1 The need for early contracts
1. On the basis of a Report by the Comptroller and
Auditor General[1], we
took evidence from the Department of Energy and Climate Change
(the Department) on early contracts for renewable electricity.
In April 2014, the Department announced the award of contracts
to eight renewable electricity projects.[2]
These contracts are early 'Contracts for Difference' under which
the Department fixes the price which renewable electricity generators
can receive for each unit of electricity they produce, known as
the 'strike price'.[3]
The Contracts for Difference scheme replaces the Renewables Obligation
as the Government's main approach to securing new renewable electricity
generation. Unlike the Renewables Obligation which allows all
eligible projects to receive support at a fixed rate set by the
Department, the Contracts for Difference scheme enables the Department
to limit the number and scale of projects receiving support and
to allow price competition for contracts.[4]
The Department awarded eight early contracts which could in total
cost consumers some £16.6 billion over the 12 to 15 year
terms of the contracts.[5]
2. The Department launched the selection process
to award early Contracts for Difference to renewable electricity
generation projects in March 2013, to address the risk of a hiatus
in investment in renewable electricity generation during the transition
to the main Contracts for Difference scheme, now expected in late
2014.[6] The Department
told us that it had considered a number of alternatives to awarding
early contracts. It decided in 2011, following discussions with
project developers, that doing nothing other than continuing to
make the Renewables Obligation available to new entrants to April
2017 would be insufficient to address the uncertainty for investors
and the potential investment hiatus. A large number of project
developers had suggested extending the Renewables Obligation from
2017 to 2020.[7] The Department
told us that it had also considered offering "letters of
comfort" that might reassure project developers that their
projects would be eligible to apply for a contract in due course.
However, its discussions with project developers indicated that
full early contracts were necessary for investment to continue.[8]
3. The Department's economic analysis showed no financial
benefit from proceeding to award contracts early, compared to
scenarios where the same projects were delayed, and so went ahead
under the main Contracts for Difference regime, or were cancelled.
The Department explained that it went ahead with the early contracts
because it expected them to achieve wider benefits on which it
could not put a monetary value[9]
including demonstrating the operability of the contracts, mitigating
the risk of the UK not meeting its 2020 EU renewable energy target,
and benefits to the renewable electricity supply chain.[10]
4. The Department noted that some of the wider benefits
from awarding early contracts were already emerging. It told us
that early contracts for offshore wind projects had helped to
secure planned investment by Siemens in new wind turbine production
facilities in Hull, with knock on effects beyond the Humber region.
The Department also noted that Drax, which has received an early
contract for one of its biomass conversion units, is also investing
in the supply chain and has arranged for the design of new train
wagons from UK-based companies. [11]
The Department told us it estimated that the early contracts would
support 8,500 jobs in and outside the UK, based on project developers'
application information and the Department's own wider industry
knowledge. The Department expected to monitor actual jobs supported
within its evaluation of the early contracts, in liaison with
the Department for Business, Innovation and Skills, UK Trade and
Investment and project developers. [12]
5. The Department considered that it had needed to
move quickly to meet its legally binding renewable energy and
greenhouse gas emissions targets. Although it had made good progress
on increasing renewable electricity to meet the UK's EU target
to produce 15% of its energy from renewable sources by 2020 and
it had hit its interim target in 2011-12, the UK has to do better
to meet the next interim target.[13]
The Department also noted that the UK's EU renewable energy target
is for electricity, vehicles and heat. As a result, any underperformance
in either heat or vehicles would require more electricity from
renewable sources to make up the shortfall. The Department also
emphasised that action was needed now to meet challenging long-term
targets. The Climate Change Act 2008 target to cut greenhouse
gases by 80% by 2050 requires the complete decarbonisation of
the electricity sector in the long-term.[14]
The Department's data on renewable electricity projects which
are under construction, awaiting construction or seeking planning
permission suggests there could be much more new renewable generation
capacity than is needed to meet the 2020 target. However the Department
considered this capacity may not all be built so early contracts
were important for supporting the continued development of the
renewables industry.[15]
6. The eight early contracts will take up 58% of
the budget for all renewable contracts for the period 2015-16
to 2020-21.[16] The Department
agreed that if less funding had been devoted to the transitional
regime then more would be available for the competitive regime
that it is now intending to apply.[17]
The Department told us it was currently assessing the demand for
future contracts from different renewable electricity projects
and the budgets which it would allocate, and it planned to move
to competition for all technologies as quickly as possible.[18]
It said that without awarding early contracts on this scale it
would not have been able to move so quickly to price competition.
The Department maintains that its transitional arrangements have
encouraged other project developers to progress their projects
and build supply chains to a point where the market may be ready
for price competition under the main Contracts for Difference
scheme. The Department noted, in particular, that they
were on track to move faster than anywhere else in the world to
compete for offshore wind.[19]
1 C&AG's Report, Early contracts for renewable electricity, Session 2014-15, HC 172, 27 June 2014 Back
2
C&AG's Report, para 1.9 Back
3
C&AG's Report, para 1.5 Back
4
C&AG's Report, paras 1.6, 3.31 Back
5
C&AG's Report, para 1.10 Back
6
C&AG's Report, para 1.4 Back
7
Q 10 Back
8
Qq 5-11 Back
9
Qq 95-97 Back
10
Q 163 Back
11
Qq 80, 81, 99 Back
12
Q 189; Department of Energy & Climate Change written evidence Back
13
Qq 187-188 Back
14
Q 72 Back
15
Q 188 Back
16
C&AG's Report, para 3.11 Back
17
Q 52 Back
18
Q 122 Back
19
Qq 52-57, 163 Back
|