Select Committee on the Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 6560 - 6579)

  6560. However, the works which Crossrail intend to carry out in this area, it now turns out, are no longer compatible with the approved redevelopment proposals. As I understand it, the powers they seek have not changed, but the way in which they actually intend to do it means that they are now no longer compatible. I think, to put it in a nutshell, what they take, although a relatively small part of the building, takes, as I understand it, a main access out. That this was the situation became clear to the Petitioner towards the end of last year and, as you have heard, as a result of that position, the Promoters have now agreed that they will, if they take, take the whole and they will do that, they say, if the Crossrail Bill is granted Royal Assent and funding for Crossrail is made available, and I will come back to that in a moment.

  6561. The lease to Lazard's expires on the June quarter day this year. Very, very briefly, the lease requires Lazard's to return the property to the condition it was in at the start of a lease of about 30 years. They will be doing some works, but those works will not make it lettable in the current market, so we have a position where, in order to achieve even short-term lettings in the current market, significant further works would be required and, when you see that in conjunction with the fact that after Royal Assent the property could be taken with a few months' notice, it is most unlikely that any viable letting of the office element will be possible. That is effectively accepted by the Promoters in the reference that you have already seen. The Promoters, as you know, my Lords, have up to five years from Royal Assent to decide whether to proceed and acquire the property. From June this year, the Petitioner's outgoings in relation to the site in terms of covering bank loan payments, empty rates, maintenance and ground rent will be something in the order of £6.45 million per annum. However, their income will be reduced from the order of £6 million to something less than £1 million once there is no longer the Lazard's lease, so, in very broad terms, Souzel will, therefore, face an annual deficit of over £5 million potentially for over five years and there is no certainty as to whether the property will be taken and, if it is taken, when it will be taken, and no application can be made to the Tribunal to assess compensation until notice to treat is served. If the property is not in the end taken at all, then there will be no compensation, so, if they wait for five years and then do not take it, no compensation. We believe that is an unacceptable and unfair position for Souzel to be left in because until such time as the Promoters decide either to start the process of acquisition or to announce they do not intend to proceed, we will suffer significant loss. We face great uncertainty as to the duration and extent of that loss without any recourse to the Lands Tribunal. This is not a case where the Petitioner will get any benefit from Crossrail because if Crossrail does go ahead, the property will be taken. This is not simply a case of an opportunity for re-development being delayed. The particular facts of this lease falling in now and the juxtaposition of Crossrail mean that the Petitioners are effectively being deprived of the benefit of the main element of the property from June this year. Their heavy ongoing liabilities remain and they have no recourse to compensation unless and until a decision is made to take the property and, for example, that makes it very difficult to plan sensibly how to deal with the loans. We believe that would be an extreme result and clearly outside the range of acceptable results. We believe that provision should be made to provide a fairer result.

  6562. My Lords, the simplest way for the result to be made fairer would be for the Promoters to undertake, or be required, to take the property earlier, ie soon after Royal Assent, I am not suggesting they take it before but soon after. I think it is still up on the screen, my Lords, the Promoter's document setting out the commitments. If you look at 4 and 5, first, funding has to be in place—I will come back to that—and, secondly, they will purchase the premises when satisfactory terms are agreed. There is nothing there that actually requires them to take it. It may be that we are not so far apart as we thought. If there was certainty that it would be taken relatively soon, that would significantly reduce the uncertainty, it would limit the extent of losses that were potentially uncompensatable and give certainty that if the property is taken, the process of determining compensation would start relatively soon. If, as we were told at the Budget speech, government funding for Crossrail is secure, it is difficult to understand why the Promoters are reluctant to give such an undertaking. If there is a risk of delay or cancellation, then in these circumstances that risk should be the Promoter's not Souzel's. They say that they intend to take it in June 2009. In that case, why can they not be held to that if they were to say, "Right, we will take it or decide not to take it in June 2009", that would be a very significant improvement on the position of this Petition.

  6563. My Lord, alternatively, the Promoter should pay a substantial sum towards the loss of rent from June 2008 on some sort of regular basis, we would suggest quarterly, until they take the property or make a final decision not to take it. We believe that the historic rent paid pursuant of the Lazards' lease would be an appropriate figure to set it out. If they then went on to take it, what had been paid could be taken into account in the final determination of compensation. If they did not take the property, then those payments would provide some mitigation of the losses incurred while the Promoters made up their mind. My Lords, if that alternative approach was adopted --- We are not looking to make a profit on this basis, we are looking to hold the position while they make up their minds.

  6564. My Lords, if I can just add one further point. The Promoters have indicated that they may refer to various company information relating to our clients. They have provided us with information relating to various companies. The Petitioner Souzel is not a subsidiary of the companies they have provided detailed searches of. It is, however, ultimately owned by one of several family trusts which have various beneficiaries and I can make it clear that we are not saying we are poor, but that does not make this fair.

  6565. My Lord, I have been brief, as promised, unless there is anything else you wish me to deal with. Barristers sometimes are brief, not always.

  6566. BARONESS FOOKES: Not often!

  6567. MR HICKS: I am glad to be the exception. Is there anything else you wish me to deal with?

  6568. CHAIRMAN: No, I do not think so.

  6569. MR HICKS: I do not anticipate, unless my learned friend indicates there are relevant dispute of facts, that it is necessary for me to call a witness.

  6570. CHAIRMAN: I should not think so, thank you. Mr Mould, you will have to have powers before you can do anything about this?

  6571. MR MOULD: My Lord, yes.

  6572. CHAIRMAN: I suppose that depends on Royal Assent?

  6573. MR MOULD: It does indeed, yes.

  6574. CHAIRMAN: Thereupon you will do something and you will now tell us. I suppose the question of blight arises?

  6575. MR MOULD: Yes. What we will do is what we have said in the list of commitments that you have in front of you, which is still on the screen. What Mr Hicks invites you to do is to say we should do more. Let me be clear, we do not consider that there is any justification in relation to these Petitioners for doing any more and I shall explain to you, I hope equally briefly, how it is that we say that. It may be helpful just to summarise my learned friend's points. He draws attention, I think, to two uncertainties which he says cause difficulties for his clients. One is the uncertainty as to whether the project will proceed at all. The second is, assuming it does proceed, the uncertainty as to when his client's property will be taken for the purposes of the project. The reason why that is significant is because, as your Lordship will very well understand, ordinarily it is the date on which property is taken, that is to say, using the legal language, when possession is taken of the property, subject to compulsory acquisition, that the process of negotiating land compensation, including land compensation to embrace disturbance costs such as lost rent, pending acquisition, it is at that date that process takes effect. That will be the position in relation to these Petitioners, subject to our commitment 5, just as it would be in the case of any investment property owner within central London whose property is required wholly or in part for the purposes of Crossrail's scheme. There is no relevant distinction to be drawn between these Petitioners and any other person, any other company with similar property holdings, affected by the Crossrail proposals and therein lies the real difficulty here. If we were to go further, as Mr Hicks says we should, in relation to their property there would be no basis upon which we could refuse to take a similar course in relation to, I suspect, literally hundreds of properties owned by investment proprietors in the West End, the City of London and so forth. This is genuinely a case where a precedent could be set.

  6576. That brings me back, if I may, to the legal context which underlies this Petition. I said this case was all about blight and so it is, Mr Hicks has made that very clear. Blight affects property, that is to say the uncertainties associated with major schemes of this kind affect property until powers are obtained, funding is committed and compulsory acquisition has taken place, your Lordships will readily understand that. There is a very clear statutory scheme to remedy the effect of blight in certain limited cases. We explained that to the Committee at the beginning of these proceedings when Mr Smith gave his presentation and, as you will recall, in relation to commercial property a remedy is provided to the occupiers of small business premises, the limitation is expressed by reference to a rentable value on it, but it has never been the case that there is a remedy for the uncertainties and the blighting effects of schemes of this kind afforded to the owners of investment property affected by such proposals. The reasons for that are perfectly straightforward. Owners of that kind are generally able to make appropriate financial arrangement to cover the costs associated with the blighting effect of major schemes in a way that small business occupiers are far less likely to be able to do, so there is a clear policy distinction to be drawn there.

  6577. The next point is also fundamental. If proprietors of the kind that Mr Hicks' clients are were able to secure advanced purchase or advanced payments of compensation to cover blight in relation to their property, the costs would soon become so prohibitive to the scheme that these schemes would never take place. One only has to think of the consequences of a commitment which would have to extend, we say, across the whole of central London to think about the impact on pursuing the Crossrail project of giving the sort of advanced purchase commitments that Mr Hicks has asked for in relation to his property to investment proprietors elsewhere along the route. The third point is the point that I have already made, that there are literally hundreds of proprietors of this kind and if this one, then in principle all of them.

  6578. My Lord, let me just clarify the position in so far as what we have offered here is concerned. The ordinary position in relation to the acquisition of property for the scheme is set out in line 6 on the document in front of you. Ordinarily, as I have said, where property is required to be taken for the purposes of constructing a project of this kind, then the question of compensation and negotiations in relation to compensation payable ordinarily begins at the time when possession is taken of the premises in question for the purposes of the works. As we have said, that would be on current programme in June 2009, but we have indicated, and I do want to reiterate this point, the effect of paragraph 5 on your list is that we say here that we will begin those negotiations, unusually in this case, in advance of that date. What we have said is that if the parties are able to negotiate satisfactory terms and board approval is received in advance on current programme of June 2009, then we will purchase at that earlier date, that gives some comfort to these Petitioners. We have also indicated at 3 that the point of particular concern, that is to say the constraining effect which the shadow of the scheme will have in June of this year on the ability to re-let the office element of their premises, we accept that, on compulsory acquisition having taken place, that in principle will be a compensatable loss; it would be an element of disturbance compensation. Of course, if the commitment in 5, embracing the commitment in 3 and 4, is to take effect, then there has to be active negotiation between the parties and we expect that we will certainly stand ready at the time we have indicated to proceed with those negotiations. I have no doubt from what Mr Hicks has told you today his clients will instruct their agents to pursue those negotiations vigorously as well. There is a measure of comfort there over and above that which would apply to other investment property owners of this kind which we have dealt with here.

  6579. My Lord, as to the question of Royal Assent and funding being the trigger point, your Lordship has already made the point you cannot do anything until you have powers. The position on funding is this: your Lordships are very well aware that the Prime Minister made an announcement last October which identified the intended funding arrangements for Crossrail and we heard something about that yesterday in terms of the progress we have been making with Canary Wharf Group in negotiating one element of that funding package. True it is also that the Chancellor in his Budget statement indicated that funding for Crossrail was in the Budget but, of course, final details of funding arrangements logically and practically will be put in place once Royal Assent has been given because then the arrangements for delivery of the project procurement and so forth and, indeed, the finalisation of the programme would all be slotted into place. That is what we are alluding to when we talk about a Funding Notice.



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008