Resetting government programmes

This is a House of Commons Committee report, with recommendations to government. The Government has two months to respond.

Seventy-First Report of Session 2022–23

Author: Committee of Public Accounts

Related inquiry: Resetting government programmes

Date Published: 15 September 2023

Download and Share

Contents

Introduction

Government expects to spend hundreds of billions of pounds across its largest, most innovative and riskiest major programmes, such as those to build railways, schools and IT systems and transform public services. Programmes can take years and changes in the external environment can create new challenges, meaning a programme may no-longer achieve its intended outcomes or it becomes too costly to do so. When this happens, a programme may need to be reset to increase the likelihood of outcomes being achieved.

Resets, which vary from a fundamental change to what is delivered to a significant revision of cost and time estimates, can be significant and risky. A programme reset can be a positive step, even if it means government bodies have spent money that will be wasted, since it provides an opportunity to reflect and rebalance a programme and prevent further waste. However, resets can be challenging and do not always work. The Infrastructure and Projects Authority (IPA), government’s centre of expertise for infrastructure and major projects, leads the project delivery function, reporting to the Cabinet Office and HM Treasury. This includes being responsible for improving project delivery by setting frameworks for delivery, undertaking assurance, and providing support.

Conclusions and recommendations

1. A lack of guidance and structure around programme resets means they are not always identified so a failing programme does not get back on track. Government does not have a standard definition for resets, with no specific guidance available. This creates confusion as to what constitutes a reset alongside challenges identifying, and therefore learning lessons from, reset experiences. For example, the number of resets relating to the Ajax programme remains unclear, but is at least two and probably three. Also, without a definition, and therefore recognition of their value, resets are often viewed negatively, which can create challenges for the programme team. We were pleased that the IPA said it would look to codify guidance and that HM Treasury suggested revisiting its approvals process and guidance. While programme teams may be best placed to identify triggers for a reset, the IPA and SROs told us the IPA assurance process can act as a robust trigger for resets. We have previously recommended the IPA makes more effective use of its insights across programmes.

Recommendation 1:

a) By June 2024 HM Treasury and the Infrastructure and Projects Authority should set out for government a common programme reset definition and how their roles and responsibilities fit alongside those of departments and Ministers to identify and manage resets.

b) Alongside this, they should provide departments with clarification on how existing processes (such as for funding approvals and assurance) and good practice apply to programme resets, filling in any gaps in guidance.

2. Resets could have been avoided with more realistic upfront planning and scoping, including to better reflect the backdrop against which government programmes operate. This is a critically important part of the inception of any project. We heard that there has been a tendency across Government to re-baseline major projects1, particularly in the Ministry of Defence. The baseline should be agreed at Full Business Case and any scope change should be negotiated with the Treasury. We continually see poor planning as a deep-rooted problem across programmes, which can lead to resets. We would hope to see fewer programmes needing to be reset in the future as the IPA strengthens its assurance regime and its focus on setting up programmes for success. Although some resets are avoidable, for example through investing in up-front planning, other resets will be harder to avoid given the long delivery horizon and complex nature of major programmes. Resets may be a natural consequence for long-term programmes because of macro changes in the economy, technology sector or across society. Political factors, such as changes in ministers or the government composition, may also impact programmes. We heard how Universal Credit had been overseen by around nine secretaries of state since the current Senior Responsible Owner started his role in 2014.

Recommendation 2:

a) Alongside the Treasury Minute response to this report, the IPA should share with us how it is embedding its good practice guidance on upfront planning and scoping, and the changes (with timeframes) it expects to see as a result. This should include providing the Committee with confirmation on how it is using its assurance regime to ensure that programmes do not pass major milestones without having followed planning good practice. The Senior Responsible Owner should produce a reconciliation statement comparing the milestones to what has actually happened on the project.

b) By June 2024 HM Treasury and IPA should develop guidance (or similar) to support programme teams to realistically reflect the uncertainties of the environment within which they operate in their programme assumptions and estimates to help reduced the likelihood of significant changes.

3. Not having the right environment to encourage diverse views, transparency and constructive challenge has created problems in identifying and managing resets. A transparent and honest culture helps create an environment which supports constructive challenge and open conversations. This will encourage risks and issues, such as the potential need for a reset, to be discussed early with a full consideration of options, including if a programme should be stopped. We have seen programmes, such as Crossrail, when there has not been sufficient candour, for example on the civil contact, and as a result resets being undertaken later than needed. Having a diverse range of individuals, such as non-executive directors, to provide views contributes to creating an effective environment and leads to better decision-making. There is more progress to be made in improving diversity amongst those in central government as well as across the programme profession.

Recommendation 3: The Infrastructure and Projects Authority should encourage and support departments in developing an environment of openness and transparency across programmes. Alongside the Treasury Minute response to this report, it should write to the Committee setting out how it plans to do this and monitor skills across all aspects of the profession against targets. This should include its pool of assessors, non-executives and practitioners.

4. On too many occasions, programmes have suffered from resets being done too quickly. The time needed to undertake a successful reset will vary case-by-case, influenced by factors such as the programme complexity and breadth of the reset. Resets of government programmes have on occasion taken less than three months and sometimes more than a year. Teams can underestimate how much time a reset can take. There can be pressures to complete resets quickly, with teams not being given the space and time to think about the next steps; if a reset is being undertaken it must be done properly, otherwise it simply increases the risk of further resets.

Recommendation 4: By June 2024, HM Treasury and the Infrastructure and Projects Authority should have drawn together and shared with the profession its insights on the factors influencing the time needed to undertake a reset and encourage programme teams to be realistic on the time they need. In doing this they should review their own processes to ensure they do not introduce milestones that incentivise rushed resets.

5. Broader programme-related good practice, such as having the skills, leadership and governance relevant to the programme stage, has not always been applied. Government departments do not always have the specific skills needed to undertake a reset. This includes not always having the right leadership with an appropriate SRO, the importance of which we have regularly highlighted, to oversee the reset or future programme. Although we are told there has been less churn of SROs than there used to be, civil service pay and promotion constraints can impact an SROs incentive to stay in post and provide continuity if needed. The IPA recognises governance as an area where it needs to sharpen its focus.

Recommendation 5: The Infrastructure and Projects Authority should set out its progress, and the actions it has and is taking, to:

  • ensure programme SROs have the required skills and stay in post the expected length of time. More widely, Cabinet Office and HM Treasury should work with departments to ensure they use any available levers where it is best to incentivise continuity of leadership.
  • accredit programme professionals across individual departments.

6. Resetting programmes can create new risks that are not always effectively managed. A programme reset is much more than the routine change management expected within any large programme. To help address the root causes of any underlying issues, a reset will necessarily significantly change what or how a programme delivers. This will introduce new risks and opportunities that need to be identified and managed such as creating new commercial relationships or changing existing ones if necessary by contractual changes. In not recognising these challenges, on its Ajax programme, the Ministry of Defence had to undertake a further reset. It is vital that departments fully appreciate the new risk landscape.

Recommendation 6: The Infrastructure and Projects Authority should encourage and support departments to understand the full risks when resetting a programme. Alongside the Treasury Minute response to this report, the IPA should write to us setting out how it is considering this as part of its ongoing assurance and review of major programmes.

1 Recognising a reset

1. On the basis of a report by the Comptroller and Auditor General, we took evidence from HM Treasury and the Infrastructure and Projects Authority (IPA) about resetting major programmes.2 We also took evidence from four senior responsible owners (SROs): Matthew Lodge, Government SRO for Crossrail, Department for Transport; Neil Couling, SRO for Universal Credit, Department for Work & Pensions; Dr David Marsh, SRO for the Ajax programme, Ministry of Defence; and Jim Barton, SRO for the Electronic Monitoring programme, Ministry of Justice.

2. As at March 2022, government expected to spend £678 billion across its 235 largest, most innovative and riskiest programmes. This was the most recent published data at the time we took evidence in June 2023. This includes strategically significant programmes to build railways, schools and IT systems and transform public services. Many of these programmes are complex and we often see government bodies needing to improve how they are managed, particularly in their early stages. As these programmes often take years, changes in the external environment, such as movements in inflation rates, may affect the programme and create further complexities. These factors, whether internal or external, may mean a programme can no longer achieve its intended outcomes, or it is too costly to do so. In these cases, a programme reset may be needed.3

3. A reset can be defined as a “fundamental or substantial change to what a programme will achieve, or how it is delivered, that cannot be managed through routine change control procedures.” For example, in 2018, the Ministry of Defence renegotiated its Ajax programme contract with its supplier for the design and manufacture of 589 armoured fighting vehicles. While the reset did not change the requirement to deliver 589 vehicles or contract price, it revised milestones and the vehicle technical specifications.4

4. A programme reset can be a positive step, even if it means government bodies have spent money that will be wasted, since it provides an opportunity to refocus a programme. However, resets can be challenging and do not always work, with some programmes being reset more than once. Over time, we have seen many programmes start and then be reset for various reasons which have created challenges securing value for money for the taxpayer.5

5. The IPA is the government’s centre of expertise for infrastructure and major projects. It leads government’s project delivery function, reporting to the Cabinet Office and HM Treasury. The IPA and HM Treasury decide which programmes join the Government Major Project Portfolio (GMPP), which the IPA oversees by supporting projects with expert advice, support and assurance. The IPA is also responsible for improving project delivery across government by setting the delivery framework, standards and assurance arrangements; providing support where necessary; and building professional capability, including that of Senior Responsible Owners (SROs).6

Guidance on resetting

6. Government does not have a standard definition for a reset.7 The SRO for Universal Credit told us that its 2013 reset was probably the first-time government had tried to reset a programme. Without a guide or map, nobody quite knew where they were going with resetting the programme.8 Even now, the HM Treasury process for approving programmes does not explicitly set out what a reset is, or what needs to be considered or happen during a reset.9 The SROs we spoke to, alongside the IPA and HM Treasury, saw value in codifying more the insights shared through the C&AG’s report to better handle resets.10 The IPA told us that it can do more to embed the principles of the C&AG’s report into its processes and procedures, although their processes only apply to larger programmes.11 The IPA suggested that tools used to set-up projects could be used for resets.12 Also, IPA and HM Treasury agreed that there could be greater clarity around what is meant by a significant change and when HM Treasury approval would be required for a reset.13 For example, on Ajax, the most recent reset has gone through a full reapproval with the investment committees and HM Treasury which was not the case for the preceding reset.14

7. As government does not have a standard definition for a reset, government bodies may not recognise when a reset is required, being carried out, or has been completed.15 There was some confusion over what was termed a reset. The SRO for Universal Credit suggested he had probably reset the programme several times but not used the term. Also, there were questions raised over the number of resets undertaken for the Ajax programme and whether the 2014 decision to move production to the UK should be counted alongside two later resets which firstly recast the commercial agreement and then sought to address quality and delivery schedule challenges.16 Not clearly defining a reset, will make it harder for government to identify lessons that can be carried over into the same or other programmes and situations.17

8. SROs described how it would be helpful if resets were seen more positively, which HM Treasury suggested government was moving towards.18 They also commented that resets can be seen as a failure and can be a traumatic event for programme staff, after which the confidence of the team would need to be rebuilt.19 Negative perceptions could mean government bodies continue trying to resolve unresolvable issues and lead to wasted effort and costs.20 The SRO for electronic monitoring commented that “sometimes, the easier path is to simply carry on doing the same thing, but it is negligent if, as an SRO, you do not call it.”21 He spoke about how the IPA confirming a ‘red’ delivery confidence status helped validate their own assessments and made it easier to have conversations about a more fundamental reset. It took the Ministry of Justice nine months from starting to think about a reset to confirming the decision.22 The IPA recognised how its response to red programme could provide a trigger if the Department or the project team did not realise the need for a reset.23 It told us it was now in a better place to discuss with departments when things can no-longer be achieved and what should be done about it.24

9. Although those deciding on a reset, such as the SRO or programme board, need to be aware of what may trigger a reset we consistently heard how the IPA and central government bodies, could help identify or build the case for significant change.25 The IPA told us how, quite often, although programmes would ideally identify the need to change, those involved would not necessarily see the issues without independent analysis and data.26 We have previously recommended, in our report on improving the accounting officer assessment process, how HMT and IPA should use their information to understand programmes specific risks and wider issues.27

Addressing the factors behind a reset

10. Various factors, both internal and external to a programme, can contribute to the need for a reset.28 We heard how this can include the programme going off track, the need to improve confidence in supplier delivery, or to resolve technical problems and set a realistic schedule.29 Factors can result from deep-rooted issues caused by poor programme planning, the importance of which we have been stressing for some time.30 The IPA told us it is trying to encourage practitioners to set up projects well given they are much harder to fix in-flight. It described how it has a several tools to help with project set-ups, and therefore reduce resets, and that it was working to equip SROs and project directors to have the right skills and knowledge at the start of a programme.31 The SRO for Ajax commented favourably on the IPAs range of products.32

11. The IPA suggested that its assurance work has become much more rigorous – it has republished the assurance workbooks it uses to undertake reviews; refreshed its pool of available independent reviewers; and started to provide them with training.33 For the 100 programmes it has the capacity to support, the IPA told us it gets more deeply involved as early as it can to help avoid issues that can lead to a programme failing later. As part of this it will look at, for example, whether there is a robust schedule, a stakeholder alignment plan, and a robust cost estimate.34

12. Although some resets could be avoided, the IPA suggested there may be occasions where multiple resets are necessary, particularly for long-term programmes.35 External factors, including financial pressures, political changes, technology developments or events such as the COVID-19 pandemic, can lead to a reset.36 At present, those programmes in construction are being particularly impacted by inflation.37 The SRO for Universal Credit felt resets were a natural result of major long-term projects. He highlighted how the United Kingdom leaving the European Union, devolution of benefits to Scotland, the COVID-19 pandemic and ongoing cost-of-living challenges had all impacted the programme.38 He also mentioned how, although there had been one Secretary of State for six years, he is now on his ninth Secretary of State since he started as SRO in 2014.39 He felt it was impossible to ‘freeze politics’, which became more of a challenge for projects extending beyond a parliamentary term.40

Creating the right environment

13. Without the right environment, individuals may be afraid to report problems in a timely and honest way, which makes it harder to identify the need for a reset and the issues a reset should address.41 We heard from the SRO for Universal Credit that creating this openness was the hardest, but most important, thing to achieve in projects.42 Also, the SRO for Crossrail spoke about how the programme started to believe its own ‘on-time, on-budget’ mantra which stopped many people raising issues.43 He also felt that, in hindsight, the governance structures did not provide the Department for Transport, as sponsor, enough transparency over potential issues.44 The SRO for electronic monitoring described a positive experience with the relevant Minister who had a firm belief in the role of electronic monitoring. He created a space and appetite for candid conversations about the programme challenges and how they could be resolved.45 From a Ministry of Defence perspective, the SRO for Ajax mentioned the additional cultural challenge of being an integrated military and civilian organisation and acknowledged that, for Ajax, it was very difficult for individuals to continually have the confidence to speak up. He explained how the MoD was working hard on this and recently commissioned a report on psychological safety in major programmes.46

14. We asked SROs about the diversity of their programme boards, which could help establish an effective, open and constructive environment. For Universal Credit, the SRO explained how, over time, the Board had included women and men in almost equal number fulfilling different roles, alongside representatives from HM Treasury, the IPA and a local authority. For electronic monitoring, the SRO described the Programme Board as representative of HM Prison & Probation Service but recognised that this did not equate to being representative of society at large.47 We also asked the IPA and HM Treasury about diversity within their respective organisations. IPA said it has quite a diverse team, both in terms of cognitive diversity and background. HM Treasury agreed that it is similarly diverse in terms of background although officials tended to have a more policy experience. HM Treasury set out that across its public spending work, around 50%, or maybe even more, were female. We commented, however, that there still seemed to be some way to go on ethnic diversity.48

15. We were interested to hear about the role of non-executive directors in creating an environment supportive of challenge and diverse thinking. The SRO for Universal Credit explained how it was useful having a non-executive director chairing the Programme Board.49 The SRO for Ajax spoke about how he has reset the Board to expand the number of voices around the table, trying to bring-in more diversity and non-advocate challenge. For electronic monitoring the SRO told us that, when they were discussing a potential reset, they had strengthened the independent voice with a non-executive challenge panel outside formal governance arrangements. This provided a space for ‘incredibly robust challenge’ of the programme.50 The IPA felt it could do more to explore whether departments bringing in appropriate external director skills.51

16. It is important to have open and honest conversations on how to progress a programme, including whether a reset is the right solution.52 Where a government body identifies a programme is at risk of not achieving its intended outcomes, it should consider a range of options to address this. This should include whether the programme should be stopped, with costs potentially written off.53 HM Treasury emphasised that it is really important programme teams consider stopping a programme, and starting again, rather than just continuing on the previous course.54 The SRO for electronic monitoring described how, following an IPA review in March 2021, they suspended developing the system which gave them three months’ breathing space to work through whether it was right to carry on with the work or to stop. HM Prison & Probation Service decided to terminate an aspect of its contract with Capita and stopped development of the Gemini case management system.55 On the most recent reset for the Ajax programme we were told that the Ministry of Defence looked at various options, including stopping the programme.56

2 Undertaking a reset

Allowing time for a reset

17. The time needed to undertake a reset will vary. Across 24 resets, the NAO found that the time spent ranged from less than three months to more than a year. Various factors contribute to the time needed for a reset such as the complexity of the programme and reset; the need to understand the underlying issues and potential opportunities; involving (and potentially rebuilding) a supply chain; engaging stakeholders, including contractors, so they remain supportive; and seeking programme approvals.57 The SRO for Crossrail described how time may be needed to work through commercial issues. On Crossrail the project team spent time re-establishing contracts and creating the right incentives to get the railway open.58 Political involvement can also mean extra time is needed for a reset. The Ajax SRO told us that over the last 18 months, the programme had benefited from very strong hands-on ministerial involvement, with his biggest lesson being that this created decision-making processes that should be planned for.59 The SROs identified how changing ministers could create additional work for programme teams.60

18. The SROs highlighted to us the need to take appropriate time to ‘do the job properly’. For the Ajax programme, the NAO found the Ministry of Defence had underestimated how long a reset would take. It expected to conclude negotiations to reset the contract in October 2017, but these took 15 months instead of two, with the legally binding agreement signed in December 2018. We heard from SROs how there is an understandable desire, and sometimes political pressure, to finish a reset as soon as possible.61

19. The C&AG’s report identified value in creating ‘space’ to reset a programme. To do this teams might generate or capitalise on opportunities to pause a programme (rather than resetting ‘in flight’); establish a dedicated reset team to focus on resetting; or not publicise details of a reset until it has been fully developed given how this could affect some stakeholders’ confidence in the programme.62 The SRO for Crossrail reflected that one of the challenges faced in undertaking a reset was the reset team retaining responsibility for the project at the same time.63 During a later reset on Crossrail, the COVID-19 pandemic forced a pause to work which allowed the team time to replan.64

Building the skills, leadership and governance

20. Governance arrangements need to evolve throughout a programme lifecycle to reflect the risks and requirements at each stage. This includes both during and after a reset, so governance and approvals processes remain proportionate to the programme risks with skills, expertise and leadership brought in as required.65 The SRO for Crossrail told us how, when they reset the project in 2018, they worked to bring sponsors, such as DfT and TfL, closer to the Crossrail board to create better conversations and share information. He reflected on whether they got the governance structure right, with the Department for Transport currently undertaking an exercise to identify lessons for project governance which they hope to publish in the summer.66 The IPA told us that it needs to sharpen its focus in the governance area.67

21. Given a reset may involve different activities, or a different focus, to how the programme was being managed it may require specific skills and expertise such as around planning, negotiation, political engagement, or stakeholder management.68 As such, the skills and leadership for long-term major programmes, may need to change to reflect the stage of the programme.69 The SRO for Crossrail reflected on the importance of bringing in the right people with the right skills, even when things may look to be progressing well. Very different skills were needed at the end of the programme to the start.70 The SRO for Universal Credit spoke about considering carefully the value of a dedicated reset team, giving leadership back to the programme as soon as possible, and whether the current SRO should do the reset.71 A dedicated reset team could bring in the necessary skills and help step back from the programme.72 On Universal Credit, the head of the then Major Projects Authority (now incorporated into the Infrastructure and Projects Authority) headed up the first reset.73 The IPA spoke about more recently being deeply involved in providing expertise and short-term resources to some programmes, including for the Ajax programme.74

22. As with a programme, those leading a reset, such as the SRO, need to have a clear vision shared with stakeholders alongside the skills and experience to critically examine a programme, motivate staff and contractors, and deal with external pressure.75 This was particularly important for resets as the SRO would need to help maintain focus on the decisions needed despite the likely heavy demands for information from those overseeing the programme.76 While SROs felt that continuity of SROs was a good thing, they stressed that it was important to have the right leader for the right moment.77 Although recognising a reset may lead to a change in SRO, we have previously commented on SROs moving off programmes too quickly.78 We were informed that the situation is improving, although heard about the challenges in encouraging SROs to stay in their role given a lack of pay incentives and the inflexibility of promotions meaning they potentially give up career opportunities.79 In terms of incentivising a continuity in SROs, the IPA told us it can now administer dedicated allowances in certain circumstances and, with minister support can agree specific milestones for SROs to stay in position.80 It also felt that an SRO, or a programme director plays a critical role in building the right team around them, particularly in terms of having the digital skills required.81

Impact of resets on programme risks

23. As a reset is a fundamental or substantial change to what a programme will achieve, or how it is delivered, it cannot be managed through routine change control procedures.82 We heard from the SRO for Ajax that when undertaking resets, it was important to understand the root causes of issues rather than just the symptoms. The IPA and HM Treasury reiterated the importance of this in helping to get resets right and avoid further unnecessary resets.83 Understanding the causes will also make it easier for programmes to set out the reset aims and focus efforts, as well as establish clear measures to assess if the reset is realistic and monitor its success.84

24. In focusing on the underlying issues, and as a reset significantly changes what or how a programme delivers, it introduces new risks and opportunities that need to be identified and managed.85 The SRO for Ajax told us how the 2018 programme reset aimed to protect the delivery date, but this introduced new risks impacting the scheduling and has meant the programme has had to be reset again.86 He described a core lesson being the need to fundamentally reassess the risk profile and landscape when making significant programme changes, which had not been fully done on Ajax.87 The SRO for Universal Credit also spoke about managing risks, and trade-offs with the timetable.88

25. The risk profile of a programme may shift with changes to the commercial approach or how this is managed during a reset. For a reset, the government body will need to consider what existing arrangements with delivery partners mean for how to undertake a reset and what it could achieve.89 Programme teams need to work with suppliers and delivery partners to establish an effective relationship for the reset and beyond.90 The SRO for electronic monitoring mentioned the role of the Government Commercial Function. It was very helpful to them as they were working through how to reset their commercial relationship with a provider who was a strategic government supplier.91 We were told that their relationship with the supplier has improved post settlement.92 The SRO for Universal Credit raised the importance of time to have discussions with suppliers to create a win-win situation.93

Formal minutes

Thursday 7 September 2023

Members present:

Dame Meg Hillier

Olivia Blake

Ben Lake

Sir Geoffrey Clifton-Brown

Mr Mark Francois

Anne Marie Morris

Resetting government programmes

Draft Report (Resetting government programmes) proposed by the Chair, brought up and read

Ordered, That the draft Report be read a second time, paragraph by paragraph.

Paragraphs 1 to 25 read and agreed to.

Summary agreed to.

Introduction agreed to.

Conclusions and recommendations agreed to.

Resolved, That the Report be the seventy-first of the Committee to the House.

Ordered, That the Chair make the Report to the House.

Ordered, That embargoed copies of the Report be made available, in accordance with the provisions of Standing Order No. 134.

Adjournment

Adjourned till Monday 11 September at 3pm.


Witnesses

The following witnesses gave evidence. Transcripts can be viewed on the inquiry publications page of the Committee’s website.

Monday 5 June 2023

Matthew Lodge, Government Senior Responsible Owner for Crossrail, Department for Transport; Neil Couling CBE, Change Director General Senior Responsible Owner for Universal Credit (SRO), Department for Work and Pensions; Jim Barton, Director Electronic Monitoring Programme, Ministry of Justice; Dr David Marsh, Senior Responsible Owner for Ajax, Ministry of DefenceQ1–101

Nick Smallwood, Chief Executive, Infrastructure and Projects Authority (IPA); Conrad Smewing, Director General of Public Spending, HM TreasuryQ102–169


Published written evidence

The following written evidence was received and can be viewed on the inquiry publications page of the Committee’s website.

RGP numbers are generated by the evidence processing system and so may not be complete.

1 Association for Project Management (RGP0001)


List of Reports from the Committee during the current Parliament

All publications from the Committee are available on the publications page of the Committee’s website.

Session 2022–23

Number

Title

Reference

1st

Department for Business, Energy & Industrial Strategy Annual Report and Accounts 2020–21

HC 59

2nd

Lessons from implementing IR35 reforms

HC 60

3rd

The future of the Advanced Gas-cooled Reactors

HC 118

4th

Use of evaluation and modelling in government

HC 254

5th

Local economic growth

HC 252

6th

Department of Health and Social Care 2020–21 Annual Report and Accounts

HC 253

7th

Armoured Vehicles: the Ajax programme

HC 259

8th

Financial sustainability of the higher education sector in England

HC 257

9th

Child Maintenance

HC 255

10th

Restoration and Renewal of Parliament

HC 49

11th

The rollout of the COVID-19 vaccine programme in England

HC 258

12th

Management of PPE contracts

HC 260

13th

Secure training centres and secure schools

HC 30

14th

Investigation into the British Steel Pension Scheme

HC 251

15th

The Police Uplift Programme

HC 261

16th

Managing cross-border travel during the COVID-19 pandemic

HC 29

17th

Government’s contracts with Randox Laboratories Ltd

HC 28

18th

Government actions to combat waste crime

HC 33

19th

Regulating after EU Exit

HC 32

20th

Whole of Government Accounts 2019–20

HC 31

21st

Transforming electronic monitoring services

HC 34

22nd

Tackling local air quality breaches

HC 37

23rd

Measuring and reporting public sector greenhouse gas emissions

HC 39

24th

Redevelopment of Defra’s animal health infrastructure

HC 42

25th

Regulation of energy suppliers

HC 41

26th

The Department for Work and Pensions’ Accounts 2021–22 – Fraud and error in the benefits system

HC 44

27th

Evaluating innovation projects in children’s social care

HC 38

28th

Improving the Accounting Officer Assessment process

HC 43

29th

The Affordable Homes Programme since 2015

HC 684

30th

Developing workforce skills for a strong economy

HC 685

31st

Managing central government property

HC 48

32nd

Grassroots participation in sport and physical activity

HC 46

33rd

HMRC performance in 2021–22

HC 686

34th

The Creation of the UK Infrastructure Bank

HC 45

35th

Introducing Integrated Care Systems

HC 47

36th

The Defence digital strategy

HC 727

37th

Support for vulnerable adolescents

HC 730

38th

Managing NHS backlogs and waiting times in England

HC 729

39th

Excess Votes 2021–22

HC 1132

40th

COVID employment support schemes

HC 810

41st

Driving licence backlogs at the DVLA

HC 735

42nd

The Restart Scheme for long-term unemployed people

HC 733

43rd

Progress combatting fraud

HC 40

44th

The Digital Services Tax

HC 732

45th

Department for Business, Energy & Industrial Strategy Annual Report and Accounts 2021–22

HC 1254

46th

BBC Digital

HC 736

47th

Investigation into the UK Passport Office

HC 738

48th

MoD Equipment Plan 2022–2032

HC 731

49th

Managing tax compliance following the pandemic

HC 739

50th

Government Shared Services

HC 734

51st

Tackling Defra’s ageing digital services

HC 737

52nd

Restoration & Renewal of the Palace of Westminster – 2023 Recall

HC 1021

53rd

The performance of UK Security Vetting

HC 994

54th

Alcohol treatment services

HC 1001

55th

Education recovery in schools in England

HC 998

56th

Supporting investment into the UK

HC 996

57th

AEA Technology Pension Case

HC 1005

58th

Energy bills support

HC 1074

59th

Decarbonising the power sector

HC 1003

60th

Timeliness of local auditor reporting

HC 995

61st

Progress on the courts and tribunals reform programme

HC 1002

62nd

Department of Health and Social Care 2021–22 Annual Report and Accounts

HC 997

63rd

HS2 Euston

HC 1004

64th

The Emergency Services Network

HC 1006

65th

Progress in improving NHS mental health services

HC 1000

66th

PPE Medpro: awarding of contracts during the pandemic

HC 1590

67th

Child Trust Funds

HC 1231

68th

Local authority administered COVID support schemes in England

HC 1234

69th

Tackling fraud and corruption against government

HC 1230

70th

Digital transformation in government: addressing the barriers to efficiency

HC 1229

1st Special Report

Sixth Annual Report of the Chair of the Committee of Public Accounts

HC 50

2nd Special Report

Seventh Annual Report of the Chair of the Committee of Public Accounts

HC 1055

Session 2021–22

Number

Title

Reference

1st

Low emission cars

HC 186

2nd

BBC strategic financial management

HC 187

3rd

COVID-19: Support for children’s education

HC 240

4th

COVID-19: Local government finance

HC 239

5th

COVID-19: Government Support for Charities

HC 250

6th

Public Sector Pensions

HC 289

7th

Adult Social Care Markets

HC 252

8th

COVID 19: Culture Recovery Fund

HC 340

9th

Fraud and Error

HC 253

10th

Overview of the English rail system

HC 170

11th

Local auditor reporting on local government in England

HC 171

12th

COVID 19: Cost Tracker Update

HC 173

13th

Initial lessons from the government’s response to the COVID-19 pandemic

HC 175

14th

Windrush Compensation Scheme

HC 174

15th

DWP Employment support

HC 177

16th

Principles of effective regulation

HC 176

17th

High Speed 2: Progress at Summer 2021

HC 329

18th

Government’s delivery through arm’s-length bodies

HC 181

19th

Protecting consumers from unsafe products

HC 180

20th

Optimising the defence estate

HC 179

21st

School Funding

HC 183

22nd

Improving the performance of major defence equipment contracts

HC 185

23rd

Test and Trace update

HC 182

24th

Crossrail: A progress update

HC 184

25th

The Department for Work and Pensions’ Accounts 2020–21 – Fraud and error in the benefits system

HC 633

26th

Lessons from Greensill Capital: accreditation to business support schemes

HC 169

27th

Green Homes Grant Voucher Scheme

HC 635

28th

Efficiency in government

HC 636

29th

The National Law Enforcement Data Programme

HC 638

30th

Challenges in implementing digital change

HC 637

31st

Environmental Land Management Scheme

HC 639

32nd

Delivering gigabitcapable broadband

HC 743

33rd

Underpayments of the State Pension

HC 654

34th

Local Government Finance System: Overview and Challenges

HC 646

35th

The pharmacy early payment and salary advance schemes in the NHS

HC 745

36th

EU Exit: UK Border post transition

HC 746

37th

HMRC Performance in 2020–21

HC 641

38th

COVID-19 cost tracker update

HC 640

39th

DWP Employment Support: Kickstart Scheme

HC 655

40th

Excess votes 2020–21: Serious Fraud Office

HC 1099

41st

Achieving Net Zero: Follow up

HC 642

42nd

Financial sustainability of schools in England

HC 650

43rd

Reducing the backlog in criminal courts

HC 643

44th

NHS backlogs and waiting times in England

HC 747

45th

Progress with trade negotiations

HC 993

46th

Government preparedness for the COVID-19 pandemic: lessons for government on risk

HC 952

47th

Academies Sector Annual Report and Accounts 2019/20

HC 994

48th

HMRC’s management of tax debt

HC 953

49th

Regulation of private renting

HC 996

50th

Bounce Back Loans Scheme: Follow-up

HC 951

51st

Improving outcomes for women in the criminal justice system

HC 997

52nd

Ministry of Defence Equipment Plan 2021–31

HC 1164

1st Special Report

Fifth Annual Report of the Chair of the Committee of Public Accounts

HC 222

Session 2019–21

Number

Title

Reference

1st

Support for children with special educational needs and disabilities

HC 85

2nd

Defence Nuclear Infrastructure

HC 86

3rd

High Speed 2: Spring 2020 Update

HC 84

4th

EU Exit: Get ready for Brexit Campaign

HC 131

5th

University technical colleges

HC 87

6th

Excess votes 2018–19

HC 243

7th

Gambling regulation: problem gambling and protecting vulnerable people

HC 134

8th

NHS capital expenditure and financial management

HC 344

9th

Water supply and demand management

HC 378

10th

Defence capability and the Equipment Plan

HC 247

11th

Local authority investment in commercial property

HC 312

12th

Management of tax reliefs

HC 379

13th

Whole of Government Response to COVID-19

HC 404

14th

Readying the NHS and social care for the COVID-19 peak

HC 405

15th

Improving the prison estate

HC 244

16th

Progress in remediating dangerous cladding

HC 406

17th

Immigration enforcement

HC 407

18th

NHS nursing workforce

HC 408

19th

Restoration and renewal of the Palace of Westminster

HC 549

20th

Tackling the tax gap

HC 650

21st

Government support for UK exporters

HC 679

22nd

Digital transformation in the NHS

HC 680

23rd

Delivering carrier strike

HC 684

24th

Selecting towns for the Towns Fund

HC 651

25th

Asylum accommodation and support transformation programme

HC 683

26th

Department of Work and Pensions Accounts 2019–20

HC 681

27th

Covid-19: Supply of ventilators

HC 685

28th

The Nuclear Decommissioning Authority’s management of the Magnox contract

HC 653

29th

Whitehall preparations for EU Exit

HC 682

30th

The production and distribution of cash

HC 654

31st

Starter Homes

HC 88

32nd

Specialist Skills in the civil service

HC 686

33rd

Covid-19: Bounce Back Loan Scheme

HC 687

34th

Covid-19: Support for jobs

HC 920

35th

Improving Broadband

HC 688

36th

HMRC performance 2019–20

HC 690

37th

Whole of Government Accounts 2018–19

HC 655

38th

Managing colleges’ financial sustainability

HC 692

39th

Lessons from major projects and programmes

HC 694

40th

Achieving government’s long-term environmental goals

HC 927

41st

COVID 19: the free school meals voucher scheme

HC 689

42nd

COVID-19: Government procurement and supply of Personal Protective Equipment

HC 928

43rd

COVID-19: Planning for a vaccine Part 1

HC 930

44th

Excess Votes 2019–20

HC 1205

45th

Managing flood risk

HC 931

46th

Achieving Net Zero

HC 935

47th

COVID-19: Test, track and trace (part 1)

HC 932

48th

Digital Services at the Border

HC 936

49th

COVID-19: housing people sleeping rough

HC 934

50th

Defence Equipment Plan 2020–2030

HC 693

51st

Managing the expiry of PFI contracts

HC 1114

52nd

Key challenges facing the Ministry of Justice

HC 1190

53rd

Covid 19: supporting the vulnerable during lockdown

HC 938

54th

Improving single living accommodation for service personnel

HC 940

55th

Environmental tax measures

HC 937

56th

Industrial Strategy Challenge Fund

HC 941


Footnotes

1 Q140

2 C&AG’s Report, Lessons learned: Resetting major programmes, Session 2022–23, HC 1198, 17 March 2023

3 C&AG’s Report, para 1

4 C&AG’s Report, para 2, figure 1

5 Q1; C&AG’s Report, para 3

6 Infrastructure and Projects Authority, Mandate, January 2021

7 C&AG’s Report, para 8

8 Qq 2, 4, 8

9 C&AG’s Report, para 26

10 Qq 97, introductory remarks before q102, 134

11 Qq introductory remarks before q102, 157, 169

12 Q 135

13 Qq 142, 169

14 Qq 17, 32

15 C&AG’s Report, para 8

16 Qq 4, 20–21, 66–67, 88

17 C&AG’s Report, para 8

18 Qq 97, introductory remarks before q102, 102

19 Qq 4–5, 18–19

20 C&AG’s Report, para 9

21 Q97

22 Q 11

23 Qq 115, 128–129

24 Q 117

25 Qq 11, 17, 97; C&AG’s Report, para 10

26 Qq 115, 105

27 Committee of Public Accounts, Improving the Accounting Officer Assessment process, Twenty-Eighth Report of Session 2022–23, HC 43, 30 November 2022, recommendation 4

28 Q 89; C&AG’s Report, paras 12–13

29 Qq 2–3

30 Q 138; C&AG’s Report, para 12

31 Qq introductory remarks before q102, 135, 167

32 Q 68

33 Q 118

34 Q 167

35 Q 134

36 C&AG’s Report, para 13

37 Qq 111–114

38 Q 69

39 Q 99; C&AG’s Report, Universal Credit: progress update, Session 2014–15, HC 786, 26 November 2014

40 Qq 73–75, 79, 90

41 C&AG’s Report, para 16

42 Q 17

43 Qq 16

44 Qq 9, 10, 91, 93

45 Qq 76–77

46 Qq 16, 19

47 Qq 70–72

48 Qq 121–124

49 Qq 12–13

50 Q 15

51 Q 168

52 Qq 104–105, 107

53 C&AG’s Report, para 11

54 Q 116

55 Q 3, C&AG’s Report, Electronic monitoring: a progress update, Session 2022–23, HC 62, 8 June 2022

56 Qq 31–33, 36–37

57 C&AG’s Report, para 21–22

58 Q 85

59 Qq 77–78

60 Qq 73–79

61 Qq 75, 95–96, 135; C&AG’s Report, The Ajax programme, Session 2021–22, HC 1142, 11 March 2022

62 C&AG’s Report, para 24

63 Q 2

64 Q 96

65 Qq 95, 120; C&AG’s Report, para 25

66 Qq 10, 68, 91

67 Q120

68 C&AG’s Report, para 28

69 Qq 14, 91–92

70 Q 70

71 Qq 96–97, 135

72 C&AG’s Report, para 28

73 Q 2

74 Qq 138–139

75 C&AG’s Report, para 29

76 Q 68

77 Qq 98–99

78 Qq 96, 98; Committee of Public Accounts, Lessons from major projects and programmes, Thirty-Ninth Report of Session 2019–21, HC 694, 29 January 2021

79 Qq 98–101

80 Qq 161–162

81 Qq 136–137

82 C&AG’s Report, para 2

83 Qq 97, 104, 134

84 C&AG’s Report, para 14

85 C&AG’s Report, para 27

86 Qq 21–22

87 Q 65

88 Q 68

89 Q 150; C&AG’s Report, para 18–19

90 C&AG’s Report, para 18

91 Q 17

92 Q 83

93 Q 84