The Economics of Renewable Energy - Economic Affairs Committee Contents


Memorandum by Sir Donald Miller

INTRODUCTION

  1.  Government, in setting out their policy on renewable energy, have on several occasions stated that the targets are "subject to the costs being acceptable to consumers"; White Paper Cm 5671 P16 Section 1.22 lines 7-8 is one such example. However no steps have been taken to assess what these are likely to be and to consult consumers on what they consider acceptable. This paper concentrates on the costs of wind energy and particularly the costs to consumers, wind being the technology for which the costs are most clearly established. It first examines the various areas where costs are incurred before attempting to quantify each to arrive at a total figure. It then adds some more general comment, based on established engineering criteria and long experience of power generation, on the likely relative costs of other renewable sources such as marine and dispersed local generation.

WIND ENERGY

  2.  It is frequently claimed that the output from wind developments will supply so many houses. In reality, as Fig 1 published by National Grid shows, the output is so intermittent and unpredictable that it cannot be relied on as a supply. An electricity system cannot store energy in significant quantity so that its operation requires there be an exact balance at all times between the demand and generation output. Thus any source of generation which cannot be relied on to produce power on demand requires to be backed up by conventional fossil fuelled generation. The burdens of this are met entirely by consumers and comprise (a) the capital costs of providing this spare generating plant but also (b) the increased operating costs required to ensure that the system can compensate for the short term and unpredictable swings in output from wind farms.

  3.  Dealing first with (a), the capital costs of support plant, it is sometimes claimed that wide dispersement of installations throughout the country will greatly mitigate the requirement for such back-up but experience does not support this. An examination of Danish performance shows that on 29 December 2000, with 1,860MW of wind turbine capacity installed and an output of 1,715MW, this was reduced to 951MW over one hour under storm conditions. Since the period of study is necessarily short, this is unlikely to correspond to the worst conditions, but nevertheless it represents a power swing of 41% of wind output per hour.

  4.   Similarly, in Germany the grid operator E.ON* in their report Wind Year Overview 2003 describe a reduction from 4,300 MW to 660MW (a drop of 3,640MW) over six hours with a peak rate of about double that or 30% of output per hour.

  5.  National Grid in their evidence to a House of Lords Select committee gave as their criteria for when the intermittency of wind power would incur additional costs for the UK system as:

    "When there is a potential loss over one hour greater than 3% of peak demand. 3 % of the UK peak demand of 60,000 MW amounts to 1,800 MW and the system must be capable of withstanding this loss at all times including the hours when wind output is falling rapidly The UK grid system is designed and operated to cater for the instantaneous loss of a major generating station or a double circuit high voltage line and thus has already to accommodate a maximum power loss of 1,250MW. If we take the maximum short term wind power reduction at say 35% of wind output we can readily calculate the capacity of installed wind generation beyond which, according to National Grid, significant additional operating cost will be incurred on the system. This calculation below shows that this occurs once the installed wind turbine capacity exceeds:


  6.  Already there some 2,500 MW of wind turbines in the UK in operation and some 19,000 MW including those in the planning process. In Scotland alone, see Fig 1, some 2,000MW are in operation or under construction and as much as 8,000MW, including those for which applications have been made for planning consent, so that we are already in line for very significant system support costs. Discussing costs, the Royal Academy of Engineering, comment in their Annual Review 2002-03 on the Government's Energy target of generating 20% of our electricity by 2020 from renewables say "this is over-optimistic and fails to address the fundamental difficulty of all renewable sources—they are intermittent."

  *E.On, owner of UK generator Powergen, is a major player in the UK wind market.

  7.  An analysis by the Grid arm of the large German utility E.On has demonstrated that this additional back up thermal generating plant needs to be 80% of the installed wind turbine capacity, a figure which is supported by the Irish Grid, The Royal Academy of Engineers, by OFGEM and more recent work in a BERR/SEDC study. Indeed other work based on probability theory both here and in Germany suggests that if the reliability of our supplies is to be maintained at traditional levels something like 90% back up will be required for the high levels of wind power envisaged.

  8.  Turning to (b), the need for operational support, since output from wind generators can vary dramatically over a short time any reduction must be compensated for by quick response conventional generating plant. However fossil fuelled plant, such as a large coal fired generation, takes typically 10 hours to start and load up from cold so that it becomes necessary to run sufficient back up plant at less than rated load whenever the wind turbines are in operation. The minimum load at which a 600MW coal fired generator can be operated is typically some 200MW or one third of rated full load so that to match the wind turbine output at any time on the system a large number of fossil fuelled units will require to part loaded with the loss of efficiency this entails. Experience suggests that the total amount of this de-loading on the system should be some 60% of the wind turbine output at any time and that this will need to be done on a regional basis, if large swings in the power transfers are to be avoided. Operation in this inefficient mode incurs further additional costs which are met by the consumer. It also increases the quantities of CO2 released compared with operation at full load, so reducing the gain in CO2 emissions by at least 20% compared with that given by a simple calculation based on the wind energy output.

  9.  Nor does this represent the whole of the financial costs incurred as a result of an excessive reliance on wind energy. There is also the cost of transmitting the energy to the consumer. It is clear that based on present planning the vast majority of wind installations, will be mainly in Scotland and to a lesser extent in Wales and the West of England, and all remote from where the demand is required in the South and South-East of England. It may therefore be instructive to look in more detail at the situation in Scotland. National Grid are planning on an installed wind farm capacity of 8,000MW in Scotland by year 2013-14 which compares with existing conventional generating capacity of 8,900MW and a maximum system demand of some 5,700 MW. The present capacity of the transmission system from Scotland to the north of England is some 2,200MW so that there is at present no outlet for additional capacity either in Scotland or over the interconnectors to England without displacing existing Scottish generating capacity. Recognising this limitation, Government and Ofgem (the electricity regulator) have authorised the Scottish Grid Companies to spend an initial £800 million on reinforcing the HV transmission system to the North of England to cater for exports from wind farms in Scotland. £350 million of this initial expenditure is for the construction of a new EHV line along the major tourist route of the A9 in the Highlands from Beauly, north of Inverness, to Glasgow with the remainder for reinforcing the cross Border links to the North of England. This will increase the capacity of the transmission to England to some 3,300MW, sufficient only to cater for the expected wind capacity for this year (2008). The extra cost this year of this transmission expenditure, which would not be required but for excessive installations of wind energy is equivalent to £35/MWhr of energy produced and alone is comparable with the price of bulk power from conventional generation

  10.  Even the heavy expenditure on the transmission system referred to above will not be sufficient to cater for the large amounts of wind power projected for installation in Scotland. The Authoritative source for information on the UK Grid System is the 1,000 page statutory Seven Year Statement published annually by the three transmission companies, National Grid, Scottish Power and Scottish and Southern. This most recent Statement (2007) contains an exhaustive analysis of the effect of increasing wind energy in Scotland on the required power flows to England and is depicted in chart form in Fig 3. The National Grid figures show an increase from wind power of 3,625MW (from 8,827 to 12,493) over the seven years to 2013 with export flows (the red line in Fig 3) increasing by 3,094MW (from 2,653 to 5,746 MW). This is all from proposed increases in wind installations in Scotland. It should be noted that these increases in wind output are not balanced by reductions in conventional generating plant, even supposing this were technically possible on the system. Indeed heavy expenditure is now being undertaken to fit flue gas desulphurisation at Longannet and Cockenzie power stations to extend their working lives beyond 2015 and further licences can be expected to extend the lives of Scotland's nuclear plants. National Grid's analysis also shows that these same levels of import are required to maintain supplies in England. This situation is illustrated pictorially in Fig 4 where by 2013 over 5,000MW is shown being exported from Scotland and transported throughout England to the SE, even affecting flows to the continent over the sub sea cables.

  11.  It should be noted that the flows described above are those used by the Grid companies for system planning and investment purposes and are for conditions at maximum demand and with wind power outputs set at 60% of installed capacity. Thus the export of 5,746 MW in 2013-14 means that the whole of the wind generation in Scotland (8,000 MW installed capacity) will be exported even at periods of high system load on the Scottish system. At lower loads, because of the relatively lower operating costs of other generation in Scotland (nuclear and high merit coal) compared with England, the high levels of wind power outputs exported to England will be maintained or even increased.

  12.  The costs of all this transmission for these massive wind power developments proposed for Scotland could not be better illustrated than by the Commentary of National Grid "Upon completion of these planned reinforcement programmes, the Scottish-England boundary continues to show insufficient transfer capacity indicating further reinforcement may be required" and proposing substantial further expenditure in Central Scotland as well as two additional double circuit high power 400KV Transmission lines from Kilmarnock in the west and Eccles in the east across the border as well as substantial reinforcement of the transmission system all the way to the SE of England-the costs of which will all be met by the electricity consumer.

  13.  It is worth noting in passing that without any wind farm installations Scotland already generates some 60% of its electricity from non CO2 emitting sources (nuclear and water) one of the highest world wide after France with its 80% nuclear and Norway with significant water power resources.

  14.  Having established that there would be very heavy expenditure on the transmission system it is next necessary to examine where these costs fall. While it is true that all costs are eventually met by electricity consumers some paths are more direct than others. For transmission costs, the charging system is operated by National grid on behalf of the three transmission owning companies. In the case of "Use of System Charges", only a proportion (currently 27%) of the cost of the transmission capacity that their installations require is met by the generators with 73% being met by electricity consumers by payments to the Distributors through their tariffs. In addition generators of less than 100MW capacity currently qualify for a "Small Generator Rebate" amounting to some £4.5/MWHR. Tariffs published by National Grid quote a cost per annum to genertaors of £ 13.5/KW of generation capacity connected in the South of Scotland (increasing to over £ 22/KW in the North) these representing 27% for their present estimate of costs. While these costs can be expected to find their way indirectly through to consumers the remaining 73% ie £36.5/KW for generation connected in central Scotland, is charged to consumers through their tariffs as a recoverable cost by the Grid Operators from the Distributors.

  15.  It is accepted that even though the developer is relieved of some of the above charges the costs of wind power would make it uncompetitive in the UK market. The Royal Society of Engineering, The UK's premier Engineering Institution published an assessment of generation costs in 2005 and a further updated study has more recently been published by PB Power one of the UK's leading Firms of Consulting Engineers Firms. The latter shows (Fig 5) onshore wind, (even when virtually ignoring system support and transmission costs) at £55/MWhr against a market price of some £40/MWhr for bulk power in recent years and an even lower cost for new nuclear. In order to make the construction of wind farms attractive to developers the Government has decreed that wind power developers are paid a subsidy (Renewables Obligation Certificate) currently £35/Mwhr escalated with RPI as well as being relieved of the Carbon Tax Levy of £ 1.4/MWhr. These costs are also paid by consumers through their electricity bills. However because the buy out payments by Distributors who are short of the required ROC certificates are redistributed to the ROC holders, the prices at auction are considerably higher than the nominal ROC values.

  16.  The implications of these various factors for the costs of electricity from wind power located in Central and in Northern Scotland to the Consumer are therefore:


Item
Cost £/MWhr
Central
Northern

Auction price
(Energy +ROC +CCL)
93.3 (average of last 4 auctions)
Capital charges for back-up plant (80%)
""
""
22.6 (as R Academy of Engineering)
Additional running costs for part loaded plant.
""
Transmission charges (73% not met by developer)
14.9
24.2
£130.8/MWhr
140.1/MWhr



  17.  These figures of £130/MWhr and £140/MWhr are some three to four times the cost of bulk power in the electricity market (Fig 5) or power from a new nuclear station. The direct subsidy to the developer alone in the auction price at some £ 50/MWhr is more than the market value of the electricity and this is before adding the additional costs incurred by the grid operator or the additional transmission charges and system losses which are a direct charge on the consumer.

  18.  It should be noted that for new generating plant, whether replacement or additional, located in the South of England where it is needed, capital investment in transmission would be minimal. There would be no requirement for Ofgem's recently authorised £800 million to cater for wind energy in Scotland, or the further heavy expenditure which is foreseen by National Grid to transmit this energy all the way to SE England.

  19.  To put this matter in perspective, the total increase in annual costs of 8000MW of wind energy in Scotland by 2013-14 would reach the startling figure of £2,000 million in that year alone. By 2020, if the cost of the Government target of 40% wind in Scotland is met, the cost of the ROC subsidy alone, all met by the consumer, would aggregate to the startling figure of some £4,000 millions with the figures for the UK some £ 30,000millions. (See the estimate of aggregate ROC subsidies by 2020 amounting to given in the House of Lords by the Parliamentary Secretary to the DTI on 5 May 2004 and the statement by the National Audit Office that subsidies would be running at £1,000 millions/annum by 2010).

  20.  The continuance of these subsidies is at variance with claims that the present support is to be regarding as launch costs and that wind turbines will become more economic with time. Engineers know that unlike conventional methods of generating electricity, the weight and thus the cost of wind turbines goes up faster with size than does the output. So the potential for cost reductions is very limited indeed.

  21.  Even if it is accepted that some premium in the cost of energy from renewable sources is justified because of reductions in CO2 emissions these levels of cost go far beyond any foreseeable level of carbon pricing. Surely too, if we are to accept such financial penalties it should only be against the assurance of a fully effective policy but this does not appear to be the case. At present there are some 19,000 MW (compared with some 25,000 MW of renewables to meet the 2020 target) wind power installations in prospect or under investigation in the UK alone. If built there would be practically no where on high ground that one would not be dominated by wind installations. As to effectiveness, a simple calculation shows that we would need to install some 10 times this capacity each year even to compensate for the additional CO2 emissions from new coal fired power stations being commissioned in China.

  22.  The inevitable conclusion is that this massive concentration on wind must be about the worst energy investment yet devised either for its ineffectiveness or its cost/benefits for consumers. It is surely time that consumers were made aware of the massive subsidies being awarded to developers and the costs being incurred in his name and the views of consumers taken into account. It raises the question as to what level of costs is required to trigger the Government criterion of "provided the costs are acceptable to the consumer" but I submit that if these costs were more widely known they are far beyond what would be acceptable to the majority of consumers, particularly as with rising energy costs, fuel poverty is a growing issue for many households and when concern is being expressed about the competitiveness of British Industry

OTHER RENEWABLE ENERGY SOURCES AND DISPERSED GENERATION

  23.It is too easy when looking at the power of the waves to believe that here is a massive energy source which could be tapped for commercial needs and recent official statements have tended to reflect this view. Objective professional engineering opinion, as typified by the 2003 Report of the Royal Academy of Engineers and the recent report of PB Engineers (Fig 5) takes a markedly less optimistic position and one which objective engineering assessment would support.

  24.  The fundamental difficulty with many, if not all, all renewable energy sources is that the energy density is low and therefore the costs of development are inherently high; it is not for nothing that high energy density, coal, oil, gas, nuclear and high head water power have been the favoured sources for energy generation and will continue to provide the lowest cost power. The energy density in a moving fluid (wind or water) is a function of the density of the fluid times the cube of the velocity. But the velocity of a fast moving tide is some 6 knots at best over a few hours at springs (much lower for most of the time) compared with some 25 knots for a brisk wind so that even with the greater density of water the energy density on average is not that much different from wind. After taking into account the much larger forces acting on a marine turbine and the harsh environment of a marine installation, the prospects are far from promising. Nor it is likely that any new technique will overturn this conclusion; we have had screw propellers and paddles, the basis of the present marine tidal prototypes for some two hundred years during which there has been no shortage of development and no-one is holding out the prospect of a better means of transferring energy between an electrical generator shaft and a marine current.

  25.  Most engineering opinion would put the prospects for wave power development even lower than for tidal, not least because of the uncertain forces to which such devices are subjected and the logistic problems of anchoring and servicing any substantial installation. With installations on any scale there must also be a high risk of danger to navigation. These disadvantages seem to be recognised in the recent decisions of Government to determine a buy out price (admittedly at the development stage) of £177/MWhr for Tidal and no less than £196/MWhr for Wave.

  26.  Turning to micro level generation for application on a domestic scale a fundamental difficulty is that of the economics of scale. It is a good rule of thumb for most plant such as that for generating electricity that a doubling of the unit size allows a reduction in the capital cost by one third per kW of output. Thus in moving from a 600MW generator to multiple units of say 6kw there will a massive capital cost penalty and also a not insignificant reduction in thermal efficiency of generation?

  This can of course be compensated for to a degree if the exhaust heat which would otherwise go to waste can be used for space heating but this requires a good match between the electricity and the heat demands at all times throughout the 24 hours and the year. At best this could only be achievable and that on a short term basis by use of an associated energy storage system.

  27.  It is frequently asked why large central heating systems on a town scale have been so widely employed in say Sweden and Finland and not in this country. There is of course the obvious difference that they have longer and colder winters than Britain with its maritime climate but detailed investigations of this in the past have shown that the district heating is heavily subsidised by the electricity sales to the detriment of the latter.

  28.  More recently we have seen increasing demands for a "buy back" tariff for electricity sold to the grid from small installations to match the buying price. It should be recognised that this is simply a call for another form of subsidy since the value of the output from any generator which cannot guarantee to provide output over periods of maximum demand is nothing more than the value of the fuel displaced. Nor of course does the small generator bear any of the costs of providing the electricity system, the expenses of which have to be recovered within the prices for energy sales to consumers. To the extent therefore that any such tariff exceeds the fuel price this would simply amount to an additional tax on the generality of electricity consumers

CONCLUSION

  29.  The question has to be asked whether the present concentration on renewables is an appropriate response to the possibility of global warming being down to anthropomorphic CO2. The science of this seems far from being firmly established, and until it is, any measures to lessen its possible impact should I suggest be regarded as more in the nature of an insurance policy with premiums rated accordingly. To accept a charge of as much as three times the current price of bulk power would seem altogether excessive in such circumstances especially when we have to hand alternative means of electricity generation which are fully proven, vastly more economic and capable of being introduced on a much shorter time scale.

3 June 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008