The cancellation of rail electrification in South Wales Contents

Annex: Work recommended

Action

Timescale

Responsible bodies

Review enhancements pipeline approach

12 months

Department for Transport, Network Rail

Monitor emissions from bi-mode trains on Cardiff-Swansea route

Every six months

Department for Transport, Network Rail

Develop plan for further reduction in emissions from bi-mode trains

12 months

Department for Transport, Network Rail (in consultation with Hitachi Rail Europe)

Produce plan for closer engagement with Welsh Government

Two months (in response to our report)

Department for Transport

Revise route study for Welsh railways

12 months

Department for Transport, Welsh Government, Network Rail

Study viability of straightening the track between Cardiff and Swansea

End of 2018

Department for Transport, Network Rail, Welsh Government

Working group exploring Swansea Bay Metro proposal

End of 2018

Department for Transport, Welsh Government, Network Rail

Assess, and report back to us on, the feasibility of devolving responsibility for rail infrastructure to the National Assembly for Wales

Six months

UK Government

Initial work to consider future options for new technologies

12 months (as part of route study process)

Department for Transport, Welsh Government, Network Rail





Published: 21 May 2018