The Economics of Renewable Energy - Economic Affairs Committee - Contents


Supplementary memorandum by National Grid

  Further to your request for additional information, please find attached below detailed answers for the respective questions.

1)  Rules governing where we can site overhead lines

  The most cost effective method of bulk transmission of electricity on mainland Britain is by overhead lines. To date virtually all transmission requirements for renewables have been met by utilising existing overhead lines although future requirements are likely to require new lines.

  The siting of our overhead lines is governed by three factors:

    1. The "Holford Rules" which are used as the guiding principles for routeing new overhead lines. These were originally formulated by Lord Holford, formerly an adviser to the Central Electricity Generation Board (CEGB), and later reviewed and supplemented by National Grid. These deal with a number of areas including route planning considerations for areas of high amenity value, scientific interest and urban areas.

    2. We would seek to route new overhead lines away from existing properties on the grounds of general amenity. We would not seek to route a new overhead line over an existing residential building (except in exceptional circumstances, such as specifically at the request of a landowner or property owner.)

    3. We would follow environmental impact assessment procedures to route a new overhead line, having followed the two factors above. Planning authorities, statutory and non-statutory bodies, administrative bodies, landowners and the general public are consulted as part of the environmental assessment process for all major new lines.

    4. If no overhead route was possible to achieve for a new line using the 3 factors above, then an undergrounding option would be considered based on case specifics. However alternative corridors / reinforcement options may exist away from built up areas and these would generally be used in preference to undergrounding.

  The information provided in both the written, as well as the oral responses, represents our preliminary views on what the investment is required to meet the 2020 target and does not include the level of detailed analysis of exact localities for the lines proposed. All the investment will be carried out in the most efficient and economic way while ensuring the above guidelines are followed.

2)  Power loses associated with transmitting over large distances in our 2020 scenarios

  Typically transmission losses account for 2% of demand seen on the transmission system. Onshore wind locating in Scotland should not increase overall loses significantly. However, for offshore wind generation, particularly for the areas designated in the Dogger Bank and the Wash on the east coast of England which are expected to contribute around 19GW, it will result in power being transferred over a large distance before connecting to the onshore grid. Initial estimates indicate losses will be in the region of 3-6%, dependent on the network technology adopted. To accommodate these increased losses it is assumed that a correspondingly larger volume of offshore generation will be needed to ensure that the overall renewable target is still met. In designing extensions for the networks, due consideration is given to minimising losses, where it is economic to do so.

3)  Level of generation reserves currently obtained from the demand-side and changes expected with high amount of wind on the system

  Currently (2008-09) 30% of the total contracted reserve is procured from the demand side. This has increased from 23% in 2000-01. We expect to see a modest increase (to 34%) next year. This is generally sourced from industrial-scale demand side providers (eg turning down demand in chemical processes and steelworks).

  Looking forward, and with more renewables on the system, our requirement for reserve will increase. There is the potential for the demand-side to play an expanded role in the provision of this reserve, however this may need to be sourced from much smaller, and more distributed loads than our current providers. In order to gain access to this reserve, and utilise it efficiently, new technology will need to be developed. We would expect that smart metering will have a role to play in this regard. Demand management technologies—that allow electric appliances, such as refrigerators and air conditioning units, to be automatically turned off or down in response to changes in supply and demand—are now becoming available. These technologies could help provide a more efficient and lower carbon, solution to the intermittency associated with renewable generation than the current approach of using conventional stand-by generation.

4)  Possible amount of UK natural gas replaced by bio-methane and challenges for both technical and sources of supply

  Work to determine the potential contribution of bio-methane in replacing part of the UK's natural gas consumption is still ongoing. There are currently no definitive figures to indicate the proportion of such consumption that it may account for. Our analysis is based on examples elsewhere in Europe such as Germany, Switzerland and Austria where bio-methane is already being injected into the gas grids. A report commissioned by the German government in 2007 on possible European biogas strategies found that EU produced bio-methane has the potential to replace roughly 50% of EU natural gas imports from Russia by 2020. This conclusion certainly serves to highlight the potential for bio-methane injection on a large scale the potential for bio-methane injection on a large scale. Such a significant contribution to the UK Government's overall renewables target of 15% would significantly reduce the burden on other technologies and would also add to the diversity of fuel sources—thus improving security of energy supply for the UK.

4.1)  Sourcing bio-methane

  A proportion of bio-methane production could come from anaerobic digestion of waste and sewage which has the added benefit of capturing the potent greenhouse gas methane from such sources. Another benefit of anaerobic digestion of waste and sewage is that it avoids the need for incineration of such waste which can cause local air-pollution.

  Delivery of large-scale bio-methane production is likely to require the use of energy crops. Clearly there is competition in the current and developing market place for such crops. However studies suggest that of all bio-fuels, biogas delivers the most energy per hectare of crops and it is also the least carbon intensive production path, with some biogas pathways actually delivering carbon-negative bio-energy. Bio-methane can be produced from a range of dedicated crops such as grass species (like sorghum, Sudan grass or hybrids) or specially bred "super" biogas maize.

4.2)  Technical challenges in supplying bio-methane

  Below are specific technical challenges in delivering bio-methane through the gas the distribution network in the UK market. These challenges are by no means insurmountable and National Grid believes that, with support from the Government and the relevant regulatory bodies, solutions can be found for each of these barriers.

  (i)  Gas quality—Regulations in the UK have been focused on the injection of large quantities of natural gas from the North Sea and imports from Europe and will present some barriers to the entry of bio-methane which has different characteristics to those of natural gas:

    a. The first issue is the Calorific Value (CV) of bio-methane. Typically bio-methane has a CV of around 36 MJ/m3. The CV entry requirements are 36.9 to 42.3MJ/m3. As a comparison the CV of North Sea natural gas is 40MJ/m3. In addition, there is a cap that requires the lowest CV source has to be within 1MJ/m3 of the flow weighted average CV to avoid CV capping and the inability to bill all the energy delivered. Bio-methane can be enriched with butane or propane to reach this minimum level, (although there would be an economic and environmental cost of doing this). There are other viable solutions including removing renewable gas from the CV cap obligation. Such solutions would require Ofgem approval.

    b. The second issue is that the oxygen content of the treated bio-methane (typically 2%) is likely to be always above the Gas Safety Management Regulations limit of 0.2%. The oxygen could be removed but this is very expensive. The other option could be to reduce the regulations on oxygen content. National Grid is investigating the feasibility of this.

    c. There is also potential for other trace elements to enter the gas. National Grid does not currently fully understand the potential for trace elements to enter the gas and whether they could be a safety concern. Further work needs to be done to assess the appropriate monitoring of the gas/feedstock to prevent any harmful elements entering the gas network.

  (ii)  Equipment requirements—The current requirements for monitoring and metering gas quality and volumes require very expensive equipment. The economies of scale needed to make this technology viable will require large plant deployment. National Grid will investigate the feasibility and assess the impact of less onerous monitoring and metering requirements for low volume injections.

  I hope the above helps to answer the Committee's questions and we will be happy to clarify and any specific parts of this supplementary evidence.

11 July 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008