Select Committee on the Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 500 - 519)

  500. If we then move on to Maryland, the argument is somewhat different, if we can put up 011.[12] Mr Berryman will explain how the lifts would be provided here and, although it is costly, it is nowhere near as complicated or disruptive as works at Manor Park, but the real issue at Maryland is the one that we have already touched on which is its close proximity to Stratford and the ease by which people could get to Stratford who currently use Maryland. If we can put up 004 again, we have Maryland there (indicating) and Stratford there (indicating).[13] It is about a 600-metre walk, but, perhaps more importantly for people with reduced mobility, there are bus routes coming down here (indicating) going to Stratford and bus routes running from the east down here (indicating). That is the end of Romford Road that runs close to Manor Park as well coming down to Stratford, so for most of the catchment of Maryland they are actually very close to Stratford anyway and it is very easy for them to get to Stratford on the buses. The other point to make is that there is no parking at Maryland, whereas there is parking at Stratford, so for people coming on Dial-a-Ride or even by taxi or being taken by a member of the family or a carer, actually Stratford is the much better and more convenient station in any event.

  501. That is a very brief overview. Unless the Committee has any questions for me at this stage, I was going to hand over to Dr Maynard for her presentation.

  502. LORD SNAPE: Is that a bus-rail interchange at Stratford? Is it all within the same complex so getting from the bus to the train for people with disabilities is not going to be particularly difficult?

  503. MS LIEVEN: Getting from the bus to the train is extremely easy. There is a brand-new, well, I say `brand-new', it was built at the time that the Jubilee Line Extension was opened, but a very swish, new ticket hall, bus station, integrated interchange at Stratford, and I suspect that will be even further upgraded with the Olympics because of course Stratford is going to be the main station for the Olympics, so it is an all-singing, all-dancing, fully integrated public transport interchange. While Dr Maynard is giving her presentation, I will try and find a photo of it because I am sure we have one somewhere in the documents.

DR ALICE MAYNARD, sworn and examined

  504. MS LIEVEN: Perhaps we can put Dr Maynard's presentation up and, Dr Maynard, I am going to hand over to you to introduce yourself.

  (Dr Maynard) My Lords, I have been asked to talk to you today about the approach that Crossrail is taking to the provision of access for people with restricted mobility and I just wanted to talk a bit about that term `people with restricted mobility'. It is a European term that Crossrail has adopted and it includes not just disabled people, but also other people who have difficulty travelling, such as parents with pushchairs or people with luggage, anyone who is sometimes called `encumbered'. The terms that I am going to use in the presentation may actually vary because some of the presentation is going to address the needs of disabled people directly and specifically and some will address the needs of that broader population, people with restricted mobility, and sometimes I will use terms, such as `mobility impairment' if that is what I mean or `visual impairment' if that is what I mean, so the terminology will vary, and I hope I do not make it too confusing. A key focus of this presentation is going to be on step-free access and this is because thus far in the design process it has been appropriate to focus on step-free access. Step-free access benefits disabled people and other people who experience barriers in the physical environment, and it is particularly important for wheelchair-users and for some people with walking difficulties. Those that present an absolute barrier if there are steps, you just cannot use that particular facility. Crossrail is fully aware that not all disabled people are wheelchair users, and will take that into account in design. I am sorry if I reinforce that particular stereotype at the moment but that is because of the stage of design. I will come back to that later in the presentation.

  505. Before I begin I am just going to tell you a little bit about myself and my background. From 1998 to 2003 I was Head of Disability Strategy at Network Rail, and I was responsible for developing a strategy to make the rail network accessible, which involved working with industry regulators, train operators and disabled people.

  506. Since 2003 I have been running Future Inclusion. Future Inclusion's transport clients include: Transport for London, London Underground, Network Rail, some of the franchise bidders in the former Strategic Rail Authority. We have undertaken a range of projects for them looking at disabled people's transport needs and their inclusion in mainstream transport provision. My own personal transport experience as a user and as a consultant incorporates most modes, but in particular rail, bus, tram and underground.

  507. I was involved in developing good practice guidance for rail in relation to COST 335, which was the European project on accessibility to heavy rail systems, where I was a member of the Stations Working Group and I wrote the report chapters on: stations, information and training; and in relation to the Strategic Rail Authority's Code of Practice, which is now the Department of Transport's code of practice, into which I had significant input during my tenure at Network Rail.

  508. I have also been involved in developing good practice guidance for bus and rail operators in Ireland, jointly developing the Irish National Disability Authority's guidance document.

  509. Lastly, I recently competed a doctorate looking at access for disabled people in the appraisal process in major transport projects and provided the monetary valuation for certain access features. This says "currently researching"—in a sense that it is a lifetime's activity; I am indeed still currently researching the value of access.

  510. My role in Crossrail is as an inclusivity advisor and I was responsible for drafting the inclusivity policy, which covers all seven equality strands, including, disabled people, older people and men and women, and women in particular—three groups that have particular difficulty on the transport network.

  511. I now maintain a watching brief over the implementation of the policy as the project develops, but I have got a particular interest in accessibility because of the background that I have in the transport industry and in particular in rail. In this respect I complement the work of David Bonnett Associates who are architectural access consultants to the project. Both his company and mine have had input into the Crossrail Design Manual.

  512. I am going to talk briefly about the law because most of you will be familiar with the law that applies in the rail environment and thus to Crossrail, but I think it is worth going over it again because of the complexity of it.

  513. The Disability Discrimination Act 1995 as amended by the Disability Discrimination Act 2005 applies both to infrastructure and to vehicles. Stations are covered under Part III of the DDA and have been since the various Part III elements of the DDA were enacted between 1995 and 2004; so coverage of stations came in in stages. Vehicles are covered, as was mentioned earlier, under the Rail Vehicle Accessibility Regulations which were introduced under Part V.

  514. Although in the rail industry we often talk about compliance with the DDA, it is actually only possible to comply with the RVAR, the Rail Vehicle Accessibility Regulations, as there are no clear standards for station infrastructure with which we could comply; so we have to grasp the somewhat amorphous concept of good practice in order to conform to the DDA's requirements, which is the way that I prefer to word it.

  515. The level of service provided to disabled people has again always been covered in relation to stations under Part III and now, I can thankfully say, since the DDA 2005 was brought in it is covered on vehicles as well. So you cannot be refused or given a worse service on the train simply because you are a disabled person.

  516. The DDA's Part III provisions are anticipatory—that is to say, service providers should not wait until a disabled person needs to use their service, but they need to think about the needs of the range of disabled people who are likely to want to use the service and respond to them in advance.

  517. In addition, since the DDA 2005, we have a public sector duty which applies to public sector bodies and requires them to promote disability equality in all their functions. Planning would be one of these functions, the stage that Crossrail is at.

  518. The public sector duty applies to Crossrail's shareholders, Transport for London and the Department for Transport. Crossrail was incorporated into the Department for Transport's Disability Equality Scheme, which they published a couple of years ago, and undertook a disability impact assessment of its policies as part of that Scheme's preparation.

  519. LORD YOUNG OF NORWOOD GREEN: You talked about the difficulty of applying good practice. When you are applying it what do you use as analogous or comparative—Where do you look: the UK, Europe or internationally? How do you establish the benchmarks?
  (Dr Maynard) One of the things I discovered when we were doing the COST 335 work was that the UK is pretty much ahead of other countries in the world. I would say we are kind of up there with the best. When I use the term "good practice" I mean good practice in other sectors actually, so looking at the kinds of things that might be expected in some of the sectors that are perhaps a little in advance of the rail industry.



12   Crossrail Ref: P8, Maryland Station-Proposed details for the provision of PRM lifts (NEWMLB-53_04-011) Back

13   Crossrail Ref: P8, Maryland Station-Local bus services providing direct links to Stratford Station (NEWMLB-53_04-004) Back


 