Lessons from major rail infrastructure programmes - Public Accounts Committee Contents


2  Delivering value for money

8. Several of the Department's past projects have taken longer than was originally planned, partly in order to control costs. For example some major work on the West Coast Mainline modernisation programme was delayed by 18 months, and phase two of the Thameslink programme was extended by three years.[11]

9. The Department acknowledged that good planning and preparation determine success on major programmes, and told us that this is its current focus on High Speed 2. The Department expects that Royal Assent on the Hybrid Bill for phase one of the programme will now be achieved by December 2016. At the time of our September 2013 report High Speed 2: a review of early programme preparation, the Department was aiming to achieve this by March 2015. According to the Department, the revised timescale will allow it to get the planning right, and it still expects to begin construction in 2017 and complete phase one by 2026.[12]

10. The Department told us that it is important that HS2 Limited takes the time to get the planning right and does not rush towards the procurement and construction phase. It told us that it is taking steps to bring forward some activities that would normally take place once Royal Assent has been achieved to help get the programme ready for construction. For example, the Department and HS2 Limited are putting in place legal agreements now, which will set out the respective roles of the two organisations and establish the basis for how the Department will hold HS2 Limited to account. In addition, HS2 Limited has appointed a Chief Executive in charge of construction and is recruiting people for the construction phase of the programme. The Department explained it is taking these steps at an earlier stage than it did on Crossrail.[13]

11. The Department told us that it is confident that it will deliver phase one of High Speed 2 within its available funding of £21.4 billion and that it will complete the whole of High Speed 2, including buying the trains, within the overall funding envelope of £50 billion set by the Chancellor. £21.4 billion includes the generous contingency of £4-5 billion and we are concerned that the contingency has been pre-empted before construction has even started. The Department also acknowledged that there is currently less certainty about the costs on phase two. In addition, High Speed 2 is a highly complex programme, but the Department told us it is confident that it has taken account of challenges, such as the risk of flooding on the water courses that the route passes through.[14]

12. The Department's budget for High Speed 2 has a generous contingency, which the Department told us is based on an assessment and quantification of risks to the programme. This includes provision for likely inflation which is based on the Treasury's guidance on the rates to apply. However, construction costs can increase more quickly than general inflation. When the National Audit Office reported on High Speed 2 in 2013, the Department estimated that phase one would cost between £15.4 billion and £17.3 billion.

13. The Department has now revised the budget for phase one and considers that it is 95% likely that it will deliver phase one within the allocated £21.4 billion of funding. The earlier cost estimates were set with a 50% likelihood that the programme would be delivered within the available funding. To achieve this increased confidence, the Department increased the required contingency provision by between £4 billion and £5 billion. The Department told us that it is not assuming that it will spend all its contingency, but that it has already spent some on, for example, concessions made to petitioners to the Hybrid Bill.[15]

14. We have seen academic research by the Omega Centre for Mega Projects in Transport and Development—part of University College London—which suggested that the cost of delivering a kilometre of railway varies significantly from country to country. The research stated that the cost per kilometre of the Channel Tunnel Rail Link was much higher than the Valence-Marseille line in France and the Köln-Rhein line in Germany. The Department told us that it is interested in learning from construction techniques that are used overseas to reduce costs, and it cited examples from France such as the laying of tarmac along the route of the new railway to make it easy for lorries to bring supplies to build the next section of railway.[16]

15. In addition to funding from the general taxpayer, the Department and Transport for London used various means, including a supplement to business rates in London, to help pay for Crossrail. However, the Department told us that the benefits from Crossrail are concentrated in London, and that a rate supplement to reduce the burden on the general taxpayer would not be appropriate for High Speed 2, because the benefits are spread very widely. However, economic benefits, from which businesses will presumably benefit, remain central to the rationale for High Speed 2. The Department did accept that there may be potential to raise some private finance for some elements of the programme such as development around stations.[17]

16. Economic benefits and regeneration have been central to the objectives of a number of the programmes we have looked at before; High Speed 1, Crossrail and High Speed 2 in particular. Seven years after High Speed 1 was completed there has been good progress in regenerating areas around King's Cross and Stratford. The Department conceded that there had been insufficient planning for benefits from High Speed 1 Ebbsfleet in Kent, which was one of the main areas where substantial benefits were expected. It also acknowledged that there had been very little progress in Ebbsfleet and that it would have liked to have seen regeneration there much earlier.[18] The Department told us that the government is now putting in place an urban development corporation at Ebbsfleet, and there is also a mayoral development corporation planned for Old Oak Common, which is on the Crossrail route.[19]

17. The Department has accepted 18 of the 19 recommendations of Lord Deighton's Growth Task Force for High Speed 2, which emphasised the need for a more active approach to make sure that regeneration happens. The Department is currently considering how to take these recommendations forward.[20] The Department sees it as the role of local authorities to use their existing powers and budgets to plan for development around proposed High Speed 2 stations. However, it also told us that it is looking into establishing an organisation to work with local areas on, for example, land assembly and specialist planning around the stations to drive the regeneration. So far, however, on a £50 billion programme, the Department has earmarked only £2.5 million of funding to support local areas. This funding will go to Birmingham and Solihull to help them plan for development around stations.[21]


11   C&AG's report, para 4.3 Back

12   Q 3; Committee of Public Accounts, High Speed 2: a review of early progress, Session 2013-14, HC478, 9 September 2013  Back

13   Qq 41-49 Back

14   Qq 54, 62-66 Back

15   Qq 50-72; Committee of Public Accounts, High Speed 2: a review of early progress, Session 2013-14, HC478, 9 September 2013, paragraph 13 and Q 40 Back

16   Qq 69, 157-160; http://www.omegacentre.bartlett.ucl.ac.uk/studies/cases/hsr-ctrl_2.php  Back

17   Qq 145-151 Back

18   Qq 73-4, 84, 146; C&AG's report, figure 2 Back

19   Q 83 Back

20   Q 74 Back

21   Qq 79-81, 73-74 Back


 
previous page contents next page


© Parliamentary copyright 2015
Prepared 16 January 2015