The Economics of Renewable Energy - Economic Affairs Committee Contents


Memorandum by Professor Andrew Bain

  I am a semi-retired professional economist. During my career I have been a Professor of Economics at several Scottish universities and from 1984-90 was chief economist at Midland Bank. I have been involved with a number of government bodies, including the Wilson Committee on the City, and I served on the Board of Scottish Enterprise for eight years. I am currently a Member of the Competition Appeal Tribunal. I participated in the Royal Society of Edinburgh's Inquiry in Energy, though I resigned before the Report was completed, and I have given evidence at Public Inquiries into the proposed Beauly-Denny transmission line and the proposed Beinn Mhor wind farm in Lewis.

1.  INTRODUCTION

  1.1  I welcome this opportunity to submit evidence to the House of Lords Select Committee on Economic Affairs in connection with its inquiry into The Economics of Renewable Energy. My particular concern is with the costs of electricity transmission and their impact on the location of renewable generation. It is important to ensure that the incentives and constraints facing developers provide the correct locational incentives and do not lead to electricity consumers incurring unnecessarily high costs for renewable energy. Consideration of transmission costs led the RSE Committee to express its "grave doubts about the overall economic rationale for large-scale wind turbines in locations remote from the consumer."[1]

  1.2  In a properly functioning system electricity consumers would pay the same for energy, regardless of the location of the generator. By setting renewables targets, imposing renewables obligations on distributors, and granting variable entitlements to renewables obligation certificates (ROCs), the UK and Scottish Governments have fragmented the energy market, so that energy generated from renewables receives a premium which varies according to the source of the energy. As a result consumers will pay more for wave or tidal energy than for energy from wind, and more for energy from off-shore than from on-shore wind. Nevertheless, within each category the cost to the consumer should be independent of the location of the generator, with any differences in production and transport costs being reflected in the profits of the generating companies.

2.  TRANSMISSION CHARGES

  2.1  For this to occur the costs necessarily incurred in transmitting energy from a generator in, say, Central Scotland to a distribution company in, say, the London area would be charged to the generator. That is not what happens in practice. There are two categories of transmission cost: the capital and operating costs of the grid, and the transmission losses associated with transmission through the grid. Charges to generators for the use of the grid are determined using National Grid's Transmission Network Use of System (TNUoS) Model. No account is taken at present of transmission losses.

  2.2  Transmission losses are materially greater when the generator is distant from the consumer, and are likely to be particularly large for generators in the Western and Northern Islands of Scotland. For example, generation losses on the proposed interconnector to transmit energy from the Western Isles as far as Beauly, west of Inverness, are said to amount some 5% of output, and for energy generated in the Western Isles there would be further significant losses during transmission from Beauly to the south of England. Failure to take account of these losses means that generators are receiving payment for significantly more energy than they are delivering to consumers—a cost that is borne by electricity consumers generally. Devising a robust method for allocating transmission losses to generators, and imposing charges correspondingly, should now have a high priority.

  2.3  The TNUoS model used at present is not an appropriate model for allocating the capital and operating costs of the grid to intermittent generators. It is a peak demand pricing model, in which the charges for grid access reflect the use made of the grid at peak demand periods. This presupposes that the grid configuration is determined by the configuration of generation and demand at that peak demand. For intermittent renewables generation this is patently not the case—what is required is a model that takes account of peak supply.

  2.4  To illustrate. The scale of wind generation in Scotland is geared to exporting energy from Scotland, and the peak transmission requirement from intermittent generators in Scotland will occur when demand in Scotland is low but wind conditions are favourable. For example, on a warm and windy summer night Scotland's two nuclear power station plus its conventional stations operating at minimum practical loads already provide more generation than is required to meet Scotland's demand, with the result that some energy has to be exported through the Scotland-England interconnector. To provide sufficient capacity to accommodate the proposed high level of wind-energy from Scotland the interconnector will have to be substantially reinforced, as will major sections of the grid to the north and south of it. This has absolutely nothing to do with meeting peak UK demand. Indeed it is not unlikely that peak UK demand will coincide with severe winter conditions, when an anticyclone with still air predominates over the UK and wind turbines make very little contribution to supply.

  2.5  There are other weaknesses in the TNUoS model. It allocates less than 30% of the costs of the grid network to generators, with the rest being payable by distribution companies. There is no evident rationale for this division, though it may reflect the fact that there is a high degree of redundancy built into the system to ensure that the supply of energy to consumers is secure in the event of unavailability of sections of the grid. This redundancy is of much greater benefit to consumers than to generators.[2] The TNUoS model also assumes that the grid has a 40-year life and that capital charges can be geared to that period. Wind farms are currently assumed to have a 25-year life, and may well be superseded by other technologies after that period. If account was taken of the "stranded asset" risk TNUoS charges for wind farms would be higher.

  2.6  Transmission charges may also be adjusted by government direction under Section 185 of the Energy Act 2004. This gives the government power to adjust the transmission charges for generators in particular areas if it seems likely that renewable generation would otherwise be discouraged. The government has decided that the additional costs of transmission from the Scottish Islands should be halved. There is no evidence that industrial-scale wind turbines in eg the Western Isles will be needed in order to meet the Scottish Government's 50% target for renewable generation (see below), so there is no compelling case for encouraging wind farms in Lewis. Nevertheless, if a new connector for the Western Isles is constructed and generators pay for only half of the additional costs, consumers throughout the UK will end up paying more for wind-energy from these Islands than from other regions.

  2.7  The upshot is that the present method for determining transmission charges needs a radical overhaul to ensure that the financial incentives facing wind farm developers encourage development where the costs, including transmission costs, to the consumer will be lowest.

3.  SCOTTISH RENEWABLES POLICY AND THE NEED FOR INVESTMENT IN THE GRID

  3.1  Regardless of the financial incentives for renewables development, actual development is frequently constrained by planning requirements and by access to the grid. These are driven by a mixture of economic and political considerations.

  3.2  It is generally accepted that within a European context conditions in the north of Scotland, and in particular in the Western and Northern Isles, are uniquely favourable to renewables generation from wind and marine sources. This has led many to conclude that there is a very strong case for developing wind and marine generation in these areas. Statements such as "Strategically it make sense to harvest renewable energy where the resource is greatest and operational efficiencies can be maximised"[3] are treated as axiomatic by the Scottish government and by regional authorities in Scotland. The need to transport the energy to the market, and the costs incurred in doing so, are overlooked. Far from it being axiomatic that renewable energy should be harvested where the resource is greatest, it is appropriate to harvest energy in these areas only if the operational efficiencies are sufficient to compete with other renewable energy sources and, in addition, more than compensate for any higher transmission costs.

  3.3  This "axiom" underlies much of Scottish policy towards renewables. It is prayed in aid in support of the Scottish Government's target for renewables generation equal to 50% of Scotland's electricity consumption in 2020. It is reflected in continuing political pressure to relieve generators in the North of Scotland and the Islands of part or all of the transmission costs, as evidenced by, for example, Section 185 of the Energy Act 2004, statements from Scotland's First Minister that the TNUoS charges are unfair, and a recent consultancy report commissioned by the Highlands and Islands Councils and Highlands and Islands Enterprise recommending greater "socialisation" of grid costs.[4]

  3.4  It is also reflected in the Scottish Government's draft National Planning Framework 2 (NPF2)[5]. This includes amongst its "national infrastructure priorities" proposed grid reinforcements to facilitate the attainment of the target and promote marine development. The proposals emanate from the Scottish grid companies, Scottish Hydro Electric Transmission Limited (SHETL) and Scottish Power Transmission Limited (SPTL), in response to applications for connections from potential wind farms. The total capacity in these applications, many of which will be turned down on planning grounds, greatly exceeds the amount required to attain the 50% target. There is no evidence that the grid priorities set out in NPF2 have had regard to the likelihood of planning consents for the proposed developments, to the capacity of the existing grid to cope with increased levels of intermittent generation, to the economic viability of wind farms if the transmission costs had to be borne by the generators, or to the likelihood that wave and tidal development will ever prove to be economic. Moreover, the Scottish Government's 50% target is predicated on much of the energy being exported to the Midlands and South of England. To the extent that generators do not pay for all the necessary grid reinforcement consumers throughout the UK, not only in Scotland, will have to bear the cost.

  3.5  NPF2 recognises that individual proposals for strengthening the grid will not be implemented without first being approved by Ofgem. Before approving investment in the grid Ofgem conducts an economic assessment, with the object of ensuring that the investment is economically justified. So the fact that a particular proposal for new grid is identified as a national priority by the Scottish Government does not necessarily mean that it will happen. But it does mean that there is strong political and industrial pressure on Ofgem to approve the proposal, particularly when Ofgem's objectives include not only the promotion of efficiency and economy in supply and transmission but also to contribute to the achievement of sustainable development[6]. If Ofgem turns down a Scottish "national priority" on the strength of an unfavourable economic assessment it will inevitably be accused both of failing to contribute to sustainable development and of thwarting the policies of the democratically-elected Scottish Government. There is danger that this may put more strain on the regulator than it can reasonably be expected to bear, with consequences for the rigour of its economic assessment.

4.  OFGEM'S ECONOMIC ASSESSMENT METHODOLOGY

  4.1  When so much depends on Ofgem it is essential that its methodology for assessing the economics of grid reinforcement is sound. Unfortunately, this cannot be relied on: the methodology adopted by Ofgem in 2004 for identifying its baseline programme of grid investment was defective[7]. Its assessment of the proposed Beauly-Denny grid line provides an example.

  4.2  Ofgem approved the Beauly-Denny grid reinforcement as part of its baseline programme on the strength of an economic analysis in which it compared the present value of the costs of constraining off energy—primarily the cost of compensating generators—if the grid was not reinforced with the present value of the costs of reinforcing the grid to accommodate additional wind farms in the north of Scotland. It found that for the likely level of wind farm development the constraint costs exceeded the cost of the line, and that the reinforcement was therefore justified.

  4.3  Ofgem's methodology was defective in several respects. It assumed that the same level of security in the system was required for intermittent generators as for conventional generators[8]. That meant the capacity of the existing grid was taken as some 500MW less than it could actually transmit[9], ie the existing grid system between Beauly and central Scotland was capable of transmitting another 500MW before constraint costs would have to be incurred.

  4.4  No allowance was made for the rather obvious possibility of storing energy by operating hydro stations in a way that complements wind power and reduces the need to constrain off wind-energy in peak generating conditions[10], and the scope for using the pumped storage facility at Foyers to add to the demand load at wind power peaks, and thus avoid constraining off, was underestimated; no account at all was taken of the possibility of operating the Cruachan pumped storage facility (in the SPTL area) to provide temporary storage for peak generation from wind farms along the southern part of the proposed line.

  4.5  No account was taken of the cost of the further substantial grid reinforcement to the south of Denny that would be required to enable the energy to be transmitted to southern England.

  4.6  Taken together these omissions fatally undermined Ofgem's conclusion that the Beauly-Denny proposed grid line was economically justified[11].

  4.7  Apart from these errors of implementation, Ofgem's methodology is inherently unsound because it effectively double-counts the ROCs associated with constrained-off energy. This is because Ofgem assumes that the wind farm developments will be in place, and then calculates the constraint costs, including the cost of the ROCs. So, the income from ROCs is taken into account, first by the developer in deciding whether to proceed with the development and then again by Ofgem in respect of any energy that has to be constrained off the system when considering the case for grid reinforcement. A proper economic assessment of the whole project, namely constructing a wind farm together with any associated grid reinforcement that will be needed, would take the total capital cost and compare it with the total expected net revenue from the development, counting the ROCs only once.

  4.8  My conclusion is that experience to date does not give grounds for confidence that Ofgem will ensure that only those grid reinforcements that are justified by economic fundamentals receive authorisation. It is in the financial interest of the grid companies to maximise the size of the grid, because once authorised they can reasonably expect to earn profits on it over its assumed 40-year life. The political pressures will always weigh in favour of allowing proposals to proceed. The present arrangements put too much weight on the proposals from the companies, with too little independent objective scrutiny, backed by political muscle, of the need for reinforcing the grid. The outcome is likely to be that electricity consumers in future will be saddled with unnecessarily high grid costs.

13 June 2008



1   Royal Society of Edinburgh Inquiry into Energy Issues in Scotland, Final Report, June 2006, p.73 Back

2   The TNUoS model is intended to ensure that the differential between generators whose energy is transmitted on average over great distances and those that are close to their markets reflects the difference in the grid costs, but the absolute amounts of the charges are not geared to the absolute costs involved. Back

3   Beinn Mhor Power Public Local Inquiry, Scottish Government Reference IECIEC/3134, Precognition of Calum Iain Maciver, Head of Economic Development of Comhairle nan Eilan Siar, paragraph 69(5). Back

4   Xero Energy, Grid Connection of the Scottish Islands-A Strategic Viewpoint, 20 June 2007. Back

5   National Planning Framework for Scotland 2: Discussion Draft, paragraphs 226-9 Back

6   Electricity Act 1989, Section 3A (a) and (ba), as amended. Back

7   Ofgem, Transmission investment for renewable generation-final proposals, December 2004. Back

8   SHETL now recognise that a lower level of security-a "non-firm connector"-is appropriate for wind-energy from eg the Western Isles. Back

9   Subject to some relatively minor capital spending for "operational intertripping" to protect the rest of the system if a fault arose. Back

10   SHETL now recognises that this is feasible. Back

11   Ofgem did not give evidence to the Beauly-Denny Public Inquiry. Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008