The Economics of Renewable Energy - Economic Affairs Committee - Contents


Examination of Witnesses (Questions 280 - 299)

TUESDAY 24 JUNE 2008

Mr Chris Bennett and Ms Nicola Pitts

  Q280  Lord Lawson of Blaby: The existing costing you gave us earlier is on the assumption that there is nothing underground.

  Mr Bennett: That is right; the exception being the examples that were provided in our evidence. There are the Scottish options that are being considered and you will see that there are two options that are being considered there, one is an onshore reinforcement that is overhead lines, the other option that is being considered is actually cables offshore which clearly is an alternative solution so we are looking at a range of solutions offshore and onshore to get the power out of Scotland.

  Q281  Lord Kingsdown: In your written evidence you have said that you are committed to developing new arrangements for access to the transmission system. Do you have a preferred outcome from the Transmission Access Review?

  Mr Bennett: I suppose our preferred outcome is a set of access arrangements which do facilitate the connection of renewables so the role that we have been playing is very much we have taken the work that BERR and Ofgem had instigated on the transmission access reform and we have now proposed a suite of modifications to the existing contractual arrangements to deliver revised access arrangements. We believe the suite we put forward, all of the options do better facilitate the connection of renewables and we are currently going through with industry a process of assessing all the various options and going through a cost-benefit pros and cons analysis, and that is taking place this summer with the aim that a final report with all the options fully costed, with the pros and cons, will go to Ofgem by October/November of this year so given the role that we are playing at the moment, which is very much trying to facilitate a range of access arrangements, all of which have the potential to facilitate the connection of renewables, we would prefer to go through the assessment phase and then having gone through the assessment that will then hopefully give a steer in terms of which is the best model.

  Q282  Lord Best: You have partially answered my question but how much offshore wind capacity did you include in your studies, how much would it cost to connect this capacity to the grid and now a new dimension, are the current rules governing offshore networks likely to lead to an efficient pattern of investment or would you like to see any changes?

  Mr Bennett: As I mentioned earlier, our assumptions in our studies at the moment for 2020 assume 19 gigawatts of offshore wind connecting primarily on the east coast of England. As I referred to earlier, if you look at the costs that are currently being talked about for the Round 2 offshore regime, seven gigawatts is estimated to be costing £2 billion, so our best estimate at the moment for the offshore costs associated with connecting 19 gigawatts offshore would be anywhere up to £10 billion. As far as the regime associated with the offshore networks is concerned, it is difficult to say at the moment that the regime as proposed will necessarily lead to an efficient level of investment. Why do I say that? I say that for two reasons: one is you need to ensure an optimal network design offshore and that then triggers the question do you just build for piecemeal investment for each gigawatt or do you oversize certain cables to think for the future requirements of those cables? The second challenge is ensuring that when we bring the offshore network together with the onshore network the two map across in a fully efficient manner. We have therefore got some concerns with the current approach of competitively tendering for the offshore regime and there is a risk that we will end up with piecemeal offshore investments and the onshore transmission owner will not necessarily know where the network is going to land. We think further debate is therefore required on the optimal design to ensure that you get a fully co-ordinated network both onshore and offshore, and we are currently having those discussions with Ofgem and BERR.

  Q283  Lord Griffiths of Fforestfach: Given that planning permission is going to be difficult in extending transmission lines onshore do you think that building a viable offshore network is possible? If it is, how much more expensive would it be compared to an onshore expansion?

  Ms Pitts: The cabling offshore that would be used to reinforce the network and the estimations that we have made on the maps with the two lines coming down from Scotland, the actual cabling is cheaper than it would be to do onshore overhead lines; what is more expensive is the converter stations each side so there is a scale issue here and once you get to a cable length of around 250 kilometres then the economics are very similar so it would be more advantageous to do that offshore but you do need that length of cable to enable that, so it is not really possible to do shorter versions of cable, that would be a more expensive option.

  Q284  Baroness Hamwee: Lord Lawson referred to the scale of the engineering project; what about capacity in the construction industry which is something one worries about in other contexts. Is this likely to be an issue?

  Ms Pitts: It is a big issue for us and we are already investing a huge amount in the transmission system which is reaching 40 years of age.

  Q285  Baroness Hamwee: The issue is the distinction between renewables and other investment.

  Ms Pitts: One of the things that we have had to do is create partnerships with our supply chain so that we can ensure that we have got the materials and the labour in place, so some of those arrangements mean that we have to contract quite far ahead to enable us to secure the resources that we need and when you look at a situation where the whole of Europe is obviously trying to get to an increased renewables target then we very much will be competing with the rest of Europe so the sooner that we have certainty around the scale of the challenge that we have to face and what proportion the Government is going to incentivise offshore the better we can make those plans.

  Q286  Baroness Hamwee: Are there distinctions we should be aware about as to whether if you are creating an offshore wind farm in the north of Scotland or further south in the North Sea or whatever there is a loss in transmission the further the distance from concentrations of population, or is that just an irrelevance?

  Ms Pitts: Because the transmission system is there to bulk transfer it is actually a fairly efficient way of doing it and so the losses are only about 1.5 per cent, so the smaller the lines the more losses you get. On the distribution system they are around five per cent.

  Q287  Lord MacGregor of Pulham Market: How much allowance have you taken in that £3.5 billion estimate for increased costs because I quite take the point that costs are rising all the time.

  Mr Bennett: It is fair to say that that £3.5 billion at the moment is a pretty rough estimate. I referred earlier to the work we are doing with the Scottish transmission owners to really look at both the deliverability issues, the supply chain issues, some of the other things that have been mentioned and the cost. £3.5 billion is our best estimate at the moment with the costs that we are aware of, but clearly there are uncertainties around the costs at the moment.

  Q288  Lord Paul: How serious are the constraints on the transmission system likely to be as shown by your studies? How often would you have to reduce output at some stations in order to keep the power flows within safe limits and how much would it cost you? Would you ever have to "spill" wind energy because of transmission constraints?

  Mr Bennett: The studies that we are undertaking try to develop a transmission system to ensure that there is not a huge increase in transmission constraints, so we are trying to design a network and the investment that we have spoken about is to try and avoid a massive increase in constraints. On the basis of the investment that we have talked about we would not expect a massive increase in transmission constraints. Just to put it in context, if you however decided that no reinforcement was required out of Scotland and we would cope with the current system capability, also include in that assumption plans in place at the moment to allow a transfer capability from Scotland into England of 3.3 gigawatts. If no investment was undertaken and you assumed the 10 gigawatts of renewables did connect in Scotland you could get to constraint figures of between 500 million a billion per year if you did not do the reinforcement, so we are trying to design a system that has sufficient investment there such that the wind can generate. Our view is that if you did not do the investment there are real risks of having to constrain off plant and there is a question then whether you constrain off renewable plant or whether you constrain off the conventional plant, but our analysis at the moment tries to keep transmission constraints at the moment on the system around about £100 million. We would foresee, even with putting the investment in place, transmission constraints probably going up a bit because it is more difficult to co-ordinate outages with wind farms than with conventional plants, so we would expect to see an increase in transmission constraints but there would be a large increase in transmission constraints if we did not undertake the investment in our view.

  Q289  Lord Paul: What is the confidence level of this study?

  Mr Bennett: As far as the constraint costs are concerned, reasonably confident. As I say, at the moment we are currently incurring costs of around about £100 million a year, primarily in Scotland because we are currently taking out part of the transmission system to reinforce it to enable the renewables to connect, so the capability of the system is temporarily reduced while you are taking outages to actually do the system reinforcement, so we have got a reasonable history of costing constraints and seeing what the costs of constraints are over the last few years.

  Q290  Chairman: Can I take you back to the point about the loss of power over a distance as I would like to understand that 1.5 per cent. If we were talking about taking power from the north of Scotland with the big wind farms there down to London, would you expect a 1.5 per cent loss or would it be greater?

  Ms Pitts: That is the average loss on the system and you have to remember that there is quite a lot of investment that will be happening in the south of the country as well. It is not that all the power will be in the North.

  Q291  Chairman: I know what you mean; you were talking about an average and that is what I was trying to get at. Is power loss not a function of distance?

  Mr Bennett: Yes. As a supplementary question it is probably fair that we follow it up: if the average is one per cent what are the differences in terms of the north of Scotland. We could happily follow that up.

  Chairman: That would be very useful.

  Q292  Lord Macdonald of Tradeston: On that is there a choice then between a DC-based system and an AC-based system in terms of efficiencies? Are you looking at that at all?

  Mr Bennett: We are. One of the options of the reinforcements from Scotland at the moment is looking at DC links so we are looking at those areas.

  Q293  Baroness Hamwee: How much short-term reserve capacity do you normally require for fluctuations and failures—outages—and so on and can you tell us what the costs are associated with that, how much you have to pay for that and how much reserve you would require if renewables were to provide 40 per cent of our supply?

  Mr Bennett: In our role as residual balancer we look to procure sufficient short-term reserve to cover the period from real time to four hours out, and obviously, the market itself is incentivised to balance in longer timescales. In our role as residual balancer we currently hold approximately 3.5 gigawatts of reserve in this period from real time to four hours; that is roughly broken down to about one gigawatt that deals with immediate frequency response, which deals with the loss of a major generator, and then 2.5 gigawatts of stand-in reserve that can then be used to replace the energy lost by the generator. We currently hold 3.5 gigawatts therefore and the combined cost at the moment of the reserve that we hold and the frequency response that we hold is about £300 million. If you now roll forward to a world with perhaps 40 per cent renewables, the main area where we would anticipate requiring additional costs is in this stand-in reserve, it is in this period out to four hours the uncertainty and unpredictability of wind would probably mean that we would be looking to hold additional reserve. Our initial estimates have suggested that we could be looking to hold between seven to ten gigawatts of reserve. To put a cost on that, the overall additional costs of balancing the system could be in the region of £500 million to £1 billion a year, but just to put that in the context of a customer bill that probably equates to between £6 and £12 on the end consumer's bill because obviously transmission is a small element of the final consumer bill.

  Q294  Lord Lawson of Blaby: How do you hold the reserve?

  Mr Bennett: You hold it on generating plant, partially from part-loaded generating plant but we also do hold some reserve on the demand side, so the likes of Anglesey Aluminium we hold demand on that. It is a mixture, therefore, of part-loaded generating plant—

  Q295  Lord Lawson of Blaby: Do you have your own generating plant?

  Mr Bennett: No, this is the market. We procure with the market for them to effectively hold that capacity ready for us to call them. As I say, there is also some demand side response as well.

  Q296  Baroness Hamwee: Can I just pursue that, is the £500 million on top of the £300 million?

  Mr Bennett: Yes, it would be additional costs of £500 million to £1 billion per annum.

  Q297  Lord Lamont of Lerwick: A similar question, how much capacity would you need in total to meet peak demand and have an adequate plant margin if we assumed 40 per cent of electricity coming from wind power specifically. What proportion of this would really be used and would you need to make additional payments to ensure that the owners were willing to keep it available in all circumstances?

  Mr Bennett: It is not National Grid's role to ensure that there is sufficient plant margin, it is for the market to determine how much generation is required to balance their end positions, but the studies that we have undertaken under this 2020 scenario with a big penetration of wind has got an assumption of total generation capacity of 99 gigawatts against a peak demand of 61 gigawatts so that would give on the face of it a gross plant margin of 62 per cent, but as I am sure you are aware there is then a debate of what can you assume the contribution is of wind on a peak day, so there have been various studies with the industry about what contribution should you assume from wind which varies anywhere from 60 per cent to 20 per cent. If you took a 20 per cent contribution assumed by wind that would get you to probably an effective plant margin of 22 or 23 per cent, and just to put that in context, the current plant margin that we operate to is 26 per cent. In that world, in the study that we have done, there is the question of other generation that is running. If you have 30 gigawatts of wind and you assume a load factor of, say, 35 per cent of that, you would have ten gigawatts of renewable wind generating and there would still be a big percentage required of conventional plant to meet the average demand which is, say, 39 gigawatts. We believe with that penetration of wind you have still got a substantial need for conventional plant to meet the overall demand requirement because of the load factor of wind.

  Q298  Lord Lawson of Blaby: When you say conventional plant do you mean either conventional nuclear or do you mean conventional?

  Mr Bennett: It is the combination of gas, coal and nuclear. In our studies that we are starting to do, rolling out to 2030, because of the broader CO2 ambitions we are looking at increased nuclear capacity and therefore we are looking at the combination of nuclear plant and renewables and how you operate the system with a large degree of renewables and nuclear.

  Q299  Lord Griffiths of Fforestfach: As we turn out these very large numbers of investment are we right to assume that they will be entirely financed in the private sector?

  Mr Bennett: That should be the working assumption.


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008