Select Committee on the Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 13420 - 13439)

  13420. MS LIEVEN: My Lords, in response to the questions yesterday, I was going to read something out which has been compiled by the team. Of course, if the Committee want Mr Thornely-Taylor to go back into the witness box, then we are quite happy to do that, he is here, but let me read out the position as we understand it and see where we can get to.

  13421. My Lords, the way that the construction railway works is that, as the TBM advances, temporary tracks are laid behind in the invert or bottom of the tunnel and the tunnel construction trains run on this, and they comprise a locomotive and rolling stock. It is likely that the trains will consist of a locomotive and three flat-bed trucks to carry the concrete segments and another flat-bed for miscellaneous materials, a grout container car and a man-rider for the workforce, so that is the form of the construction train.

  13422. CHAIRMAN: Of course the spoil is going out on the conveyor.

  13423. MS LIEVEN: The spoil is going out on the conveyor, so this is the trains bringing the materials in to effectively support the TBM. The locomotives are likely to be diesel-powered with hydrodynamic or hydrostatic transmissions, and I am going to refer to the noise information below. I have got material on the frequency, but I do not think that matters too much at this stage. The normal working speed of the construction trains is 15 kilometres per hour and, in working areas and at switching crossings, the speed will be reduced to five kilometres per hour. There will be a set of crossovers adjacent to the Westbourne Park footbridge and others adjacent to the Westbourne Park worksite, so one can see from that that we are talking about very low speeds here.

  13424. The construction noise assessment, which was carried out for the Environmental Statement, shows that baseline noise levels for Westbourne Park Villas at that time were assessed as 64dB LAeq eight hours at night. Now, that was for the ES, so it was some time ago. The predicted construction noise level during the tunnelling phase, that is the 24-hour operational phase, from the above is 56dB LAeq and that was assessed for 99 Westbourne Park Villas. Therefore, the tunnel trains would have to be considerably louder than the other plant operating to increase the predicted noise level by a sufficient amount to cause a significant construction noise effect, and the manufacturer's noise information obtained indicates that that is very unlikely to be the case. A point to emphasise here, and I can call Mr Thornely-Taylor to deal with this if the Committee want to take it further, is that my instructions from him are that the predominant noise source from this kind of activity is the train being loaded. It is not the trains going along the tracks, it is the train being loaded, so it makes very little difference whether you have a battery-operated train, a diesel-operated train or indeed, as Mr Thornely-Taylor put it to me outside, a horse-drawn train because it is not the trains going along that are making the material noise here. In addition, consideration of the operation of the construction trains shows that they will create noise for a much shorter proportion of time than the other plant and equipment. It remains a possibility that movements in the construction train may be audible to nearby residents on some occasions, but that has to be considered in the context of other construction activity and mainline train traffic.

  13425. The other point for the Committee to note in terms of the reality of what is happening here is that mention was made by Mr Berryman of battery-operated trains, and my instructions are such that such trains have been used overseas, for instance, we think, on the mass transit system in Hong Kong, but we are simply not sure at this stage whether it would be feasible to use battery-operated trains here, even if it were justified, because we have very long tunnel drives. Since we changed the tunnelling strategy a couple of years ago, we now have these very long tunnel drives, and my instructions are, to put it non-technically, that we are just not sure whether the batteries would manage to get the trains to the right place, and they might run out of—I was going to say "steam"—while in the tunnel.

  13426. There were issues such as that which simply have not been determined, but the important point to understand, away from the technicalities, is that the Promoter has made a commitment to apply section 61 of the Control of Pollution Act process to the construction sites and that requires that the nominated undertaker demonstrate that best practicable means to control noise have been utilised.

  13427. In the context of the construction train and the selection of either diesel or electric trains, the Promoter will have to demonstrate that the train type selected is the best practicable means to control noise. It is for that reason that if circumstances demonstrate that a particular train type has material advantages over another train type, that will be highly material to deciding what is best practicable means. Therefore, to specify at this time a particular type of locomotive could be counter-productive to achieving the best practicable means, because you might specify now battery-operated and you might find that that was not best practicable means. So actually, it is not in anybody's benefit to try to pin this issue down at this stage.

  13428. The commitment to use best practicable means in this regard means the Committee can be completely confident that this issue of whether there is any material impact on noise will be fully taken into account in the final decision as to what type of train to use, as of course will be the reality of whether we can get battery-operated trains to do the job in any event.

  13429. I have given that really in order to save time as we are on the last day, but if the Committee want Mr Thornely-Taylor to give evidence or just to go into the witness box—

  13430. CHAIRMAN: Before we decide on that, did I understand you to say that it is not the locomotive that is going to be causing the noise; it is putting the segments or whatever it is on to the presumably flat wagons?

  13431. MS LIEVEN: The predominant noise source is the train being loaded. I do not want you to think we drop the segments and they go "crash!" because apparently that is not what happens. Apparently, a major part is the crane noise of bringing them over. It is the train being loaded; it is not the actual noise from the locomotives. It is completely different from the EWS issue at the batching plant, where the noise source is the noise coming out of the top of the train. We are talking about a very different scale of noise here.

  13432. CHAIRMAN: You are putting material on to the flat trucks with a crane.

  13433. MS LIEVEN: Yes.

  13434. CHAIRMAN: Presumably, it makes a noise when they get on to the platform of the vehicle.

  13435. MS LIEVEN: Yes, my Lord. I keep being told it is the crane, not the material hitting the flatbed truck.

  13436. CHAIRMAN: It is the crane that makes the noise.

  13437. MS LIEVEN: It is the crane that makes the noise.

  13438. CHAIRMAN: So it is a diesel crane.

  13439. LORD JAMES OF BLACKHEATH: It is the chain in the crane that makes the noise.



 