Select Committee on the Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 11380 - 11399)

  11380. I am just seeing how you can make the thing work more effectively, and I am sure you will go on refining this, will you not?

   (Mr Zamit) I think if you spoke to other people we have dealt with, and the City Council and others, that we are good people to work with, and we end up with a better result and a better design.

  11381. MS LIEVEN: My Lord, I am conscious that we have had some quite helpful correspondence with the City Council about this issue. What I suggest is I will get that correspondence copied over the lunch adjournment and ask Mr Berryman about it after lunch. Obviously it is not really for us today to get into precisely how this liaison panel works, but they are issues that we have been concerned about, our community relations officers are involved in, and Mr Graham King, from the City Council, is the chair of this liaison group, so we are all working quite well together, I would suggest, on this particular location. I will get that correspondence copied and we can look at it briefly after lunch.

  11382. CHAIRMAN: I think that would be helpful. The more efficient this is the better. Mr Zamit, in your petition you raised the question of the Heathrow Express. Nothing has been said about that this morning—is there any point left that you want to make on this?

   (Mr Zamit) There is nothing to raise on the Heathrow Express.

  11383. MS LIEVEN: It is one of the aspects we agreed this morning with the City Council, as to how we would handle the undertakings that we given under the Heathrow Express Act.

  11384. CHAIRMAN: For reasons of course I understand, we do not know what you have agreed and we never will! It is in the petition, I just wanted to make sure it was not being missed out. Do you want to ask any follow-up questions?

  11385. MR WALTON: No, my Lord. I am most grateful for the interest which your Lordships have been taking in the matter, but I do not wish to re-examine.

  11386. CHAIRMAN: In that case, I think it is a very good time to adjourn. Shall we do so until half past two. Will that give you enough time to do the photocopying?

  11387. MS LIEVEN: Absolutely, my Lord.

The witness withdrew

The Committee adjourned from 1.03pm until 2.30pm

  11388. CHAIRMAN: As a result of listening to the rail freight Petitions, we thought that it was worth putting to the Promoter the possibility of an undertaking in the following terms:

  11389. We recognise the importance of rail freight to the economy and require the Promoter to give an undertaking that any subsequent decisions taken by the Promoter on the proposed infrastructure will not impact negatively on the ability of the rail network to sustain, and expand, the carriage of rail freight to the forecast levels for 2015, accepted by the Office of Rail Regulation.

  11390. There is no need to answer now on the part of the Promoter. You may just conceivably have seen it before, but, if you could give us at some time an answer to that, whether you will be able to do that, it might go a little way towards resolving the dispute.

  11391. MS LIEVEN: We will take instructions, my Lord.

  11392. CHAIRMAN: Indeed so.

  11393. CHAIRMAN: Now, Mr Berryman?

  11394. MS LIEVEN: My Lord, I alluded before lunch to a letter that I was going to put before the Committee just to show where we were on consultation, and I think it is just being copied at the moment, so, I will go straight to Mr Berryman instead.

MR KEITH BERRYMAN, recalled Examined by MS LIEVEN

  11395. MS LIEVEN: Mr Berryman, I think the only thing we need really to cover is our approach to consultation with groups such as PRACT. First of all, can you just explain what consultation will take place with PRACT in relation to surface-level works under the Bill?

   (Mr Berryman) Yes, the first thing to say is that we have a very effective liaison group working already in the Paddington area. It is chaired by Westminster City Council and appears to be meeting the needs of all the people who attend it at the moment, although I think, as PRACT have said this morning, that there is perhaps a need for some more detailed discussion on some aspects with a smaller number of people, and that is something we will come back to when we have got the copied letter. The basic means by which this residents' group and any other residents' group will be consulted is during the planning process under Schedule 7 of the Bill when they will be consulted by the local authority prior to the local authority granting consent. What we will be doing in this case, and in all the other cases, is getting from each local authority a list of those persons to whom we should circulate the planning applications at the same time as we send them in to the local authority, and we would confidently expect in the case of this area that PRACT would be one of those groups, so they will get the documents from us at the same time as the local authority gets those documents. Prior to that—

  11396. CHAIRMAN: So it is really a matter for Mr Walton to provide you with it or Westminster City Council?

   (Mr Berryman) To provide us with a list of who should get the documents?

  11397. Of who should be circulated.

   (Mr Berryman) Yes, it is for Westminster City Council to provide that list. In this case, knowing, as I do, the relationship between Westminster City Council, PRACT and myself, I would have no doubt that PRACT will be one of those groups to whom we would be required to circulate the applications. Prior to that, we will expect the consultation to take place at the liaison group or at an offshoot of the liaison group, if you like, so that we can pick up the residents' concerns and suggestions.

  11398. MS LIEVEN: Can you then explain what the differences are between the process for surface-level works and for sub-surface works?

   (Mr Berryman) I think the point to make about the sub-surface works is that the design of the sub-surface works is very, very heavily constrained by the standards which we adopt which are to some extent LUL standards, but, because of the scale of these works, we have some standards of our own, which are agreed with all the relevant safety authorities, and the passenger circulation which we have to achieve, and the need for the trains to be properly accessed by the passengers. It sounds a silly thing to say, but you clearly have to be able to get on and off the trains. The constraints, the freedom of action in the underground works is very, very seriously limited and we would expect that it is probably less likely that a group, such as PRACT, or a residents' group would be able to make much of a contribution to that design.

  11399. While we are on the consultation issue, can we just look at this document which we have just had handed round. The second part of this page is an email from Gareth Epps who is one of our community relations managers to Graham King who is the lead officer at Westminster on Crossrail issues and who, I think, chairs the liaison group. Is that right?

   (Mr Berryman) That is correct, yes.



 