Summary
National Savings & Investments (NS&I) launched a high-risk digital Business Transformation Programme (the Programme) in 2020, attempting to modernise its operations and measurably reduce its running costs. NS&I did not have the skills to deliver such a programme. In 2022–23 and 2023–24 the programme was rated ‘red’ meaning successful delivery of the project appears to be unachievable. As a result, the Programme has been undergoing a ‘reset’ since 2024, with little transformation delivered to date. Total costs of the Programme, including running costs, were estimated in 2024 at £3.0 billion, an increase of £1.3 billion from 2020, but further increases are likely once the reset is complete.
The underlying causes of Programme delays were weaknesses in understanding programme complexity, awarding contracts before NS&I understood dependencies, no agreed integrated plans, and a lack of skills and expertise. Despite the lack of progress, NS&I has not demonstrated to us that it understands and accepted what went wrong. It remains over-confident about its ability to meet its current timetable, even though it still does not have an agreed, integrated programme plan five years after starting the Programme. NS&I’s ‘good-news’ culture, and weak risk management, means the Programme has not provided the right information to inform key decisions and to enable effective scrutiny. Throughout the Programme NS&I has been advised by other organisations in government and consultants, who highlighted risks and made recommendations for improvements, but has often been slow to act on advice given.
HM Treasury (the Treasury), which sponsors NS&I, was too slow to realise there was an issue and to act. We welcome the Treasury’s appointment of senior people with experience of digital transformation to support NS&I and to hold it to account, but it has limited levers and there is a risk that more taxpayer funding will be provided without assurance that the Programme can be delivered. NS&I left it to the Treasury to instigate these changes, and we are not confident that NS&I’s current management will listen to advice from Treasury appointees.
NS&I’s remedial actions are too little, too late. Despite some improvements in specific areas of capability, governance and risk management, recent work by NS&I’s consultants suggests that the Programme cannot be delivered by March 2028 when the Atos contract ends. NS&I is still trying to complete the Programme even earlier, with high-risk work on replacing the core banking engine still at an early stage. We are not convinced that even now NS&I has the realism needed for the Programme, and we are not confident that NS&I will deliver the Programme successfully.
Conclusions and recommendations
1. NS&I is over-confident about its ability to deliver its Business Transformation Programme (the Programme), has no workable plan, and no idea of eventual cost. The Programme is late and is yet to deliver meaningful benefits, despite NS&I spending £111 million on the Programme by 31 March 2024. After five years, NS&I still has no agreed and approved integrated plan, and has no realistic estimate of what the Programme will cost. The NAO report identified underlying causes of the Programme’s problems, including not understanding the interdependencies of critical tasks before making key decisions nor having a plan taking account of those interdependencies. NS&I still claims to be confident that it can deliver the Programme to an ambitious timetable, with little evidence to support its confidence. A draft integrated plan produced for NS&I in late 2025—far too late for a Programme which started in 2020—indicated the Programme would not be delivered before March 2028 and would cost more than the budget available. We are not convinced that NS&I’s response, to try and compress the work and deliver the Programme even faster, is realistic. In December 2025, The Treasury appointed David Goldstone, previously Chair of the Office for Value for Money, to advise it on Programme progress.
recommendation
a. NS&I should stop trying to compress work to deliver the Programme by March 2028. It should prepare a realistic bottom-up integrated plan with a timetable and associated estimated costs and budget, to be reviewed by its non-executives, Mr Goldstone and the Treasury for realism.
b. Within six months, NS&I should write to the Committee setting out the details of the integrated plan including timelines, and a revised estimated cost of the Programme.
2. NS&I’s positive news culture has meant it has not learned lessons, which has affected its ability to deliver the programme. NS&I told us that that it promotes a “can do” attitude and culture; while this has benefits in encouraging commitment to NS&I and to transformation, NS&I acknowledges that it has been over-confident about its ability to deliver the Programme. The Government Internal Audit Agency’s December 2024 review of NS&I’s culture found that its leaders were not taking responsibility for taking action to address issues raised. NS&I says it understands that its transformation will require a change in mindset and accountability, but it was not able to tell us how it would do this. Instead, when asked about a “positive news culture” which can result in decisions not made and disagreements not resolved, NS&I’s leadership continued to emphasize positive scores from staff engagement surveys. As these surveys only capture employees’ views, it does not give it an external perspective. The external organisations that have reviewed the programme told the NAO that NS&I was often slow to act on advice, or did not act.
recommendation
NS&I should seek positive attestation from NS&I non-executive directors and from the Treasury, that:
- NS&I has implemented recommendations from the culture review and other recent reviews; and that
- NS&I’s leadership has demonstrably learned lessons as the Programme has progressed
3. It has taken NS&I far too long to develop a risk management framework, which has left the taxpayer exposed to unacceptable risks. NS&I launched multiple procurements and planned to deliver four transitions in parallel with no understanding of the risks this was exposing the organisation and its customers to. The programme was rated high-risk by external reviews on several occasions, but NS&I has not shown it can manage the risks effectively. In 2025, NS&I implemented a new Risk Management Framework, but it is not yet fully embedded. There are still many risks for the Programme to manage, for example the replacement of core banking engine is extremely high risk, but the main work has yet to start. NS&I is bringing in skills through its new System Integrator (CapGemini), but it is not yet clear that NS&I is listening to what it has to say about the realism of the timetable and the delivery risks. Programme governance has been strengthened, with the Treasury instigating the main changes by appointing new non-executive directors to NS&I, establishing a new committee to scrutinise the programme and by appointing David Goldstone in an advisory capacity.
recommendation
a. NS&I should ask Mr Goldstone to review how the Programme is applying the new risk management framework, and identify what additional support is needed.
b. By June 2026, NS&I should write to the Committee setting out the progress implementing its risk management framework, and how NS&I will strengthen and fully embed the framework in its operations.
4. NS&I has failed to support the Programme with the skills and expertise it needs to deliver successfully. As an organisation with most of its operations contracted out to Atos, it is not surprising that NS&I had limited experience of digital transformation when starting the Programme. NS&I told us it has found it difficult to recruit the additional skills and capability the Programme needs. Since 2024, NS&I has added capability at senior levels, for example, by appointing a new commercial director, but it still relies on consultants to fill skills gaps. NS&I has made very substantial (£43 million) use of consultants in the Programme, but was vague about how it holds consultants to account. NS&I said it has more staff now, but it still does not have a resource management strategy in place. NS&I will continue to rely on Atos, which suffered financial distress in 2024, until at least 2028. NS&I told us it now has a contract management framework to manage Atos and the contracts with new suppliers, but it will need to be much better at managing supplier contracts to maximise the benefits of transformation.
recommendation
Within six months, NS&I should write to the Committee setting out its resource management strategy, including use of consultants, and how it will ensure that it manages consultants effectively. NS&I should also set out more clearly how it will manage suppliers and contracts, to manage risks in moving to the multi-supplier model.
5. NS&I’s governance structures still do not have the performance metrics and information needed to hold the Programme to account. It is difficult to establish the cost of the Programme from the information provided by NS&I. The Treasury told us that, outside the times where it was being asked to approve a formal business case, it found it challenging to understand the cost and progress being made by the Programme. The NS&I witnesses could not tell us how much had been spent on the Programme to date, which is deeply concerning. NS&I said it had improved its financial reporting and had ‘the right data’, but was finding it challenging to take the data from its system and to ‘present’ it. NS&I’s annual report and accounts state that it is meeting its overarching corporate metrics, including the important measure of how much finance it raises for government; but those metrics do not cover Programme progress. There are risks to NS&I’s whole business—and especially to customers—if the Programme is unsuccessful, and NS&I needs to show greater transparency in how the Programme is progressing.
recommendation
NS&I should set out how it will amend its overall reporting, both internally and externally, to include additional metrics around the Programme including its cost and progress.
6. The programme had suffered several serious setbacks before the Treasury gave it the attention it deserved. While NS&I is responsible for the Programme, the Treasury is NS&I’s sponsor department and, given its wider role in promoting good practice in managing major programmes and the high risk that the Programme delivery carried, we would have expected the Treasury to have been more heavily involved from the start. The Treasury had applied its usual scrutiny to the Programme’s Outline Business Case in 2020 and Full Business Case in 2023, approving each subject to conditions, but there were no consequences for not delivering. The Treasury that has been more interventionist since 2024, and told us it acknowledged that it should have intervened much earlier in the Programme. The Treasury expects NS&I to say whether it can deliver within budget when it has an agreed integrated plan, but was vague on how it would assess requests for more funding. We are concerned if further funding were to be approved without real assurance that NS&I can demonstrate it has a realistic plan.
recommendation
a. The Treasury should report to the Committee setting out more clearly how it will assess NS&I agreed integrated plan, including the sufficiency of its budget for the Programme.
b. The Treasury should set out what it has learned from its oversight of NS&I’s Programme, and examples of what it has changed in how it looks at government activities more generally.
1 Causes of failure to deliver the Programme
Introduction
1. On the basis of a report by the Comptroller and Auditor General, we took evidence from National Savings & Investments (NS&I) and from HM Treasury (the Treasury) on NS&I’s Business Transformation Programme.1
2. National Savings & Investments (NS&I) borrows, on behalf of the government, from retail investors through the issue and sale of savings and investments products such as Premium Bonds. It is one of the largest savings organisations in the UK with some 25 million customers, who have collectively over £240 billion invested with NS&I. The Treasury sponsors NS&I and oversees its operations.2
3. Since 1999, NS&I had outsourced much of its operations to Atos. NS&I formally launched its Business Transformation Programme, originally called Project Rainbow, in 2020 to replace this arrangement with multiple smaller contracts. Through the Programme, NS&I aims to reduce cost and make itself a self-service digital business. The Programme aimed to award five separate contracts, with most services transitioned by the end of Atos’s contract in March 2024. These included a contract to operate the core banking system that manages all NS&I products including Premium Bond prize draws.3
4. The Programme is late and over budget. In 2022–23 and 2023–24, the programme was rated ‘red’ meaning successful delivery of the project appears to be unachievable and NS&I reset the Programme in 2024. By March 2024, the date NS&I originally set for the Programme to end, none of the new services had been modernised or were live. Total costs for the Programme, including running costs, were estimated in December 2024 at £3.0 billion, an increase of £1.3 billion from 2020 estimates.4
5. The NAO found that there were four main causes of why the Programme did not progress as intended: NS&I had a weak understanding of the highly integrated system it was seeking to replace; it did not have an integrated plan; it lacked the capability needed for this type of Programme; and it awarded contracts without a good enough understanding of the dependencies.5
Setting an over-ambitious timetable
6. Previous Committee reports have noted that major transformation programmes are particularly complex, and the NAO’s reports over the last decade have shown that government’s attempts at digital transformation have had mixed success.6 NS&I formally started its Programme in 2020, with the aim of completing the transition to a new multi-supplier model by March 2024, when its contract with Atos was due to end. The Programme has experienced substantial difficulties since 2022. It is late and over budget, and is yet to deliver meaningful transformation of NS&I’s services.7 NS&I reset the Programme in 2024.8 NS&I now views March 2028, when the (now extended) Atos contract is due to end, as the Programme end-date.9 In 2025, the Treasury appointed David Goldstone CBE, previously Chair of the Office for Value for Money, to help deliver the Programme, and told us it had asked him to pick up explicitly on the issues coming out of the NAO report.10
7. We asked NS&I why it had been trying to do such a complex Programme, splitting operations undertaken by a single supplier into a multi-supplier model, in such a risky way. The NAO report shows that NS&I original planned expected four transition stages to happen largely at the same time, and NS&I accepted that it was originally trying to do too much at once, and that it should have recognised this before 2024, taken a step back and re-evaluated, and made sure that it had a viable implementation plan. NS&I said it originally wanted to do things in a more sequential way, and suggested it had been forced to change approach when it had been unable to award a contract (for the second phase, customer experience) as planned.11
8. In December 2025, after five years, NS&I still has no agreed and approved integrated plan to indicate a Programme end date and milestones. NS&I has repeatedly failed to deliver such a plan.12 At our session in December 2025, NS&I said its system integrator Capgemini had now developed a draft plan, which showed that the Programme would run beyond March 2028. NS&I is now doing a re-planning exercise to try and compress the work and bring this end date forward. NS&I said it would take advice from David Goldstone on this work.13 NS&I could not tell us how much the plan would need to be adjusted, but claimed this would add months not years, and said it was aiming to finish its replanning by March 2026.14 This would leave just two years to complete the Programme before the Atos contract is due to end in March 2028.15 When pressed for whether it could deliver before the Atos contract ends, NS&I acknowledged it would look at extending the Atos contract, potentially to 2031, which would imply a further delay of 3 years and additional cost from the longer timeframe.16
9. In the absence of a complete and approved integrated plan, NS&I was unable to provide us with an updated estimate of Programme costs. It had spent £111 million on the Programme by March 2024, but could not give us a newer spend-to-date figure in our December 2025 evidence session, despite telling us it had the financial data to “make the right decisions at the right point”.17 It claimed to have the “routes, mechanisms and people” to deliver the Programme to the plan that it has not yet finalised, but also told us that it had not yet completed a “reset” of the commercial contracts so there is not yet “real solidity” of the milestones and deliverables; this means costs could increase further.18 NS&I agreed that the Programme cost would likely exceed the available budget, and expects to discuss this with the Treasury.19 The Treasury was clear that there would need to be further discussions with Ministers should NS&I require additional budget to that agreed in the spending review.20 This means NS&I could not give us any confidence that it yet has reliable estimates of how much the programme would cost. It could only point to the work in progress on the integrated plan, that might allow it to do so by March 2026.21
10. Despite the lack of information on timetable and cost, NS&I claimed it was confident that it could find a way to deliver the Programme by 2028, by “deprioritising” some aspects of the Programme.22 When asked how it could be confident without an agreed integrated plan, NS&I could only say this was a “good question”.23 NS&I acknowledged it should have appointed a “big, heavyweight” systems integrator earlier, and said this could have improved its planning process.24 When asked what evidence or assessment had led it to conclude that the Programme’s approach of introducing multiple contracts to manage would be easier than managing one large contract, it had no answer, other than there were benefits of being able to switch suppliers in future.25
11. When we asked if decisions were being taken based on evidence, NS&I said that “there is always a chance that assumptions are incorrect”.26 The National Infrastructure and Service Transformation Authority had found that NS&I’s understanding of the alternative approaches had not been robust, and NS&I said its understanding had improved since the Programme started. However, it also sought to blame Atos’s financial difficulties, saying it had needed to spend time, energy and resources developing continuity plans instead of on the Programme.27 NS&I dismissed suggestions that it should have done more work at the start, saying “you can always do more analysis”, and appeared to blame suppliers for not bidding for Programme contracts.28
A good news culture can prevent lessons being learnt
12. The external organisations that have reviewed the programme told the NAO that NS&I was sometimes or often slow to act, or did not act at all, on advice.29 We asked whether NS&I’s leadership had learned from the issues with the Programme. NS&I offered two lessons: it acknowledged that it had over-estimated the complexity of the Programme; but then claimed there was a positive lesson because it had continued to operate the organisation as a whole despite the delays.30 When asked if it regretted that more money was being spent on the Programme instead of being available for improving public services, it could only reiterate how much funding NS&I had raised for government through its activities.31
13. We asked the chief executive if he was creating a ‘good news’ culture, which the NAO has identified as a factor in why programmes resets may not work, and which can lead to a situation where decisions are not made and disagreements between stakeholders are not resolved. He told us that having a “can-do” attitude meant NS&I staff were committed to its objectives and transformation, which was “invaluable”, and he was pleased to see higher scores on NS&I’s recent annual staff engagement survey.32 But these scores do not give a full view of the lack of progress on the Programme because the survey only covers NS&I employees and not the large number of suppliers working on the Programme, meaning NS&I is missing an external perspective.33 We questioned whether NS&I had taken action to ensure a “good news culture” did not prevail, but NS&I gave us no details, and could only acknowledge the importance of the tone set from the top.34 NS&I conceded there had been occasions when its culture led to staff being overly optimistic about the delivery of the Programme.35
14. The Government Internal Audit Agency’s review of NS&I’s culture in December 2024, found that staff felt decision-making was slow and hierarchical, decision-making processes were not understood, and there was a lack of transparency within Programme processes.36 NS&I introduced a leadership development programme as a response to the review, and NS&I said that from this it had found that where issues were raised, “there was not always recognition that those leaders in the room were going to address those issues and drive it forward”. NS&I noted that moving to a multi-supplier model takes a shift in mindset and accountability, and that strategic workforce planning and management is a key part of how it continues to develop that capacity to get the change.37
2 Conditions for success
Improving understanding and management of risk
15. In taking forward the Programme, NS&I launched multiple procurements and planned to deliver four transitions in parallel, with no understanding of the risks that this was exposing the organisation and its customers to. NS&I said it had identified supply chain risk as a key area of focus.38 However, NS&I focused more on how it had handled past issues, telling the Committee how it had developed contingency plans when Atos had financial difficulties in 2023; it did not provide evidence that it had considered how to manage the current contracts.39 When asked if it was confident that it had resolved the issues with procurements, NS&I could only say that it had awarded contracts. NS&I acknowledged that these still contain the original milestone dates, which would need to be changed to take account of delays in NS&I’s Programme implementation.40
16. There are still many risks for the Programme to manage, for example the replacement of the ‘core banking engine’ is extremely high risk, but the main work has yet to start.41 NS&I agreed that when it replaced its banking engine, data migration would be a “huge consideration”, and said it knew this would need to be managed “in minute detail”, but gave no details of how it would do this. NS&I’s contract with Atos to run the banking engine expires in 2028, and it will need a new contract after then to ensure continuity.42
17. In 2025, NS&I implemented a new Risk Management Framework, but has not yet fully embedded the framework throughout its organisation.43 We wanted assurance that this framework is good enough to ensure that risks to customer data could be managed, and NS&I claimed it was “comprehensive”.44 NS&I did say that it had improved its risk management processes through greater involvement of its risk directorate, but also said that it was relying on GIAA, as “we accept that we do not have all the expertise in these areas”.45 GIAA is intended to be an internal audit function which should be assuring risk management, rather than doing the work.
Having the right skills and capability to deliver the Programme
18. NS&I had most of its operations contracted out when starting the Programme, and it had limited capability to deliver a digital transformation.46 NS&I told us it has found it difficult to recruit the additional skills and capability the Programme needs. It has made substantial use of consultants in the Programme, spending £43 million on advice.47 NS&I has found it particularly difficult to recruit technical roles, and is using secondments and temporary staff from other departments and the private sector, saying “it would not have made sense” to recruit into permanent roles.48 Since 2024, NS&I has added capability at senior levels, for example, by appointing a new commercial director, but it still relies on consultants to fill skills gaps.49
19. We pushed NS&I to tell us if it now had the skills and capability it needed. NS&I acknowledged that it had needed to bring in more capability, including in systems integration and at senior levels.50 It also, eventually, recognised that for a Programme “this big and complex, we will not have all the skills”. NS&I said it now has non-executive directors with private sector experience of digital transformation. The Treasury added that appointing non-executive directors (NEDs) was giving it more confidence that costs were being managed by NS&I.51 The Treasury also noted that as this was a complex programme, a systems integrator is “very necessary”.52 This had not been in place from the start, and we noted that not managing systems integration is the cause of problems on other programmes.53
20. NS&I said it was now developing a plan for workforce management in a more structured way, but did not provide details.54 It had identified the need to transfer knowledge from consultants to permanent staff.55 Its recruitment increased the NS&I headcount from around 200 to over 350 people.56 This includes increasing its commercial team fourfold.57 It said this increase was temporary, and that its target was 270 people.58 NS&I tried to claim that the additional costs of these extra people were built into the budget, but we were sceptical of this given that NS&I’s latest cost estimate is from 2024.59 We noted that adding more skilled capability would increase costs; while NS&I initially claimed this was accounted for in its estimates, it later acknowledged that the longer timeframe would mean that costs would increase.60
21. NS&I will continue to rely on Atos, which suffered financial distress in 2024, until at least 2028. NS&I told us it now has a contract management framework to manage Atos and the contracts with new suppliers. NS&I will need to be much better at managing supplier contracts to maximise the benefits of transformation.61 NS&I told us it now had an additional 75 to 80 people with technical skills from the system integrator.62 When asked how it was judging supplier performance, it said it was paying based on interim milestones, which were being met although it also knows that these will need to be reset in future.63
3 Governance
Improving Programme governance and financial reporting
22. NS&I has its own accounting officer and its own Board, and is responsible for the Programme, while the Treasury is NS&I’s sponsor in government and also has a role overseeing major programmes across government.64 The Treasury told us that it has to judge how it provides this oversight, operating an “earned autonomy model”, so that “If everything is going well, we will leave it more alone, and if not, we will intervene”.65
23. The NAO found that the Treasury has increased its scrutiny of the Programme since 2024, and had instigated changes to governance, including appointing new NEDs.66 The Treasury noted that it has now moved to a “quite interventionist” approach, but agreed that this could have happened earlier.67 Although the Treasury knew that the programme was already rated “red” in Infrastructure and Projects Authority’s 2022–23 annual report, it took until 2024 to get a grip on the programme and appoint new NEDs, a new chair of the transformation board and, in November 2025, asking Mr Goldstone to look at the programme.68
24. NS&I said its governance structures had evolved, and it would add more NEDs. It said these changes were improving delivery, but gave no substantive answer to how its governance would ensure problems did not happen again. It also acknowledged that there was still a lack of clarity over the role of governance boards, and said it was again reviewing governance, as a result of the NAO report, to help the programme “deliver at pace”.69 NS&I said that it had only now started reporting programme costs to its transformation and audit committee, which was generating useful insight.70 NS&I said it now added 6 more people in its finance function, an increase of 20%.71
25. The NAO reported that it was challenging to establish the cost of the Programme from the information NS&I provided. NS&I said it was working on improvements to its cost data for its next business case this.72 The Treasury said it had been satisfied by the spend data in each business case it approved, but there was a lack of clarity at other times.73 When challenged on its understanding of cost data, NS&I said it had “access to the information”, but that legacy systems meant it still has “”some more work to do in terms of how we how we present that information”, and that it was “working through” these issues as it developed the new Programme plan.74 It considered that it had made “significant changes” over the last six to eight months, and said it was “good” that GIAA had rated its financial controls as “moderate”.75 GIAA defines “moderate” as meaning “some improvements are required to enhance the adequacy and effectiveness of the framework of governance, risk management and control”.76
26. The Treasury told us that the lack of transparency from NS&I had made it difficult for the Treasury to understand the reasons for the cost increases, saying it was not always clear whether the funding NS&I received was being used on the Programme or running NS&I. It also said NS&I had been “sluggish” to respond to conditions that the Treasury had set as part of the business case approval.77 NS&I told us that the transformation programme affects its whole business, including all its IT, operations, customer services and products. It claimed it was able to give the information on cost to the NAO, but the NAO report says it had proved “challenging to identify spend to date, and forecast spend for the remainder of the Programme”, and the cost estimates should be “treated with caution”.78
27. NS&I’s annual report and accounts state that it is meeting its overarching corporate metrics, including the important measure of how much finance it raises for government. There are risks to NS&I’s whole business and to its customers if the Programme is unsuccessful. NS&I agreed that its overall corporate metrics did not measure progress on the Programme. This is despite the risks to customer data and NS&I operations. It accepted that disruption from the Programme could impact NS&I’s operations, but claimed that measuring progress might not “add anything”, despite the Programme taking a lot of senior management time, and suggested delays only impact the “perception” of performance.79
The role of the Treasury
28. The Treasury had applied its usual scrutiny to the Programme’s Outline Business Case in 2020 and Full Business Case in 2023, approving each subject to conditions.80 The Treasury said it had been satisfied by the spend data in the business case it approved, but the NAO found that there were errors in the spend reported.81 The Treasury told us it had thought it had clarity on the programme spend when approving the business case, but between business case approvals it had less clarity over spend, the Treasury agreed that money spent on the Programme is not available for other public service.82 The Treasury noted that determining whether the programme is within budget depends on the plan being developed by NS&I.83
29. The Treasury said its spending review controls require the lead NED on the transformation committee to assure Ministers that the finances of the programme are under control.84, and it now seeks quarterly affirmation from NS&I NEDs on progress before releasing funds.85 We asked the Treasury how NS&I could deliver the programme if the budget had been fixed before the outcome was determined. The Treasury reiterated that the programme needed a plan first, and denied that if NS&I asked for more funding beyond agreed amounts it would automatically get it.86 It acknowledged that Ministers would need ultimately decide whether to increase the budget later, and would expect NS&I to present options for meeting the budget set at the spending review.87
Formal minutes
Monday 9 February 2026
Members present
Sir Geoffrey Clifton-Brown, in the Chair
Mr Clive Betts
Anna Dixon
Rachel Gilmour
Sarah Olney
Blake Stephenson
Matt Turmaine
Declaration of interests
The following declarations of interest relating to the inquiry were made:
18 December 2025
The Chair declared the following interest: Holder of premium bonds.
NS&I’s transformation programme
Draft Report (NS&I’s transformation programme), proposed by the Chair, brought up and read.
Ordered, That the draft Report be read a second time, paragraph by paragraph.
Paragraphs 1 to 29 read and agreed to.
Summary agreed to.
Conclusions and recommendations agreed to.
Resolved, That the Report be the Sixty-seventh Report of the Committee to the House.
Ordered, That the Chair make the Report to the House.
Ordered, That embargoed copies of the Report be made available (Standing Order No. 134).
Adjournment
Adjourned till Thursday 12 February at 9.30 a.m.
Witnesses
The following witnesses gave evidence. Transcripts can be viewed on the inquiry publications page of the Committee’s website.
Thursday 18 December 2025
Dax Harkins, Chief Executive, National Savings and Investments; Matthew Smith, Programme Senior Responsible Officer, National Savings and Investments; James Bowler CB, Permanent Secretary, HM Treasury; Sam Beckett, Chief Economic Adviser and Second Permanent Secretary, HM Treasury; Stephen Farrington, Director of Fiscal Policy, HM TreasuryQ1-82
Published written evidence
The following written evidence was received and can be viewed on the inquiry publications page of the Committee’s website.
NTP numbers are generated by the evidence processing system and so may not be complete.
1 Buziuk, HlebNTP0002
2 Fraser, Dr AnthonyNTP0001
List of Reports from the Committee during the current Parliament
All publications from the Committee are available on the publications page of the Committee’s website.
Session 2024–26
|
Number |
Title |
Reference |
|
66th |
Tackling fraud and error in benefit expenditure 2024-25 |
HC 1231 |
|
65th |
Efficiency and resilience of the Probation Service |
HC 1235 |
|
64th |
Costs of clinical negligence |
HC 1234 |
|
63rd |
Increasing police productivity |
HC 1239 |
|
62nd |
Faulty energy efficiency installations |
HC 1229 |
|
61st |
Financial sustainability of children’s care homes |
HC 1233 |
|
60th |
DWP follow-up: Autumn 2025 |
HC 1447 |
|
59th |
Ministry of Justice follow-up: Autumn 2025 |
HC 1240 |
|
58th |
Government services: Identifying costs |
HC 1421 |
|
57th |
Government services: Generating income |
HC 890 |
|
56th |
BBC Accounts and Trust Statement 2024–25 |
HC 1230 |
|
55th |
Reducing NHS waiting times for elective care |
HC 820 |
|
54th |
Afghanistan Response Route |
HC 1391 |
|
53rd |
Cost of maintaining the FCDO’s overseas estate |
HC 884 |
|
52nd |
Resilience to threats from animal disease |
HC 885 |
|
51st |
The UK’s F-35 stealth fighter capability |
HC 1232 |
|
50th |
Local bus services in England |
HC 892 |
|
49th |
Administration of the Civil Service Pension Scheme |
HC 888 |
|
48th |
Smarter delivery of public services |
HC 889 |
|
47th |
First Annual Report of the Chair of the Committee of Public Accounts |
HC 1300 |
|
46th |
Improving local areas through developer funding |
HC 886 |
|
45th |
Improving family court services for children |
HC 883 |
|
44th |
Governance and decision-making on major projects |
HC 642 |
|
43rd |
MoD’s oversight of Reserve Forces’ and Cadets’ Associations |
HC 893 |
|
42nd |
Water sector regulation |
HC 824 |
|
41st |
UK Research and Innovation |
HC 826 |
|
40th |
Collecting the right tax from wealthy individuals |
HC 827 |
|
39th |
Government’s use of private finance for infrastructure |
HC 821 |
|
38th |
Increasing teacher numbers: Secondary and further education |
HC 825 |
|
37th |
Immigration: Skilled worker visas |
HC 819 |
|
36th |
Jobcentres |
HC 823 |
|
35th |
Introducing T Levels |
HC 822 |
|
34th |
Department for Business and Trade Annual Report and Accounts 2023-24 |
HC 818 |
|
33rd |
Supporting the UK’s priority industry sectors |
HC 1070 |
|
32nd |
The Future of the Equipment Plan |
HC 716 |
|
31st |
Local Government Financial Sustainability |
HC 647 |
|
30th |
Antimicrobial resistance: addressing the risks |
HC 646 |
|
29th |
Condition of Government property |
HC 641 |
|
28th |
Decommissioning Sellafield |
HC 363 |
|
27th |
Government’s relationship with digital technology suppliers |
HC 640 |
|
26th |
Tackling Violence against Women and Girls |
HC 644 |
|
25th |
DHSC Annual Report and Accounts 2023-24 |
HC 639 |
|
24th |
Government cyber resilience |
HC 643 |
|
23rd |
The cost of the tax system |
HC 645 |
|
22nd |
Government’s support for biomass |
HC 715 |
|
21st |
Fixing NHS Dentistry |
HC 648 |
|
20th |
DCMS management of COVID-19 loans |
HC 364 |
|
19th |
Energy Bills Support |
HC 511 |
|
18th |
Use of AI in Government |
HC 356 |
|
17th |
The Remediation of Dangerous Cladding |
HC 362 |
|
16th |
Whole of Government Accounts 2022-23 |
HC 367 |
|
15th |
Prison estate capacity |
HC 366 |
|
14th |
Public charge points for electric vehicles |
HC 512 |
|
13th |
Improving educational outcomes for disadvantaged children |
HC 365 |
|
12th |
Crown Court backlogs |
HC 348 |
|
11th |
Excess votes 2023-24 |
HC 719 |
|
10th |
HS2: Update following the Northern leg cancellation |
HC 357 |
|
9th |
Tax evasion in the retail sector |
HC 355 |
|
8th |
Carbon Capture, Usage and Storage |
HC 351 |
|
7th |
Asylum accommodation: Home Office acquisition of former HMP Northeye |
HC 361 |
|
6th |
DWP Customer Service and Accounts 2023-24 |
HC 354 |
|
5th |
NHS financial sustainability |
HC 350 |
|
4th |
Tackling homelessness |
HC 352 |
|
3rd |
HMRC Customer Service and Accounts |
HC 347 |
|
2nd |
Condition and maintenance of Local Roads in England |
HC 349 |
|
1st |
Support for children and young people with special educational needs |
HC 353 |
Footnotes
1 C&AG’s Report, National Savings & Investments’ Business Transformation Programme, Session 2024–26, HC 1379, 14 November 2025
2 C&AG’s Report, paras 1, 2
3 C&AG’s Report, paras 3, 4 and Figure 2
4 C&AG’s Report, para 10
5 C&AG’s Report, para 13
6 Committee of Public Accounts, Government’s relationship with digital technology suppliers, Twenty-Seventh Report of Session 2024–25, HC 640, 6 June 2025, para 2; C&AG’s Report, Government’s approach to technology suppliers: addressing the challenges, Session 2024–25, HC 543, 16 January 2025, para 3
7 C&AG’s Report, para 10
8 Q 1
9 C&AG’s Report, para 10
10 Qq 5, 15
11 Q 11; C&AG’s Report, Figure 6
12 C&AG’s Report, paras 14 and 3.15
13 Qq 19-20
14 Qq 12, 74-75
15 Qq 12-13; C&AG Report para 10
16 Qq 76-77
17 Qq 18, 56, 79
18 Qq 23-25
19 Qq 13, 25
20 Q 27
21 Q 12
22 Q 21
23 Q 23
24 Qq 1-2
25 Q 6
26 Qq 7-8
27 Q 9
28 Qq 10-11
29 C&AG’s Report, para 19
30 Q 1
31 Q 4
32 Q 45; C&AG’s Report, para 3.5
33 Qq 50-51, 60-61
34 Qq 47-48
35 Q 46
36 C&AG’s Report, para 3.5
37 Q 49; C&AG’s Report
38 Qq 6, 11; C&AG Report, para 2.4 and Figure 6
39 Q 65
40 Q 22
41 C&AG’s Report, paras 20 and 24
42 Q 78
43 C&AG’s Report, para 3.23
44 Q 66
45 Q 63
46 C&AG’s Report, paras 8, 13
47 Q 67; C&AG’s Report, para 3.10
48 Qq 67, 69
49 C&AG’s Report, paras 3.10 and 3.11
50 Qq 22, 35
51 Qq 37-38
52 Q 70
53 Q 73; C&AG’s Report, paras 15 and 21
54 Q 22
55 Q 36
56 Qq 3, 22
57 Q 7
58 Qq 22-33
59 Qq 36, 79
60 Qq 23-24
61 C&AG’s Report, paras 11, 17
62 Q 22
63 Qq 23, 58-59
64 C&AG’s Report, para 2
65 Q 69
66 C&AG’s Report, paras 21, 3.18
67 Qq 69, 16
68 Q 16; Infrastructure and Projects Authority Annual Report 2022–23, July 2024
69 Qq 52-53
70 Q 18
71 Q 55
72 Q 57; C&AG’s Report, para 9
73 Q 17
74 Qq 56-57
75 Qq 18, 54-55
76 C&AG’s Report, Figure 9
77 Q 16
78 Q 18; C&AG’s Report, para 9
79 Qq 62-64
80 Q 18; C&AG’s Report, Figure 9
81 Q 17; C&AG’s Report, para 9
82 Qq 18, 39, 42
83 Q 44
84 Q 16
85 Q 42
86 Q 26
87 Qq 27-31