The Economics of Renewable Energy - Economic Affairs Committee Contents


Memorandum by Energy Networks Association

LONG-TERM INVESTMENT IMPLICATIONS OF HITTING THE RENEWABLES TARGET

  1.  The UK faces a significant challenge in delivering its share of the EU Renewable Energy target. Critical to success is Government support and recognition of the need for significant investment in network infrastructure and the creation of a more efficient and supportive planning framework. In addition, the need for a supportive regulatory regime, aligned to Government's ambition in meeting EU targets, is paramount.

  2.  The Business Council for Sustainable Energy UK (UKBCSE) believes that by 2020 around two-thirds to three-quarters of the new renewable electricity generation capacity could come from offshore and onshore wind energy. This will have implications for the supporting infrastructure needed to maintain energy system stability, including securing sufficient generation capacity to manage intermittent supply from renewables.

  3.  There is a need for significant investment in the network infrastructure to manage the increased contribution from renewable energy, and to manage the associated peak capacity and operational and system stability issues. Innovative approaches to optimising use of present network assets as well as network expansion will need consideration.

ELECTRICITY DISTRIBUTION SYSTEMS

  4.  Distributed Generation by definition is connected to the distribution networks. Within England and Wales distribution networks are defined as 132kV and below which are owned and operated by Distribution Network Operators. In Scotland 132kV and above is defined as transmission network with distribution limited to 33kV and below. As of March 2007, approximately 3.5GW of renewable generation was connected to distribution systems throughout the UK.

  5.  A number of projects have been undertaken to assess the potential levels of distributed generation, in particular the Supergen Future Network Technologies Consortium work and the UKBCSE May 2008 paper. It is estimated that the potential for onshore renewable distribution connections will be in the order of 12GW by 2020. This can be further classified into generation technology; onshore wind—1-2GW; Biomass—2-4GW; Hydro—1GW; Marine—1-2GW; Microgen—2-3GW.

  6.  Larger schemes, such as offshore wind farms, large onshore wind farms and projects the scale of the Severn Barrage will connect directly to the transmission system, with no impact on the distribution network.

  7.  Although there are some exceptions, in England and Wales projects generating less than 100MW are likely to connect to distribution networks. These networks were originally designed to supply energy and when distributed generation results in the reversal of this flow of energy, this can trigger modification to the associated network.

  8.  In areas where natural renewable resources are plentiful, for example wind, the distribution system is often sparse. This will result in new generation triggering significant infrastructure, and in many cases this will include the construction of new overhead lines. The provision of infrastructure to accommodate 2020 targets will be challenging. This will only be achieved with supportive planning policies and a regulatory regime that enables the timely investment in new network infrastructure.

  9.  As distributed generation connects, it will initially displace local demand, however it will ultimately result in "export" onto the transmission system, this in turn will have implications for the requirement for transmission infrastructure including potential uprating.

  10.  The energy mix that will be realised by 2020 will be a major influence on where infrastructure will be required. If the larger projects do not proceed but a larger volume of distributed renewables do connect, then the impact and resulting need for investment in the distribution system will be intensified.

  11.  To date, significant work has been undertaken by the joint BERR/Ofgem sponsored Electricity Networks Strategy Group (ENSG) to consider the future penetration of renewable generation connecting to the Distribution Network. This work has culminated in several reports being written covering topics such as Network Access; Solutions for the Connection and Operation of Distributed Generation; Technical Guidance on the Connection of Generation to the Distribution Network; and more recently, completed in 2007, Future Network Architectures Report.

  12.  The Future Network Architectures Report considered a number of DG penetration scenarios and provides an insight into the scale of change to network architecture that might be required under each scenario.

ELECTRICITY TRANSMISSION SYSTEM

  13.  Electricity transmission infrastructure is key to enabling the increased levels of renewable generation estimated to be seeking a connection. The three GB electricity transmission licensees have provided a preliminary view of the capacity of the existing GB transmission system to accommodate new renewable generation without the construction of new overhead line routes. The diagram below, taken from the May 2008 paper produced by UKBCSE, is a summary of the indicative guidance from the three licensees.

Figure 6

CAPACITY OF THE TRANSMISSION SYSTEM TO ACCOMMODATE RENEWABLES


  14.  The diagram provides a general indication of the levels of renewable generation that could be accommodated on the GB transmission system by 2020. It assumes completion of transmission upgrades already in train (eg the South West Scotland and Beauly-Denny upgrades) as well as completion of those works expected to be delivered without protracted planning issues.

  15.  The proposed offshore licensing regime gives rise to individual licences for connecting offshore wind farms to the onshore grid. This will promote a "radial connection" approach and raises questions as to whether such an arrangement is sustainable or whether instead (or in addition) an offshore interconnected transmission system might be desirable from both a technical and economic perspective to fully realise the potential offshore resource. It should also be noted that in order to accommodate offshore generation (expected to be in the order of 33GW), significant investment in the onshore network will be required (estimated at £300/kW). It will also be necessary to consider an integrated approach towards both the planning and design of both the onshore and offshore system.

  16.  Delivery of the 2020 renewable energy target will require swift action to ensure that; the supporting infrastructure is in place; planning decisions are made in a timely manner; and that key issues such as technology supply chain constraints are addressed. In addition to planning and construction for renewable energy projects, there are also time implications of new network infrastructure, including identifying Offshore Transmission Owners, coordinating connection between offshore and onshore infrastructure followed by construction.

  17.  It is therefore particularly important that investment in necessary network infrastructure is facilitated in a timely manner to ensure progress towards delivering the 2020 renewable energy target.

David Smith, CEO

13 June 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008