Delivering value from government investment in major projects

This is a House of Commons Committee report, with recommendations to government. The Government has two months to respond.

Thirty-Second Report of Session 2023–24

Download and Share

Contents

Introduction

Major projects represent a significant element of government expenditure. As at March 2023, the Government Major Projects Portfolio—the government’s biggest and riskiest projects—included 244 projects with an estimated total whole-life cost of £805 billion. Major projects present unique challenges for government. The success of a project and whether it represents value for money will ultimately be determined by whether the intended value—such as economic growth or improved, more efficient public services—has been delivered, and whether the value of the project justifies its cost. The Comptroller and Auditor General’s recent report made a series of observations and drew out lessons based on an examination of projects that had been complete for some time and which had been broadly successful in delivering value from the investment. Delivering to budget and schedule are important in determining whether a project has been delivered for value for money. This report also, therefore, covers important areas related to project delivery and the challenges that government faces in ensuring that projects do not go over time and over budget, as we so often see on this Committee. These areas include the supply of project delivery skills in government departments and the supply chain, cost estimating and government’s ability to learn from other projects.

Conclusions and recommendations

1. Government departments spend too little time and effort establishing what value they expect a project to deliver and ensuring that major projects deliver the intended value. In 2020, HM Treasury revised the Green Book (its guidance on appraising options and producing business cases) to make it clearer that before appraising options for what to deliver, government departments should clarify the strategic objectives that they want to achieve and the value that they are aiming to deliver. The Infrastructure and Projects Authority (IPA) has also produced tools and guidance to challenge departments to be clearer about their objectives. But departments still find it challenging to consider fully the potential value from a project and incorporate that into business cases. Once a project is operational, a Gate 5 review—a review of how the project is operating—typically closes out the project. But that is only the beginning of the process of realising value. Government departments are too focused on the short term, and do not look at the long-term economic benefits enough. Plans for realising benefits are insufficiently professional and robust and there is currently no formal, centrally mandated process—such as a Gate 6 review—for looking at what value has been delivered once the project has been operational for some time.

Recommendation 1: The IPA and HMT should review the case for a centrally mandated review stage to look at what value a major project has achieved once it has been operational for some time, such as a new Gate 6 review.

2. Government departments still have few incentives to commission and carry out high-quality evaluations of major projects. High quality evaluation is an important means of providing evidence about what works, transparency about what value a project has produced, and making the case (or not) for further investment. As we pointed out in our May 2022 report on the use of evaluation and modelling in government, in 2019, only 8% of £432 billion of spend on major projects had robust impact evaluation plans in place, and 64% of spend had no evaluation arrangements at all. The Evaluation Task Force is currently updating the 2019 analysis of how much evaluation of major projects now takes place and there is still room for improvement. In our May 2022 report we also pointed out that the same barriers such as a lack of political engagement and a lack of incentives for departments to produce evaluations had persisted since 2013. HM Treasury says it still has more to do to address these barriers, but that the time that it can take for value and benefits to be realised and the time it takes to carry out an evaluation can be barriers. HM Treasury does not, however, consider the cost of evaluation to be a barrier.

Recommendation 2: HM Treasury and the evaluation task force should develop a plan that addresses the root causes of why evaluations are not routinely carried out and how to incentivise departments to carry our more high-quality and independent evaluations.

3. There are signs of improved cross-government working but government still struggles to establish effective governance and accountability arrangements on the most complex projects where multiple departments are involved. In our February 2024 report on cross-government working in general we concluded that “effective cross-government working is fundamental to delivering government’s priorities but there is a lot of work to do”. This is particularly so for complex major projects, which often contribute to the objectives of multiple government departments and involve a number of organisation in delivery. There are examples of good practice, such as the East-West Rail project’s growth board that brings together local and central government, and the No 10 Delivery Unit can also be effective in bringing departments together to deliver cross-cutting priorities. For some projects it may be more effective to have an organisation outside of the project delivery team accountable for delivering value. Development corporations such as those established to deliver regeneration benefits at Ebbsfleet for High Speed 1 and the Queen Elizabeth Olympic Park for the London 2012 Games have been effective. But bringing together the right stakeholders to deliver value does not come naturally to government departments and this remains a challenge. Ensuring that appropriate individuals sit on project boards is also important to provide challenge to project teams, support delivery and ensure that value is delivered.

Recommendation 3: HM Treasury and the Infrastructure Projects Authority should:

a) analyse what governance structures and incentives work well to encourage cross-government working; and

b) issue guidance on how government departments can apply the right approaches that reflect the objectives and complexity of their projects including for delivering value once a project is complete.

4. Government departments and the broader economy lack the necessary skills and capacity to deliver the government’s ambitious portfolio of major infrastructure projects. The UK’s projected spend on infrastructure projects over the next five years is very high—unprecedented, according to the IPA—with the UK building more than it has ever built and in a range of sectors including roads, rail and energy. With global competition from other countries with massive investment projects such as Saudi Arabia, there is a risk of skills shortage to deliver such an ambitious portfolio of investment. Skills shortages in specific trades such as welding are already being seen but design and project management skills are also in short supply. Failure to build market capacity could result in higher prices for scarce skills. Too little of the right skills in government has led to an overreliance on the supply chain, particularly in technical and engineering disciplines. The IPA says that nearly 1,000 accredited project professionals have now passed through the government’s major project leadership academy and that it has an ambition to get another 1,000 accredited professionals through the programme by the end of March 2025. However, that is only a small proportion of the 16,000 government project professionals that need to gain accreditation.

Recommendation 4: Alongside their response to this report HM Treasury and the Infrastructure Projects Authority should write to the Committee with an analysis of risks to the government’s portfolio of infrastructure projects caused by the lack of skills.

5. The IPA’s plans to improve the quality of government’s cost estimates of major projects have taken too long to implement. We have examined many projects where early cost estimates have proved to bear little resemblance to what a project will ultimately cost, and there is optimism bias in nearly every project we look at. Funding packages are often agreed, and projects approved before projects have reached sufficient maturity. High Speed 2 is a prime example of a budget being set well before plans were sufficiently mature. The IPA says that departments should be using ranges of potential costs until a project is sufficiently mature to finalise a funding package. Lack of cost-estimation capability in government means that departments end up too reliant on suppliers to determine what a project will cost. The IPA has produced cost-estimation guidance and developed a cost-benchmarking hub to provide better data to improve cost estimation. However, the IPA does not expect departments to populate it with their project cost data until later this year and currently does not intend that the benchmarking hub also includes information on the value and benefits that projects produce.

Recommendation 5: Alongside their response to this report, the Infrastructure Projects Authority and HM Treasury should write to the Committee setting out how they plan to incentivise departments to populate the IPA’s benchmarking hub with accurate and consistent information on the actual costs and benefits of their projects.

6. Government departments do not routinely learn lessons from their own projects or those of other departments, so are missing opportunities to improve effectiveness and efficiency of future projects. Applying learning about what has been successful in major project delivery can bring great efficiency and reduced costs, particularly where standardisation of design is possible. Schools, hospitals and prison building programmes are starting to apply digital methods of design and off-site fabrication and to apply the approach of ‘design one, build many’. Of course, the success of this approach would require the supply chain to have enough of the required skills and capacity. There are government forums for the sharing of lessons about what works well in project delivery, such as the IPA-chaired Government Construction Board. However, learning across government departments still does not occur systematically, and departments must think more broadly about lessons in maximising long-term value, rather than just about lessons in delivering similar projects. The IPA acknowledged it could do more to challenge departments to learn from one project to another. Our February 2024 report on cross-government working also highlighted a lack of routine data sharing between departments and poor arrangements for sharing best practice and learning.

Recommendation 6: Alongside their response to this report, the Infrastructure Projects Authority and HM Treasury should write to the Committee outlining their plans for embedding cross-government learning for future major projects.

1 Identifying, delivering and evaluating value from major projects

1. On the basis of a report by the Comptroller and Auditor General, we took evidence from the Infrastructure and Projects Authority and HM Treasury.1

2. Major projects represent a significant element of government expenditure. As at March 2023, the Government Major Projects Portfolio—the government’s biggest and riskiest projects—included 244 projects with an estimated total whole-life cost of £805 billion. But major projects present unique challenges for government. All too often we see projects and programmes that are poorly managed and are delivered late and over budget. Delivering to budget and schedule are important in determining whether a project has been delivered for value for money and this report covers important areas of project delivery and the challenges facing government departments. These include the supply of project delivery skills in government departments and the supply chain, cost estimating and government’s ability to learn from other projects. However, the success of a project and whether it represents value for money will ultimately be determined by whether the intended value – such as economic growth or improved, more efficient public services – has been delivered, and whether the value of the project justifies its cost.2

3. The Comptroller and Auditor General’s recent report made a series of observations and drew out lessons based on its examination of projects that had been complete for some time and which had been broadly successful in delivering value from the investment over the long term. These projects included the Millennium Dome (now the O2 Arena), the London 2012 Olympic and Paralympic Games, High Speed 1, the BBC’s move to Salford, and two science and research projects funded by UK Research and Innovation: the Diamond Light Source and the Hartree Centre.3

Identifying and delivering value

4. The first lesson identified by the NAO in its report is “Start with the difference you want to make and the value you want to produce, rather than the project you want to do”. HM Treasury told us that this is how the system by which government departments develop business cases for projects is meant to work: start with what you are trying to do, set strategic objectives, develop a long list of options and trim that down to a short list before arriving at your preferred project. In 2020, HM Treasury reviewed and updated the Green Book—HM Treasury’s guidance on appraising options and producing business cases—to make it clear that departments should be considering their overall strategic objectives and the value they want to deliver, rather looking at the project only through the lens of the economic appraisal and the benefit-cost ratio. The Infrastructure and Projects Authority (IPA) told us that it has been spending a lot of time in the last two to three years developing tools including the project outcome toolkit and the project route-map, which challenge stakeholders to be clear about the objectives they want to deliver.4

5. It can take time for the economy, a local area or people to benefit from a project once it is complete. From the point of view of visitor numbers, the Millennium Dome was not a great success with the venue only achieving half of its planned visitor numbers during 2000. The Dome was converted to the O2 Arena in 2005 and the first concert was held there in 2007. The O2 Arena is now one of the world’s most popular entertainment venues and has brought employment and an important boost to the economy of the Greenwich Peninsula. Some projects which have the potential to support regeneration of a local area can take a particularly long time, particularly if the right organisations are not in place. The economic development around Ebbsfleet station did not happen until a long time after High Speed 1 was built and Ebbsfleet station completed in 2007. It was not until the government set up Ebbsfleet Development Corporation in 2015 that regeneration of the area began to take shape. The London Legacy Development Corporation also had a positive impact in East London. HM Treasury told us that development corporations are an important part of maximising the chance that government can achieve the wider benefits from its investment.5

6. Despite the length of time it can take for value to be realised, the IPA told us that government departments are too focused on the short-term. The IPA told us that government departments do not always fully consider the potential upsides and long-term value from projects when developing their business case. In preparing its report, the NAO spoke to people with project management expertise from within and outside government who expressed the view that government focuses more on identifying potential benefits to make the case for investment, and on delivering to budget and schedule, than on ensuring that projects achieve the intended purpose and long-term value. The IPA told us that once a project is complete, a Gate 5 review—a review of how the project is operating and what benefits are being delivered—typically closes out the project. However, the IPA also told that benefits realisation plans for projects should go beyond Gate 5 to ensure that benefits are realised over the longer term. It also told us that benefits realisation plans are neither robust nor professional enough, although the Departments for Transport and Energy, Security and Net Zero are taking benefits realisation more seriously. There is currently no formal, centrally mandated process—such as a Gate 6 review—for looking at what value has been delivered once the project has been operational for some time. The IPA considered that benefits realisation plans that are clear about who is delivering value and over what time period would be helpful.6

Evaluation

7. High quality evaluation is an important means of providing evidence about what works and transparency about what value a project has produced. In our May 2022 report on government’s use of evaluation and modelling, we stated:

“Without the right incentives, improvements to oversight and culture, and addressing challenges such as sharing data, decisions will continue to be made without being informed by a robust evidence base. This can put value for money unnecessarily at risk.”7

The C&AG’s 2024 report provides examples of the importance of evaluation to enable government departments to understand how they can deliver better value from their major projects. The Diamond Light Source’s 2021 study into the scientific, technological, societal and economic benefits of the facility contributed to the evidence base and input to future funding requests. An evaluation of the London 2012 Olympics, meanwhile, demonstrated how it had been able to implement sustainable procurement on the programme.8

8. There are too few evaluations of government’s major projects. As we pointed out in our May 2022 report on the use of evaluation and modelling in government, in 2019, only 8% of £432 billion of spend on major projects had robust impact evaluation plans in place, and 64% of spend had no evaluation arrangements at all. HM Treasury told us that this figure is too low and that it is not acceptable for departments to have no evaluation arrangements in place. The IPA told us that most departments have gaps in terms of their evaluations but that the Ministry of Defence has particularly significant gaps. The Evaluation Task Force is currently updating the 2019 analysis of how many projects in the Government Major Projects Portfolio have robust evaluation plans.9

9. In our May 2022 report on evaluation, we pointed out that the same barriers to departments doing more evaluations had been in place since 2013. These include a lack of political engagement and a lack of incentives for departments to produce evaluations. HM Treasury told us that it still has more to do to address these barriers. It told us that departments have the desire to demonstrate what they have delivered for their investment. However, the time it can take for value and benefits to be realised, as well as the time it can take to carry out an evaluation means that evaluations are not always carried out. In particular, these issues of timing do not always match with the political cycle of, for example, elections and spending reviews, which can mean that departments are not incentivised. HM Treasury told us that because the cost of an evaluation is small compared to the cost of delivering a project, it does not consider cost to be a barrier.10

Cross-government working

10. Although it is often the case that a single government department has ultimate accountability for delivery of a major project, it is often the case that multiple departments as well other stakeholders and organisations will be involved in delivery and in ensuring that value is delivered. Indeed, success depends on many organisations working together to create a shared vision through delivery and beyond. The C&AG’s report includes examples of where this has gone well. These include the developer’s masterplan for the Greenwich Peninsula which had widespread support from stakeholders including local authorities and the operator of the O2 Arena, and the Hartree Centre’s involvement of industry and academia in forums focused on getting value from the facility.11

11. For some projects it may be more effective for an organisation outside of the project delivery team to be accountable for delivering the value from the project. On two of the projects referred to in the C&AG’s report development corporations were set up by government to ensure that regeneration benefits were realised. The Ebbsfleet Development Corporation was set up to accelerate regeneration of the area around Ebbsfleet International Station and the London Legacy Development Corporation fulfilled a similar role in relation to the area in and around the Queen Elizabeth Olympic Park. HM Treasury told us that such approaches can be helpful.12

12. In our February 2024 report on cross-government working we concluded that “effective cross-government working is fundamental to delivering government’s priorities but there is a lot of work to do to make it more than just a ‘nice to have’”. However, the IPA told us that ensuring that stakeholders are involved at all stages still does not come naturally to departments, despite the fact that it is required as part of the national infrastructure planning process and is key to the success of a project.13

13. The IPA gave us examples where the involvement of stakeholders has been working well. For example, the East-West Rail project’s growth board that brings together local authority and government department and the A303 and Lower Thames Crossing projects have built support from controversial projects. The IPA also told us that the establishment of the No 10 Delivery Unit has been effective in bringing departments together to deliver cross-cutting projects and priorities. A presence on project boards from those outside the main delivery department can also bring alternative perspectives. Including independent non-executives with appropriate experience that matches the stage of the project on project boards is a good example and can help to provide challenge to project teams, support delivery and ensure that value is delivered.14

2 Progress with project delivery capability

Project delivery skills

14. As set out above, in March 2023, the value of the Government Major Projects Portfolio in terms of total whole-life costs was £805 billion. With major projects in the transport and energy sectors and programmes or projects to build new schools, hospitals and prisons, the UK’s projected spend on infrastructure projects over the next five years is very high. According to the IPA, which oversees major projects and infrastructure investment for government, the scale of investment is unprecedented, with the UK building more than it ever has.15

15. However, the IPA told us that it is already seeing evidence of current and future skills shortages and stiff competition from other countries with their own major investment programmes for scarce skills. The IPA gave specific examples of skills shortages in trades such welders for building frigates on behalf of the Ministry of Defence in Rosyth on the Firth of Forth, and steel fixers for the major civil engineering projects the government is delivering. However, there is also evidence of shortages of supply contractor management teams to fill the demand for contractors, with the same teams bidding for different projects. Saudi Arabia is one example of a country investing massively in its infrastructure. IPA told us that a design company with several hundred designers recently left the UK market to work on Saudi projects. The IPA told us that it is unclear whether the UK has enough capacity to deliver but there are likely to be pinch points, with the risk that increased demand for scarce skills could increase costs. The IPA told us that it is important that government does what it can to increase market capacity and that it has carried out a market analysis of capability and capacity. The IPA told us that it is also important that the speed of government investment matches the development of the market to minimise inflationary pressure.16

16. The IPA told us that there remains a lack of project management skills in the civil service and that there are particular shortages in technical and engineering skills. This lack of skills places too much reliance on the supply chain for those skills, which can place government departments in a weak position because it means departments cannot act as an intelligent client. Improving project management skills in government could also help to mitigate risks from there being shortages in the supply chain. The IPA told us that there are signs of senior responsible owners being better able to respond to the challenges of the IPA. The IPA mentioned a programme for moving projects from a red rating to an amber or green rating, stating that 70% of ‘red’ projects move to amber or green within twelve weeks. More project professionals are also gaining accreditation via the government’s major project leadership academy but there is still a long way to go and there is a particular need for skilled professionals in senior positions. Of 16,000 professionals required to gain accreditation, the IPA told us that 1,000 now have accreditation and that it has an ambition to get another 1,000 accredited professionals through the programme by the end of March 2025.17

Cost estimating

17. We have examined numerous projects over the years where cost estimates have increased significantly over the life of the project. Optimism bias in government is a significant factor in nearly every project we look at. Another, related, factor is a tendency in government to approve projects before they have been developed sufficiently for there to be confidence in the accuracy of the cost estimate. High Speed 2 has been a case in point. In our February 2024 report on the High Speed 2 programme, we stated that HS2 Ltd had estimated that the cost to complete Phase 1 between London and Birmingham will be £49 billion to £57 billion (2019 prices) and could rise by a further £8 billion to £10 billion due to inflation since 2019. This is substantially higher that the budget of £44.9 billion that was set in 2020. The IPA told us, and HM Treasury agreed, that departments should be using ranges of potential costs until a project is sufficiently mature to finalise a funding package. But, although HS2 Ltd is now using ranges of potential costs, the IPA noted that plans for High Speed 2 had only reached maturity level of 10% when the final business case—the point at which projects are approved to begin construction—was approved.18

18. Lack of cost-estimation capability in government means that government is reliant on suppliers to government defining what a project will cost. The IPA told us that cost estimation is an important skill and one that government departments need to be much better at. HM Treasury told us that the challenge of estimating cost accurately for developing business cases and for spending reviews is an area that government still has not cracked and that better transparency about cost estimates can be helpful. The IPA has produced guidance on cost estimating and told us that it will be important for departments to move away from reference-class forecasting—applying costs from previous projects that are similar to those in your project—because that can miss important unique aspects of your project. The IPA also told us that it has developed a community of cost estimators across all 19 government departments and a cost-benchmarking hub to provide better data to improve cost estimation. More extensive use of standardisation and use of data and digitalisation of project designs could help produce more accurate estimates. However, the cost benchmarking hub does not yet have the data to make it useful and effective as a tool. The IPA does not expect departments to populate it with their project cost data until later this year. The IPA told us that including information on estimates of benefits could also be useful in the future but it does not currently intend to use the benchmarking hub for this purpose.19

Learning from previous projects

19. Applying learning about what has been successful in major project delivery can bring great efficiency and reduced costs. The C&AG’s report, and other lessons learned reports like it, as well as those produced by this Committee are useful resources for government to find out what works. The C&AG’s report used examples of long-completed projects that have been broadly successful in generating value to identify observations and lessons that could be useful for departments.20

20. The IPA told us that increased standardisation of design of some projects can be a helpful way to learn and apply what has worked well. The IPA told us that the schools, hospitals and prison building programmes are starting to apply digital methods of design and off-site fabrication and to apply the approach of ‘design one, build many’. Such an approach can bring cost savings and improve learning. However, this brings with it challenges because the programme of investment needs to have the scale to make it cost-effective to apply the process of standardisation.21

21. In our February 2024 report on cross-government working we highlighted that a lack of routine data sharing between departments and poor arrangements for sharing best practice and learning. Learning lessons from major projects can, however, be a challenge because of the nature of some projects. It may not be immediately clear, for example, what projects can learn from such specific projects as the Millennium Dome, the London 2012 Olympics, or the programme to maintain a nuclear deterrent. That said, comparison with such projects is still possible if departments are clear about their strategic objectives and identify similarities between projects.22

22. The IPA told us it could do more to challenge departments to learn from one project to another. The IPA did, however, point to areas where learning is improving in government. For example, the IPA chairs the Government Construction Board, where lessons about what works well in project delivery are shared, and the IPA is preparing materials for departments on what good looks like. The government has also recently produced a report on lessons from the Crossrail project. The IPA told us that non-executive directors and governance boards of major projects can bring helpful learning and insight. The IPA cited the example of the board for the Sizewell C project to build a new nuclear power station, where he is the government non-executive Director.23

Formal minutes

Wednesday 8 May 2024

Members present

Dame Meg Hillier, in the Chair

Olivia Blake

Sarah Olney

Matt Warman

Ms Marie Rimmer

Delivering value from government investment in major projects

Draft Report (Delivering value from government investment in major projects), proposed by the Chair, brought up and read.

Ordered, That the draft Report be read a second time, paragraph by paragraph.

Paragraphs 1 to 22 read and agreed to.

Summary agreed to.

Introduction agreed to.

Conclusions and recommendations agreed to.

Resolved, That the Report be the Thirty-second Report of the Committee to the House.

Ordered, That the Chair make the Report to the House.

Ordered, That embargoed copies of the Report be made available (Standing Order No. 134).

Adjournment

Adjourned till Monday 13 May at 3.30 p.m.


Witnesses

The following witnesses gave evidence. Transcripts can be viewed on the inquiry publications page of the Committee’s website.

Wednesday 20 March 2024

Conrad Smewing, Director General Public Spending, HM Treasury; Nick Smallwood, CEO, Infrastructure and Projects AuthorityQ1–80


Published written evidence

The following written evidence was received and can be viewed on the inquiry publications page of the Committee’s website.

VGI numbers are generated by the evidence processing system and so may not be complete.

1 Association for Project Management (VGI0003)

2 Centre for Public Data (VGI0005)

3 Coleman, Ms Sarah (University of Manchester) (VGI0007)

4 Institution of Civil Engineers (ICE) (VGI0002)

5 Mineral Products Association (VGI0004)

6 Newman, Jack (University of Bristol); Ayres, Professor Sarah (University of Bristol); Bates, Dr Geoff (University of Bath); and McClatchey, Rachael (University of Bristol) (VGI0008)

7 The Productivity Institute (VGI0006)


List of Reports from the Committee during the current Parliament

All publications from the Committee are available on the publications page of the Committee’s website.

Session 2023–24

Number

Title

Reference

1st

The New Hospital Programme

HC 77

2nd

The condition of school buildings

HC 78

3rd

Revising health assessments for disability benefits

HC 79

4th

The Department for Work & Pensions Annual Report and Accounts 2022–23

HC 290

5th

Government’s programme of waste reforms

HC 333

6th

Competition in public procurement

HC 385

7th

Resilience to flooding

HC 71

8th

Improving Defence Inventory Management

HC 66

9th

Whole of Government Accounts 2020–21

HC 65

10th

HS2 and Euston

HC 67

11th

Reducing the harm from illegal drugs

HC 72

12th

Cross-government working

HC 75

13th

Preparedness for online safety regulation

HC 73

14th

Homes for Ukraine

HC 69

15th

Managing government borrowing

HC 74

16th

HMRC performance in 2022–23

HC 76

17th

Cabinet Office functional savings

HC 423

18th

Excess Votes 2022–23

HC 589

19th

MoD Equipment Plan 2023–2033

HC 451

20th

Monitoring and responding to companies in distress

HC 425

21st

Levelling up funding to local government

HC 424

22nd

Reforming adult social care in England

HC 427

23rd

Civil service workforce: Recruitment, pay and performance management

HC 452

24th

NHS Supply Chain and efficiencies in procurement

HC 453

25th

Scrutiny of sound financial practice across Government

HC 673

26th

The BBC’s implementation of Across the UK

HC 426

27th

Government resilience: extreme weather

HC 454

28th

Student loans issued to those studying at franchised higher education providers

HC 455

29th

Progress in implementing Universal Credit

HC 458

30th

Non-executive appointments

HC 460

31st

Department of Health and Social Care 2022–23 Annual Report and Accounts

HC 459

1st Special Report

Eighth Annual Report of the Chair of the Committee of Public Accounts

HC 628

Session 2022–23

Number

Title

Reference

1st

Department for Business, Energy & Industrial Strategy Annual Report and Accounts 2020–21

HC 59

2nd

Lessons from implementing IR35 reforms

HC 60

3rd

The future of the Advanced Gas-cooled Reactors

HC 118

4th

Use of evaluation and modelling in government

HC 254

5th

Local economic growth

HC 252

6th

Department of Health and Social Care 2020–21 Annual Report and Accounts

HC 253

7th

Armoured Vehicles: the Ajax programme

HC 259

8th

Financial sustainability of the higher education sector in England

HC 257

9th

Child Maintenance

HC 255

10th

Restoration and Renewal of Parliament

HC 49

11th

The rollout of the COVID-19 vaccine programme in England

HC 258

12th

Management of PPE contracts

HC 260

13th

Secure training centres and secure schools

HC 30

14th

Investigation into the British Steel Pension Scheme

HC 251

15th

The Police Uplift Programme

HC 261

16th

Managing cross-border travel during the COVID-19 pandemic

HC 29

17th

Government’s contracts with Randox Laboratories Ltd

HC 28

18th

Government actions to combat waste crime

HC 33

19th

Regulating after EU Exit

HC 32

20th

Whole of Government Accounts 2019–20

HC 31

21st

Transforming electronic monitoring services

HC 34

22nd

Tackling local air quality breaches

HC 37

23rd

Measuring and reporting public sector greenhouse gas emissions

HC 39

24th

Redevelopment of Defra’s animal health infrastructure

HC 42

25th

Regulation of energy suppliers

HC 41

26th

The Department for Work and Pensions’ Accounts 2021–22 – Fraud and error in the benefits system

HC 44

27th

Evaluating innovation projects in children’s social care

HC 38

28th

Improving the Accounting Officer Assessment process

HC 43

29th

The Affordable Homes Programme since 2015

HC 684

30th

Developing workforce skills for a strong economy

HC 685

31st

Managing central government property

HC 48

32nd

Grassroots participation in sport and physical activity

HC 46

33rd

HMRC performance in 2021–22

HC 686

34th

The Creation of the UK Infrastructure Bank

HC 45

35th

Introducing Integrated Care Systems

HC 47

36th

The Defence digital strategy

HC 727

37th

Support for vulnerable adolescents

HC 730

38th

Managing NHS backlogs and waiting times in England

HC 729

39th

Excess Votes 2021–22

HC 1132

40th

COVID employment support schemes

HC 810

41st

Driving licence backlogs at the DVLA

HC 735

42nd

The Restart Scheme for long-term unemployed people

HC 733

43rd

Progress combatting fraud

HC 40

44th

The Digital Services Tax

HC 732

45th

Department for Business, Energy & Industrial Strategy Annual Report and Accounts 2021–22

HC 1254

46th

BBC Digital

HC 736

47th

Investigation into the UK Passport Office

HC 738

48th

MoD Equipment Plan 2022–2032

HC 731

49th

Managing tax compliance following the pandemic

HC 739

50th

Government Shared Services

HC 734

51st

Tackling Defra’s ageing digital services

HC 737

52nd

Restoration & Renewal of the Palace of Westminster – 2023 Recall

HC 1021

53rd

The performance of UK Security Vetting

HC 994

54th

Alcohol treatment services

HC 1001

55th

Education recovery in schools in England

HC 998

56th

Supporting investment into the UK

HC 996

57th

AEA Technology Pension Case

HC 1005

58th

Energy bills support

HC 1074

59th

Decarbonising the power sector

HC 1003

60th

Timeliness of local auditor reporting

HC 995

61st

Progress on the courts and tribunals reform programme

HC 1002

62nd

Department of Health and Social Care 2021–22 Annual Report and Accounts

HC 997

63rd

HS2 Euston

HC 1004

64th

The Emergency Services Network

HC 1006

65th

Progress in improving NHS mental health services

HC 1000

66th

PPE Medpro: awarding of contracts during the pandemic

HC 1590

67th

Child Trust Funds

HC 1231

68th

Local authority administered COVID support schemes in England

HC 1234

69th

Tackling fraud and corruption against government

HC 1230

70th

Digital transformation in government: addressing the barriers to efficiency

HC 1229

71st

Resetting government programmes

HC 1231

72nd

Update on the rollout of smart meters

HC 1332

73rd

Access to urgent and emergency care

HC 1336

74th

Bulb Energy

HC 1232

75th

Active travel in England

HC 1335

76th

The Asylum Transformation Programme

HC 1334

77th

Supported housing

HC 1330

78th

Resettlement support for prison leavers

HC 1329

79th

Support for innovation to deliver net zero

HC 1331

80th

Progress with Making Tax Digital

HC 1333

1st Special Report

Sixth Annual Report of the Chair of the Committee of Public Accounts

HC 50

2nd Special Report

Seventh Annual Report of the Chair of the Committee of Public Accounts

HC 1055

Session 2021–22

Number

Title

Reference

1st

Low emission cars

HC 186

2nd

BBC strategic financial management

HC 187

3rd

COVID-19: Support for children’s education

HC 240

4th

COVID-19: Local government finance

HC 239

5th

COVID-19: Government Support for Charities

HC 250

6th

Public Sector Pensions

HC 289

7th

Adult Social Care Markets

HC 252

8th

COVID 19: Culture Recovery Fund

HC 340

9th

Fraud and Error

HC 253

10th

Overview of the English rail system

HC 170

11th

Local auditor reporting on local government in England

HC 171

12th

COVID 19: Cost Tracker Update

HC 173

13th

Initial lessons from the government’s response to the COVID-19 pandemic

HC 175

14th

Windrush Compensation Scheme

HC 174

15th

DWP Employment support

HC 177

16th

Principles of effective regulation

HC 176

17th

High Speed 2: Progress at Summer 2021

HC 329

18th

Government’s delivery through arm’s-length bodies

HC 181

19th

Protecting consumers from unsafe products

HC 180

20th

Optimising the defence estate

HC 179

21st

School Funding

HC 183

22nd

Improving the performance of major defence equipment contracts

HC 185

23rd

Test and Trace update

HC 182

24th

Crossrail: A progress update

HC 184

25th

The Department for Work and Pensions’ Accounts 2020–21 – Fraud and error in the benefits system

HC 633

26th

Lessons from Greensill Capital: accreditation to business support schemes

HC 169

27th

Green Homes Grant Voucher Scheme

HC 635

28th

Efficiency in government

HC 636

29th

The National Law Enforcement Data Programme

HC 638

30th

Challenges in implementing digital change

HC 637

31st

Environmental Land Management Scheme

HC 639

32nd

Delivering gigabitcapable broadband

HC 743

33rd

Underpayments of the State Pension

HC 654

34th

Local Government Finance System: Overview and Challenges

HC 646

35th

The pharmacy early payment and salary advance schemes in the NHS

HC 745

36th

EU Exit: UK Border post transition

HC 746

37th

HMRC Performance in 2020–21

HC 641

38th

COVID-19 cost tracker update

HC 640

39th

DWP Employment Support: Kickstart Scheme

HC 655

40th

Excess votes 2020–21: Serious Fraud Office

HC 1099

41st

Achieving Net Zero: Follow up

HC 642

42nd

Financial sustainability of schools in England

HC 650

43rd

Reducing the backlog in criminal courts

HC 643

44th

NHS backlogs and waiting times in England

HC 747

45th

Progress with trade negotiations

HC 993

46th

Government preparedness for the COVID-19 pandemic: lessons for government on risk

HC 952

47th

Academies Sector Annual Report and Accounts 2019/20

HC 994

48th

HMRC’s management of tax debt

HC 953

49th

Regulation of private renting

HC 996

50th

Bounce Back Loans Scheme: Follow-up

HC 951

51st

Improving outcomes for women in the criminal justice system

HC 997

52nd

Ministry of Defence Equipment Plan 2021–31

HC 1164

1st Special Report

Fifth Annual Report of the Chair of the Committee of Public Accounts

HC 222

Session 2019–21

Number

Title

Reference

1st

Support for children with special educational needs and disabilities

HC 85

2nd

Defence Nuclear Infrastructure

HC 86

3rd

High Speed 2: Spring 2020 Update

HC 84

4th

EU Exit: Get ready for Brexit Campaign

HC 131

5th

University technical colleges

HC 87

6th

Excess votes 2018–19

HC 243

7th

Gambling regulation: problem gambling and protecting vulnerable people

HC 134

8th

NHS capital expenditure and financial management

HC 344

9th

Water supply and demand management

HC 378

10th

Defence capability and the Equipment Plan

HC 247

11th

Local authority investment in commercial property

HC 312

12th

Management of tax reliefs

HC 379

13th

Whole of Government Response to COVID-19

HC 404

14th

Readying the NHS and social care for the COVID-19 peak

HC 405

15th

Improving the prison estate

HC 244

16th

Progress in remediating dangerous cladding

HC 406

17th

Immigration enforcement

HC 407

18th

NHS nursing workforce

HC 408

19th

Restoration and renewal of the Palace of Westminster

HC 549

20th

Tackling the tax gap

HC 650

21st

Government support for UK exporters

HC 679

22nd

Digital transformation in the NHS

HC 680

23rd

Delivering carrier strike

HC 684

24th

Selecting towns for the Towns Fund

HC 651

25th

Asylum accommodation and support transformation programme

HC 683

26th

Department of Work and Pensions Accounts 2019–20

HC 681

27th

Covid-19: Supply of ventilators

HC 685

28th

The Nuclear Decommissioning Authority’s management of the Magnox contract

HC 653

29th

Whitehall preparations for EU Exit

HC 682

30th

The production and distribution of cash

HC 654

31st

Starter Homes

HC 88

32nd

Specialist Skills in the civil service

HC 686

33rd

Covid-19: Bounce Back Loan Scheme

HC 687

34th

Covid-19: Support for jobs

HC 920

35th

Improving Broadband

HC 688

36th

HMRC performance 2019–20

HC 690

37th

Whole of Government Accounts 2018–19

HC 655

38th

Managing colleges’ financial sustainability

HC 692

39th

Lessons from major projects and programmes

HC 694

40th

Achieving government’s long-term environmental goals

HC 927

41st

COVID 19: the free school meals voucher scheme

HC 689

42nd

COVID-19: Government procurement and supply of Personal Protective Equipment

HC 928

43rd

COVID-19: Planning for a vaccine Part 1

HC 930

44th

Excess Votes 2019–20

HC 1205

45th

Managing flood risk

HC 931

46th

Achieving Net Zero

HC 935

47th

COVID-19: Test, track and trace (part 1)

HC 932

48th

Digital Services at the Border

HC 936

49th

COVID-19: housing people sleeping rough

HC 934

50th

Defence Equipment Plan 2020–2030

HC 693

51st

Managing the expiry of PFI contracts

HC 1114

52nd

Key challenges facing the Ministry of Justice

HC 1190

53rd

Covid 19: supporting the vulnerable during lockdown

HC 938

54th

Improving single living accommodation for service personnel

HC 940

55th

Environmental tax measures

HC 937

56th

Industrial Strategy Challenge Fund

HC 941


Footnotes

1 C&AG’s Report, Lessons learned: Delivering value from government investment in major projects; Session 2023–24, HC 554, 23 February 2024

2 Q1; C&AG’s Report, paras 1–2; Infrastructure and Projects Authority, Annual report on Major Projects 2022–23, 20 July 2023

3 C&AG’s Report, paras 4–5

4 Qq 2–3, 58; C&AG’s Report, Figure 1

5 Qq 4, 25, 29, 65; C&AG’s Report, para 27 and Figure 2 and 4, pages 18–19 and 22–23

6 Qq 4, 31, 64; C&AG’s Report, para 2

7 Committee of Public Accounts, Use of evaluation and financial modelling in Government, Fourth Report of Session 2022–23, HC 254, 27 May 2022

8 Ibid; C&AG’s Report, paras 10–12, 15, Figure 3

9 Qq 32, 44–45; Committee of Public Accounts, Use of evaluation and financial modelling in Government, Fourth Report of Session 2022–23, HC 254, 27 May 2022

10 Qq 32–37, Committee of Public Accounts, Use of evaluation and financial modelling in Government, Fourth Report of Session 2022–23, HC 254, 27 May 2022

11 Q25; C&AG’s Report, paras 20–24

12 Q4; C&AG’s Report, para 23

13 Qq 25–26; Committee of Public Accounts, Cross-government working, Twelfth Report of Session 2023–24, HC 75, 13 February 2024

14 Qq 17, 22–29

15 Qq 9, 74–75; C&AG’s Report, para 1

16 Qq 74–75

17 Qq 45–53

18 Qq 70; Committee of Public Accounts, HS2 and Euston, Tenth Report of Session 2023–24, HC 67, 7 February 2024

19 Qq 39–43; 66–67

20 Q1; C&AG’s Report, paras 1–8, Figure 1

21 Qq 9 - 13

22 Q 3; Committee of Public Accounts, Cross-government working, Twelfth Report of Session 2023–24

23 Qq 16; 21–24