House of Lords portcullis
House of Lords
Session 2002 - 03
Publications on the Internet
Judgments

Judgments - Sage (Respondent) v. Secretary of State for the Environment, Transport and the Regions and others (Appellants)

HOUSE OF LORDS

SESSION 2002-03
[2003] UKHL 22
on appeal from: [2001] EWCA Civ 1100

OPINIONS

OF THE LORDS OF APPEAL

FOR JUDGMENT IN THE CAUSE

Sage (Respondent)

v.

Secretary of State for the Environment,
Transport and the Regions and others (Appellants)

ON

THURSDAY 10 APRIL 2003

The Appellate Committee comprised:

Lord Nicholls of Birkenhead

Lord Hope of Craighead

Lord Hobhouse of Woodborough

Lord Scott of Foscote

Lord Rodger of Earlsferry


HOUSE OF LORDS

OPINIONS OF THE LORDS OF APPEAL FOR JUDGMENT

IN THE CAUSE

Sage (Respondent) v. Secretary of State for the Environment, Transport and the Regions and others (Appellants)

[2003] UKHL 22

LORD NICHOLLS OF BIRKENHEAD

My Lords,

    1. I have had the opportunity of reading a draft of the speech of my noble and learned friend Lord Hobhouse of Woodborough. I agree that, for the reasons he gives, this appeal should be allowed.

LORD HOPE OF CRAIGHEAD

My Lords,

    2. I have had the advantage of reading in draft the speech of my noble and learned friend Lord Hobhouse of Woodborough. I agree with it, and for the reasons which he has given I too would allow the appeal.

    3. As my noble and learned friend has explained, Mr Sage's primary argument at first instance was that the building was an agricultural building for which he did not need planning permission. This was a pure question of fact, and it was resolved against him conclusively by the inspector's finding that the building was not an agricultural building but was best described as a dwelling house that was in the course of construction.

    4. This led to the alternative argument that the notice was out of time because the operations that must be substantially completed for the purpose of section 171B(1) of the Town and Country Planning Act 1990 comprise the operations which constituted a breach of planning control, or (as it was put) the operational development, and not the whole operation of completing the dwelling house. The inspector's view was that the four year period did not begin until the whole operation of creating the dwelling house was substantially completed. He then held, treating the question as one of fact and degree, that the building in this case was not a substantially completed dwelling house. Here again the inspector's decision on the facts went against Mr Sage and the contrary is not longer arguable. The question which remains is whether the inspector was right when he said that the four year period did not begin until the whole operation of creating the dwelling house was substantially completed.

    5. Mr Sage's argument is that the reference in section 171B(1) to the date "on which the operations are substantially completed" has to be read in the light of the wording of the other relevant sections in the 1990 Act, and that by tracing the language of that subsection back through section 171A(1)(a) the reader is required to bring into account the definition of "development" in section 55(1) of the Act, those operations which section 55(2)(a) says are not to be taken to involve development and the definition of the word "building" in section 336(1). If this approach is right the position is, as Keene LJ explained in paras 27 -31 of his judgment, capable of being resolved quite simply by saying that what have to be substantially completed are those operations which amount to a breach of planning control and that operations and works which do not amount to development because they fall within section 55(2)(a) are not to be taken into account. On this approach, it does not matter that the inspector did not think that the building was a dwelling house. All one needs to find is that there is a building which has been erected in breach of planning control.

    6. I was initially attracted to this approach, as it seemed to me to be consistent with the language of the statute and to be unlikely, as Keene LJ said in para 32 of the judgment, to give rise to practical difficulties. But I have in the end been persuaded, with respect, that the language of the statute is open to a different interpretation and that it makes better sense of the legislation as a whole to adopt the holistic approach which my noble and learned friend has described. What this means, in short, is that regard should be had to the totality of the operations which the person originally contemplated and intended to carry out. That will be an easy task if the developer has applied for and obtained planning permission. It will be less easy where, as here, planning permission was not applied for at all. In such a case evidence as to what was intended may have to be gathered from various sources, having regard especially to the building's physical features and its design.

    7. If it is shown that all the developer intended to do was to erect a folly, such as a building which looks from a distance like a complete building - a mock temple or a make-believe fort, for example - but was always meant to be incomplete, then one must take the building when he has finished with it as it stands. It would be wrong to treat it as having a character which the person who erected it never intended it to have. But if it is shown that he has stopped short of what he contemplated and intended when he began the development, the building as it stands can properly be treated as an uncompleted building against which the four year period has not yet begun to run.

    8. It must be emphasised that it is not for the inspector to substitute his own view as to what a building is intended to be for that which was intended by the developer. But that was not what the inspector did in this case. It was not just that the building looked to him like a dwelling house that was in course of construction. His conclusion was supported, in his view, by an application which Mr Sage had made in 1994 to use the building for tourist accommodation and by his finding that that remained Mr Sage's stated intention. These matters were relevant to the question which he had to decide, and in my opinion he was entitled on the facts which he found to reach the conclusion which he did.

    LORD HOBHOUSE OF WOODBOROUGH

    My Lords,

    9. On 19th March 1999, the Maidstone Borough Council (the Council) as the relevant planning authority issued and served on Mr Sage an enforcement notice (the Notice) under Part VII of the Town and Country Planning Act 1990 (the Act). The Notice informed him that the Council considered that he was in breach of planning control in erecting (or, as later amended, partially erecting) a dwelling house and requiring its removal. Mr Sage appealed raising various grounds under s.174(2). Besides applying for planning permission ex post facto, the two main grounds of his appeal were firstly that the building was an agricultural building and did not require planning permission and, secondly, that the notice had been served outside the four year time limit permitted by s.171B(1), a section inserted into the Act by the Planning and Compensation Act 1991.

    10. Section 171B(1) provides:

    "  Where there has been a breach of planning control consisting in the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land, no enforcement action may be taken after the end of the period of four years beginning with the date on which the operations were substantially completed."

This provision followed the lead given by Mr Robert Carnwarth QC in his Report to the Secretary of State for the Environment (Enforcing Planning Control: February 1989) which called for greater simplicity and clarity in the law and procedures of enforcement which had become excessively technical and complex and open to evasion and abuse. There can be no doubt that the underlying purpose behind s.171B(1) was to introduce a single easily applied limitation period for operations. Section 171B(2) and (3) adopted in respect of change of use and other breaches four and ten year periods respectively, running in either case from the date of the breach.

    11. The point raised by this appeal by the Council to your Lordships' House concerns the construction of s.171B(1) and the starting point of the four year period - ie "the date on which the operations were substantially completed". Mr Sage contends that it means the date after which the building work remaining to be done would no longer itself involve a breach of planning control, because, if taken on its own, it would not require planning permission. The judge, Deputy Judge Ouseley QC, and the Court of Appeal summarised the point in a brief sentence:

    "  The building operations are complete when those activities which require planning permission are complete."

The Council on the other hand argue for a holistic construction, asking: has the building been substantially completed and, if so, when? The Council, like the inspector, adopt the passage in the Ministry Circular No.10/97, paragraph 280.

    "  ... in the case of a single operation, such as the building of a house, the four-year period does not begin until the whole operation is substantially complete. What is substantially complete must always be decided as a matter of fact and degree. … All the relevant circumstances must be considered in every case."

The inspector, deciding in favour of the Council and upholding the Notice, applied the latter approach; the judge and the Court of Appeal (Schiemann LJ, Keene LJ and Sir Murray Stuart-Smith), deciding in favour of Mr Sage, preferred the former.

    12. The inspector heard Mr Sage's appeal (together with two other appeals concerning the same parties) over the space of two days including a view of the relevant premises. Both parties were legally represented and adduced oral and written evidence. It was accepted by the Council that Mr Sage had not done any further building work on the relevant structure during the last four years before the Notice was served. It was also common ground that it was an 'operation' case falling within s.171B(1) not a change of use case under subsection (2).

    13. The inspector started by considering Mr Sage's contention that it was an agricultural structure and therefore he had never needed any planning permission to erect it. He considered how it was constructed and concluded that it was constructed with domestic not agricultural features, as a dwelling not as a building to be used for agricultural purposes. It was constructed with cavity block walls. Three elevations were clad with tiles and the fourth with timber boarding (but the cladding was incomplete). The entrance door and the fenestration were typical of a dwelling designed and constructed for human habitation not agricultural use. The external tile hung walls in his view supported the same conclusion. The building had an upper floor with further fenestration though no stairway had been installed. He applied the test of physical layout and appearance derived from Belmont Farm Ltd v MHLG (1962) 13 P&CR 417 and Mckay and Walker v Secretary of State for the Environment [1989] JPL 590.

    14. The inspector rightly did not investigate the intentions of Mr Sage at various stages in the history nor the uses he had made of the structure from time to time. The character and purpose of a structure falls to be assessed by examining its physical and design features. The relevance of the assessment is to determine whether or not the building operation is one requiring planning permission. The actual use made of the building does not alter the answer to be given. Keeping a pig in the sitting-room or hens in the kitchen does not turn a dwelling house into an agricultural building even if the humans move out. Permission for a change of use may have to be applied for but that would be a separate question. The starting point for considering the permitted use of a new structure is the character of the building for which permission has been given or does not require to be given: s.75(3) - " … the permission shall be construed as including permission to use the building for the purpose for which it is designed."

    15. He expressed his conclusion in the words:

    "  As a matter of fact and degree, I consider that, having regard to its layout and appearance, [this building] is not an agricultural building and was not designed as such. … [It] is best described as a dwelling house that is in course of construction."

Having read the evidence and considered the photographs which have been included in our papers, the inspector's conclusion on this point would seem to have been inevitable. Therefore that ground of appeal failed.

    16. This led on to Mr Sage's further ground for challenging the Notice, that it was out of time. The starting point is that the building is to be classified as an unfinished dwelling house. It was unfit for habitation. The floor at ground level consisted of rubble. There were no service fittings. There was no staircase. The interior walls were unfinished, without lining or plaster. None of the windows, including that on the upper floor, was glazed. One witness refers to the roof-light as being glazed. There was no guttering. Mr Sage had said in evidence that the building had originally been glazed but that the glass had been broken by vandals more than four years earlier and he had not replaced it. Mr Sage's evidence was contradicted by other evidence which was inconsistent with the windows ever having been glazed. It appears that the inspector probably did not accept Mr Sage's evidence on this point. But it was not critical to the inspector's decision nor to those of the judge and the Court of Appeal.

    17. On this state of the facts, the issue of the construction of s.171B(1) became critical and was the effective subject matter of Mr Sage's recourse to the jurisdiction of the High Court. On the argument of Mr Sage, it was necessary to consider whether the work needed to complete the structure as a dwelling house was such as of itself to require planning permission, a point which Mr Sage submitted was at least arguable and had not been taken into account by the inspector in arriving at his decision and therefore (as the judge ordered) his decision should be quashed and he be directed to reconsider the appeal against the Notice having regard to that factor.

    18. It is convenient to examine this argument at the outset although it is not the central point raised by this appeal. Section 57(1) in Part III of the Act provides that (subject to immaterial exceptions) "planning permission is required for any development of land". "Development" is defined in s.55 as meaning -

    "  the carrying out of building, engineering, mining or other operations in, on, over or under land ...."

Subsection (1A), added in 1991, amplifies this by providing that "building operations" shall include -

    "  (a)  demolition of buildings;

    (b)  rebuilding;

    (c)  structural alterations of or additions to       buildings; and

    (d)  other operations normally undertaken by a     person carrying on business as a builder."

Subsection (1) is subject to subsection (2) which so far as material provides -

    "  The following operations … shall not be taken for the purposes of this Act to involve development of the land -

    (a)  the carrying out for the maintenance, improvement or other alteration of any building of works which -

      (i)  affect only the interior of the         building, or

      (ii)  do not materially affect the external       appearance of the building

    .................."

Mr Sage submits that the work remaining to be done was all either internal work or work which did not materially affect the external appearance of the building.

    19. It would be a question of fact whether the external work still to be done would have had a material effect on the building's appearance. But that question would only become significant if the work was work carried out "for the maintenance, improvement or other alteration" of the building. Work carried out by way of completing an incomplete structure would not come within exception (a). So, once it has to be accepted, in accordance with the inspector's finding, that the structure was a dwelling house in the course of construction, it follows that the work would be properly described as work carried out in the course of completing the construction of the building. Exception (a) clearly contemplates and involves a completed building which is to be maintained, improved or altered. It follows that an essential element in the argument of Mr Sage is missing. He cannot on the facts of this case rely upon exception (a) to say that he would not still require planning permission to complete the structure because it would not have amounted to a "development" (the premise upon which his argument under s.171B is founded). The breach of planning control would not have been exhausted; it would be continuing.

    20. The Court of Appeal rejected this conclusion for two reasons. Keene LJ (in paragraph 26) said that so long as the structure had progressed to the stage where it could be said to have an interior, ie, as Mr Sage's counsel put it, say 3 or 4 walls and a roof, exception (a) could be applied and the developer could potentially take advantage of it. Schiemann LJ (in paragraph 37) thought that the Council's argument introduced a subjective element:

    "  I can see no policy reason why we should construe s.55(2)(a) as limited in its application to buildings which have been completed according to some notional plan."

I do not accept either argument. It is not a question of referring to 'some notional plan'. Ex hypothesi, the erection is an uncompleted dwelling house; what is involved is its completion as a dwelling house by carrying out works essential for a completed dwelling house. The approach of Keene LJ not only does violence to the language used in exception (a) but also would make a mockery of planning control by inviting abuse and evasion.

    21. Returning now to s.171B(1), it can be seen that the same words have been used by the draftsman to describe building operations as in s.55(1), inviting, it is said, the reader to read the two sections together. However it still does not equate the term 'operation' with the term 'development' as further appears from s.191. But the more important part of Mr Sage's argument is that such a cross-reference is required by the words: "Where there has been a breach of planning control consisting in the carrying out without planning permission of building ... operations ....". The phrase "the date on which the operations were substantially completed" should, he submits, be answered by asking when did those operations reach the stage at which no further breach of planning control was involved. He would then answer that question by reference to exception (a) in s.55(2). Section 171A(1) provides that -

    "  For the purposes of this Act ... carrying out development without the required planning permission … constitutes a breach of planning control"

He thus argued that the enforcement notice could only relate to breaches of planning control and that, once no further breach was involved in completing the development, there could be no further building operations to which an enforcement notice and s.171B could apply. Therefore the operations referred to in s.171B must have been completed.

    22. Again these arguments were accepted by the Court of Appeal. Keene LJ (at paragraph 31) said:

    "  I conclude that, as a matter of law, operations and other works which do not amount to development are not to be taken into account in deciding whether there has been substantial completion within the meaning of s.171B(1). As the deputy judge pointed out, where all the operations amounting to development have been carried out there is nothing remaining against which the local planning authority could take enforcement action."

Schiemann LJ added (at paragraph 38):

    "  I am presently inclined to the view (without the matter having been fully argued) that substantial completion has taken place when there is enough to enable a planning authority to judge whether or not the building has sufficient adverse effects to make it expedient to issue an enforcement notice."

The section might have been drafted as Schiemann LJ prefers but it was not. The criterion he suggests would fly in the face of the simplicity and clarity that the revisions of planning control law were seeking to achieve. As regards the reason given by Keene LJ and the judge, it involves giving a limited meaning to the phrase 'building operations', not its natural meaning, and does so on the basis of adopting an extended meaning to exception (a) which is open to the objections I have already referred to. But the most substantial objection to his approach is that it is contrary to the holistic approach upon which this part of planning law is based.

    23. When an application for planning consent is made for permission for a single operation, it is made in respect of the whole of the building operation. There are two reasons for this. The first is the practical one that an application for permission partially to erect a building would, save in exceptional circumstances, fail. The second is that the concept of final permission requires a fully detailed building of a certain character, not a structure which is incomplete. This is one of the differences between an outline permission and a final permission: s.92 of the Act. As counsel for Mr Sage accepted, if a building operation is not carried out, both externally and internally, fully in accordance with the permission, the whole operation is unlawful. She contrasted that with a case where the building has been completed but is then altered or improved. This demonstrates the fallacy in Mr Sage's case. He comes into the first category not the second.

    24. The same holistic approach is implicit in the decisions on what an enforcement notice relating to a single operation may require. Where a lesser operation might have been carried out without permission or where an operation was started outside the four year period but not substantially completed outside that period, the notice may nevertheless require the removal of all the works including ancillary works: Ewen Developments Ltd v Secretary of State for the Environment [1980] JPL 404, CA; Howes v Secretary of State for the Environment [1984] JPL 439, Hodgson J; Somak Travel v London Borough of Brent [1987] JPL 630 Stuart-Smith J. The first of these upheld a requirement that the whole of an embankment be removed. In the second the inspector had directed himself that the removal of a hedge and the creation of an access was "a continuous operation and each step in the work prolong[ed] the period for serving the enforcement notice as regards every earlier step of the development": the judge upheld the notice. The third case involved an unauthorised change of use case from residential to commercial use. The notice not only required the cessation of the commercial use but also the removal of an internal staircase which had been put in to facilitate that use though in itself the staircase had not required permission.

    25. These decisions underline the holistic structure of planning law and contradict the basis upon which the Court of Appeal reached its decision in favour of Mr Sage.

    26. Finally, it was argued for Mr Sage that the inspector should have had express regard to an inspector's decision letter reported in [1972] JPL 385 where the facts bore some similarity to those of the present case and he had held the enforcement notice to be out of time. However that decision was based upon the finding by the inspector that "the appeal building had become a viable building more than four years before [the] service of the notice and that in the form which it then took it [was] immune from enforcement action". The inspector's finding in the present case was that the structure was best described as a dwelling in the course of construction. The inspector was right to think that the 1972 decision did not help; indeed it was adverse to Mr Sage's case.

    27. Accordingly the inspector's decision was correct. The Notice had not been served after the end of the period of four years beginning with the date on which the building operations were substantially completed. Indeed they had still not been substantially completed at the date of the Notice. The appeal should be allowed and Mr Sage's CPR Pt.8 proceedings dismissed and the orders of the judge and the Court of Appeal set aside, including the costs orders made in favour of Mr Sage.

    28. Leave to appeal to your Lordships' House was given "on terms that, if successful, the petitioners do not seek any order for costs against the respondent". Accordingly no order will be made in respect the costs in this House or in the courts below.

LORD SCOTT OF FOSCOTE

My Lords,

    29. I have had the advantage of reading in advance the opinion of my noble and learned friend Lord Hobhouse of Woodborough and gratefully adopt his exposition of the facts and statutory provisions that have given rise to this appeal to the House. I, like your Lordships, have come to the conclusion that this appeal by Maidstone Borough Council should be allowed and I am in general agreement with the reasons expressed by Lord Hobhouse as to why that should be so. There is, however, an aspect of this case which seems to me unsatisfactory and I think I should explain what it is.

    30. The purpose of section 171B of the Town and Country Planning Act 1990 (added to the 1990 Act by amendment with effect from 2 January 1994: see s 4, Planning and Compensation Act 1991 and SI 1991/2905) was, as Lord Hobhouse has explained in para 10 of his opinion, to introduce a straightforward, easily applied, set of time limits within which enforcement action to remedy breaches of planning control must be brought. The section divides breaches of planning control into three categories.

 
continue