Procuring new trains - Public Accounts Committee Contents


2  Delivering major rail projects more successfully

8. The Department made significant changes to the specifications for the new Intercity Express trains, which delayed the procurement. These problems might have been avoided if the Department had a better understanding of the sector's infrastructure and train needs, and a clearer strategic overview of the rail network.[16] The Department went out to tender before it had decided which Intercity routes the new trains would run on, resulting in it specifying six different routes and then eliminating some. The Department agreed that it should perhaps have been clearer about its plans for electrification of routes before it drew up its initial specifications, rather than considering electrification part way through the procurement process. It also acknowledged that its specified range of between 500 and 2,000 carriages was very broad, and it had in practice assumed that between 500 and 1,000 carriages would be procured.[17]

9. When the Department drew up its original specifications for the Intercity Express programme, the business case for electrification on the Great Western line was weak, so the Department specified that it required self-powered (diesel) trains. When electrification of parts of the line were approved in 2009, the Department had to change its specification as self powered trains were no longer required.[18] Rather than stop and retender the Intercity Express train procurement to reflect these significant changes, the Department pressed on with the procurement with its preferred bidder, Agility Trains. The Department said that before proceeding it had assessed very carefully whether these changes fell within the original boundaries of the procurement. The Department maintained that had there been better value solutions available it would have stopped the procurement. However, the Department concluded that the abortive costs of stopping and then restarting the procurement would have been around £100 million.[19]

10. We asked the Department what the Intercity trains would have cost if it had pursued a standard public procurement rather than a PFI route.[20] The Department told us that it had evaluated this option at the beginning of the procurement and that it had concluded that the PFI approach offered the best value for money. Affordability, not value for money was the key factor in the decision to procure Thameslink trains using PFI, and affordability was also a factor in the decision to use PFI for Intercity Express.[21] The Department said that the Government at the time believed that a PFI-type approach could bring significant benefits in terms of value for money, by creating incentives for the manufacturer and its funders to deliver the trains on time and to the given specification, and to maintain the trains so that they would operate well throughout the life of the contract.[22]

11. The Agility consortium reduced its price by 38 per cent when the Department changed the specification at a late stage. Such a large unsolicited reduction does not inspire confidence that the Department has managed the procurement process well.[23] The Department selected Agility in 2009, but in 2010 the Government put the programme on hold as part of its overall spending review and commissioned a re-evaluation of the programme's value for money, including potential alternatives.[24] The Department suggested that Agility made the reductions as it saw the deal as globally important. However, the Department's admission that it could not have afforded to proceed with the procurement without this reduction did little to reassure us that the price the Department has negotiated is best value for the taxpayer. That Agility was able to offer such a significant reduction raises questions about whether the original tender was inflated.[25] The Foster Review into the value for money of Intercity Express, commissioned by the Secretary of State in March 2010, stated that he was "not convinced that all the potentially viable and possibly preferable alternatives to IEP (Intercity Express programme) have been assessed alongside it, on an equal footing". In September 2010, the Department received a revised proposal from Agility Trains, to provide fewer trains with a revised design at a lower price.[26]

12. The Department admitted that it did not have a credible alternative plan in case its negotiations with Agility stalled. It could have extended the life of the existing rolling stock while it paused to rethink before going through some further form of procurement. We note that the Department considers itself extremely fortunate that Agility revised its bid and offered an unsolicited reduction in price.[27]

13. There was a lack of continuity on these two projects, with 7 changes of senior staff leading the projects in 7 years. The Department said that it would have welcomed more continuity, particularly on the Intercity Express procurement. It is worrying that on major projects like these, the Department does not have consistent personnel in charge.[28]

14. The Department has a shortage of suitably qualified and experienced staff and is still reliant on contractors and interims. It has a programme in hand to recruit more permanent staff and reduce its reliance on contractors, although it foresaw that it would always have a need for contractors and interims to help it manage peaks in its workload. It has launched a commercial fast track programme, for example, to hire in young talented people who are interested in developing commercial skills.[29]

15. Hitachi will be assembling the Intercity Express trains in the UK, but Siemens will not be doing so with the Thameslink trains. We asked the Department what attempts it had made to insist on a proportion of the manufacture of the trains being carried out in the UK. The Department told us that its focus with these procurements was on getting the lowest price and value for money, and that having obligations for trains to be manufactured in the UK would have breached European law. The Department also told us that it tries to help the UK rail supply base to develop, but that this objective is treated as separate from its procurements.[30]


16   C&AG's Report, para 8 Back

17   Q 93 Back

18   C&AG's Report, paragraph 2.3, Q 93 Back

19   Qq 69, 70, 71 Back

20   Q 32 Back

21   Qq 33, 34 Back

22   Q 34 Back

23   Q 74 Back

24   C&AG's Report, para 2.13 Back

25   Qq 73, 75, 76, 78 Back

26   C&AG's Report, para 11 Back

27   Qq 77, 78, 80 Back

28   Qq 1, 3, 4 Back

29   Q 94 Back

30   Qq 36-37 and 44 Back


 
previous page contents next page


© Parliamentary copyright 2014
Prepared 17 December 2014