The Economics of Renewable Energy - Economic Affairs Committee - Contents


Supplementary memorandum by the Office of Gas and Electricity Markets (Ofgem)

  1.  The Committee heard oral evidence on 8 July 2008 from Ofgem's Chief Executive, Alistair Buchanan, and Managing Director of Networks, Steve Smith. The Committee raised several issues during the course of the session on which it was suggested that Ofgem could provide additional advice and information.

Lessons from the Danish experience with renewables

  2.  Renewable energy currently constitutes 14% of total energy in Denmark and 28 per cent of electricity generated.[3] The UK Government's target is for renewables to contribute 15% of Britain's total energy which equates to approximately 35-40% of electricity generated.

  3.  The principal challenge that has faced Denmark in accommodating such a large proportion of renewable generation has been to manage the load variations associated with intermittency. At night time and in summer they have often had a surplus of wind generation. In order to balance the system, therefore, they have been forced to sell this electricity to neighbouring countries at very low or even negative prices. A similar challenge could be faced in Britain where demand during night time and in summer can fall to 30% of winter daytime peak levels. At the moment it would be difficult for Britain to export large amounts of surplus electricity because of our relatively smaller interconnector capacity. However, a new interconnector to the Netherlands is under construction and there are plans for new interconnectors to the Republic of Ireland, Belgium and France.

  4.  One solution that has been tried in Denmark is to put heating elements in Combined Heat and Power (CHP) boilers so that they can be switched from gas to electricity, thus using surplus wind power overnight and saving on high gas costs. While this specific solution may not be as relevant to Britain where we have a lower proportion of CHP, given time and investment it could be possible to deploy similar solutions, for example using immersion heaters in domestic heating systems. This would be likely to take time and require smarter metering and control systems to allow remote switching between gas and electric heating in response to changes in prices that may occur over short time periods.

  5.  More generally, there are a range of potential solutions involving suppliers offering new services and tariffs to encourage customers to redistribute their demand across the day. More use could be made of time-controlled domestic appliances such as dishwashers and washing machines or more advanced technologies that are able, for example, to reduce the load taken by refrigerators and freezers whilst maintaining temperature in response to prices. However, this too would require smarter metering technology as well as dynamic demand control technologies.[4]

Requirements for reserve generation capacity

  6.  National Grid (NG) operates the electricity transmission system in Britain and is responsible for forecasting demand and ensuring that enough reserve capacity is available to deal with sudden changes in demand or loss of generating capacity over operational timescales (typically changes within the existing half hourly balancing period). Generators and suppliers contract with each other in the wholesale electricity market to meet this demand and they notify NG of their contractual and physical positions. NG can then signal to generators if additional capacity needs to be brought on stream. In the event that generators' and suppliers' contractual and physical positions are not in balance at any given time, they incur imbalance or "cash out" charges that are designed to reflect the costs incurred by NG in dealing with any imbalance.

  7.  NG procures different types of reserve services depending on their assessment of risk. Generally, NG holds primary reserve (ie reserve that can respond within 2 seconds for up to 30 seconds) large enough to cover the loss of the largest single generating unit (currently Sizewell B at about 1.3GW). Under its licence obligation it is required to hold enough reserve for an event that can be reasonably expected.

  8.  Intermittent wind generators would contract with suppliers in a similar way to other generators. They would then predict their likely output, based on wind forecasts, and would have two options to ensure that they have enough electricity to meet their contractual obligations even when there is insufficient wind for them to be able to generate. Firstly, they could contract with other generators who would provide power when their wind turbines are unavailable. (Many wind turbines are part of larger generation portfolios so this process would be relatively straight forward for them.) Alternatively, they could rely on NG to procure reserve but accept that they would have to pay the costs that NG incurs in procuring and using this reserve.

  9.  A new generation of nuclear power stations would also have an impact on the amount of reserve capacity required. It is likely that new nuclear power stations would be larger than the existing ones, at around 1.6GW, and that NG may therefore be required to hold more reserve capacity to insure against the risk of the sudden loss of a nuclear power station. This may not solely be an issue for new nuclear power stations as some of the planned offshore wind farms could all feed into a single line connecting to the onshore grid and be of a similar size. This would also require NG to hold more reserve. NG have estimated on the basis of current market prices that the costs of additional reserve necessary to secure the system against the loss of the larger nuclear designs (or similar sized offshore connections for offshore wind) could be of the order of £100 million per annum to make sure they could maintain system frequency if a larger nuclear station (or offshore renewable connection) became suddenly unavailable over operational timescales—as happened recently on 27 May. These additional reserve costs would not increase proportionately for every large new nuclear station added to the system as the probability of losing two large nuclear stations is much lower than the probability of losing a single station. NG would therefore assess the cost of procuring reserve against the level of risk.

  10.  We have stated that NG would need to consult on a cost reflective methodology to target the recovery of any additional reserve costs, wherever possible, at those generators which are causing them to be incurred. This should ensure that the arrangements do not favour any particular technology but instead seek to target any additional network and balancing/reserve costs on those generators who cause them. It would simply extend the existing principles that apply to the recovery of transmission infrastructure costs and balancing and reserve costs.

  11.  In the longer term, the challenges associated with intermittency can be met through a range of established and emerging technologies combined with behavioural changes. Intermittent generation requires back up, for example when the wind is not blowing, and this could be provided by pumped storage and open cycle gas turbines as well as coal and gas stations (with or without Carbon Capture and Storage). However, as the proportion of wind energy increases, the back-up generation becomes correspondingly more expensive as it sits idle for much of the year. Emerging technologies including batteries and fuel cells could become economically viable if their costs continue to fall or if the volatility of electricity prices rise. Finally, behavioural and technological changes can help by managing demand in response to intermittency. For example, smart meters, time of day pricing and new technologies that control domestic and industrial appliances—such as shutting down fridge motors—can be used to manage demand in response to intermittency. However, all of this costs money and takes time.

The role of Ofgem in helping to meet the target

  12.  Ofgem has clear plans and timetables to ensure that there are no barriers arising from electricity and gas regulation to meeting the Government's renewable energy target.

  13.  For example, we have three main areas for action to improve access to the electricity transmission grid. First, new transmission access arrangements from April 2010 will enable better use of existing grid capacity (eg through sharing and trading), faster connections and better information to National Grid about future demand—all of which will contribute to better investment planning. Second, we are introducing short term measures to allow renewable generators to connect to the grid in the next two years, before the new enduring access arrangements come in, if they are able to accelerate their plans. Third, we aim to have in place new investment incentives on the network companies within the next 12 months which will protect consumers by encouraging grid companies' shareholders to take on more of the risk when they seek to invest. More information on this work can be found in paragraphs 27-43 of our initial memorandum.

  14.  All this is in addition to Ofgem's existing work through our price controls. We are allowing a 160% increase in investment in the onshore electricity grid between 2007 and 2012. This is to upgrade the wires and connect new generation, much of it from renewable sources. The funding is flexible and can increase automatically if more generation seeks connection than was assumed when the price control was originally set.

  15.  We also have workstreams addressing the issues for smaller generators, covering distributed energy, microgeneration and the role of the electricity distribution networks. We are advising Government on design of policy in relation to heat and energy efficiency.

Could the costs become excessive?

  16.  Members were interested to understand the circumstances in which the cost of promoting renewables could be excessive.

  17.  The cost of promoting renewable electricity generation will depend on a number of factors including the level of any target, the robustness and efficiency of the policy measures, the resource costs of the technologies and their evolution over time, and the impact on system security and balancing costs.

  18.  One scenario could be if the subsidy mechanism to meet a renewable energy target is poorly designed and has unintended consequences. For example, when the existing Renewables Obligation was designed, few in the industry would have anticipated the large increases in wholesale electricity prices that have occurred since 2003 or the introduction of a carbon price through the European Emissions Trading Scheme. As a result, the level of subsidy for some forms of renewables has exceeded the amount needed to make them viable. This problem could be addressed by Ofgem's suggestion of linking the level of subsidy inversely to the wholesale electricity price.

  19.  A second scenario could be if insufficient attention is paid to other more effective and efficient ways to achieve green house gas emission reductions. These means could include other low carbon generation technologies, energy efficiency, emissions trading and renewable heat—as well as renewable electricity. At present, for example, there is considerable uncertainty about the future costs of different renewable energy technologies. The main rationale for supporting renewables at greater cost than the shadow price of carbon is to develop the technology so that costs fall. Generally, the best way to ensure that the costs incurred do not exceed the level necessary is not to support particular technologies but to put in place broad-based policy instruments which allow the market to find the most cost-effective way of reaching the overall objective of reducing carbon.

  20.  A third scenario whereby costs may be excessive would be if there was no locational signal in transmission charging and most new renewable generation chose to locate in the most difficult areas for the network to accommodate at significant cost and with potential environmental damage if there were other, low carbon generation technologies that could be located closer to demand reducing the economic and environmental cost of a much larger grid. This is discussed further below.

Locational transmission charging

  21.  The further a source of energy is from its end user, the more it generally costs to transmit. Generators who are sited closer to the main centres of demand therefore pay lower network charges than those who are further away.

  22.  The approach of locational charging has two main benefits. First, it is equitable because the charges to generators reflect the costs they are imposing on the grid. Second, it encourages generators to make efficient decisions about where to locate. This helps to reduce costs to customers and cut carbon emissions. To see how this works in practice one can look at the example of the north of Scotland. This largely rural area is far away from the main sources of demand for electricity in Britain. Generators who choose to locate in the north of Scotland therefore pay higher network charges to reflect the associated costs of transmitting it to the main urban centres. Scottish customers, on the other hand, pay substantially lower network charges than in the south of England, because they live nearer to the electricity and it does not have to travel as far to reach them.

  23.  Critics of the current approach tend to come from one of two perspectives. Some argue that the locational charges do not vary enough and that there should be an even stronger economic signal to generators to site their plant closer to demand. For example, Professor Andrew Bain argued in his written evidence that there should be an additional locational charge to take into account the cost of the electricity lost as it travels down the transmission wires. At present, all generators pay equally based on the average cost of electricity lost on the whole transmission system rather than for their specific loss factor, which can vary significantly at different locations on the network. We are sympathetic to Professor Bain's argument and for over 15 years we have supported proposals to change the industry rules in order to introduce locational charging for transmission losses. However, some generators have vigorously opposed the proposals and have subjected them to judicial review three times—most recently winning a challenge in June this year. We have continued to indicate our support for the principle of locational transmission losses charges but there are currently no such proposals on the table. Under the current industry rules, Ofgem does not have the right to initiate such proposals and so they must come from the industry itself.

  24.  Others argue that the current approach unfairly penalises Scottish generators by making them pay higher charges (even though Scottish customers benefit by paying lower charges). We do not think that this argument is convincing. The introduction of locational charging has not proved to be a disincentive to renewable generation in Scotland, and the major barriers to renewables are in fact planning delays and the time needed to build transmission connections.

  25.  Before locational charging was introduced, Scottish generators had to pay a number of separate fees for accessing the network and transmitting their power. These fees have now been replaced by a single locational transmission charge, thus making the system much simpler. Second, locational charging does not harm the viability of renewables in Scotland given the support these schemes receive through the Renewables Obligation. In fact, since the launch of the Britain-wide electricity market in 2005, a queue has built up in Scotland of around 165 renewable projects awaiting connection—significantly more than is needed to meet the Scottish Government's renewable energy targets. This evidence is in line with the conclusions of two sets of consultants hired by the Government to assess the economic case for using the power under section 185 of the Energy Act 2004 to cap transmission charges for renewables in remote parts of Scotland. The consultants concluded that even with locational transmission charges a 250MW windfarm on the Orkney Islands could earn a rate of return of nearly 40% based on the current level of support offered by the RO scheme. Both sets of consultants concluded that using the powers would not be necessary to make wind projects in Orkney and Shetland viable, and that there was only a marginal economic case for using the powers in respect of the Western Isles.[5]

  26.  We hope this information is useful to the Committee and we would be happy to provide any further assistance that you may require.

Steve Smith

Managing Director of Networks

1 August 2008



3   Danish Energy Authority Back

4   Dynamic demand control devices can either be built into appliances or be attached to appliances and communicate with a smart meter to change their electric demand dynamically according to the conditions on the grid and/or movements in energy prices. Back

5   http://www.berr.gov.uk/files/file46776.pdf Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008