in the programme, the nine that did not have planning consent before financial close all had compensation clauses covering the same sort of costs as the Norfolk contract. Those funded by contractors' balance sheets also contained similar compensation clauses, but without elements related to arranging bank finance.[27] So far, the Norfolk contract is the only one where the compensation clauses have been triggered as no other contracts have been cancelled after signature.[28]

16. The Department told us that, when signing the funding agreement in 2012, it had had serious concerns that Norfolk had not scheduled sufficient time to obtain planning permission. The Department was also aware that any delay in obtaining planning permission posed a serious financial risk to the local taxpayer, as Norfolk had secured finance in advance and signed a related compensation clause with the contractor. The Department raised these concerns with Norfolk County Council as far back as 2010, but the local authority was confident that it would achieve planning permission within the proposed timetable.[29] When asked why it had agreed to provide funding despite having such serious misgivings about the project timetable, the Department confirmed that it had been under no legal obligation to provide funding, but had chosen to do so on the basis that it had been a "reasonable decision" given that Norfolk met the Department's criteria for funding and the local authority could have taken the Department to judicial review if it had not provided funding.[30]

17. A major factor behind the Department's decision to cancel the PFI funding agreement in October 2013 was that the proposed waste facility in Norfolk was no longer needed to meet England's contribution to the EU target.[31] The decision to cancel the funding agreement came only 20 months after it had been signed and was unprecedented within the programme. [32]

18. The Department told us that when it made the decision to withdraw PFI credits from the project, it had been fully aware of the compensation clauses in Norfolk County Council's contract and the compensation costs the council would face if it cancelled the contract. The Department noted that it had considered the impact of withdrawing funding on the affordability of the project to Norfolk when making its decision.[33] Norfolk County Council told us that the Department's withdrawal of funding 'left the County Council limited opportunity to pursue the substantial savings that could have been gained had it adopted different contract terms to those in standard PFI contracts'.[34]




19   C&AG's Report, Oversight of three PFI waste projects, paragraphs 1.10 and 1.14 Back

20   Q 22 Back

21   Qq 124-7 Back

22   Qq 113-17 Back

23   C&AG's Report, Oversight of three PFI waste projects, paragraph 1.13 Back

24   Q 19 and C&AG's Report, Oversight of three PFI waste projects, paragraphs 1.16-19  Back

25   C&AG's Report, Oversight of three PFI waste projects, paragraph 1.20 Back

26   C&AG's Report, Oversight of three PFI waste projects, paragraph 2.41 Back

27   Evidence from Defra Back

28   Q 37 Back

29   Qq 34, 58 Back

30   Qq 43-51 Back

31   Q 101 Back

32   Qq 86-90 Back

33   Qq 39, 85 Back

34   Evidence from Norfolk County Council to the Public Accounts Committee, 23 June 2014, p.2 Back


 
previous page contents next page


© Parliamentary copyright 2014
Prepared 17 September 2014