Select Committee on European Union Twenty-Seventh Report


APPENDIX 5: VISIT TO SCROBY SANDS OFFSHORE WIND FARM—9 MAY 2008


The Members of the Committee that visited Scroby Sands were Lord Freeman (Chairman), Lord James of Blackheath, Lord Powell of Bayswater, Lord Walpole.

Scroby Sands is a wind farm owned and managed by E.ON. It was opened in 2005 and is sited 2.5km off the coast of Caister, near Great Yarmouth. It has a generating capacity of 60MW, supplying energy for 41,000 homes.

The Committee were met by Dave Rogers, UK Regional Director of E.ON Climate and Renewables, Adrian Chatterton, Head of Construction and John Beresford, Asset Leader for the wind farm.

Dave Rogers gave the Committee an overview of E.ON Climate and Renewables, a business within E.ON set up in 2007 to manage and develop E.ON's renewable energy portfolio. E.ON has 1353MW of renewable generation installed in Europe and the USA. 245MW of this is sited in the UK spread across 20 generation sites. These sites include 2 offshore wind farms, 1 biomass plant and 17 onshore wind farms. The Scroby Sands installation is the largest of these. Currently under construction is a third offshore wind farm in the Solway Firth. This wind farm, Robin Rigg, will have a generating capacity of 180MW.

Adrian Chatterton then gave a presentation describing the construction of the Scroby Sands site. The choice of the site on the relatively shallow waters of Scroby Sands had benefits and problems. The shallow waters mean that the 7.4km2 site is located away from shipping lanes. This was a problem during construction because it required the use of suitably shallow draught construction vessels and construction could not be carried out a low tide. The Scroby Sands site does, however, benefit from good port facilities at Great Yarmouth and Lowestoft.

The power generated from the wind farm is cabled back to shore and connected at an existing substation to the distribution network. This meant that the project bypassed any potential problems with connection to the transmission grid.

During his presentation Mr. Chatterton identified some of the constraints on developing this kind of wind farm. There are the practical difficulties of matching the construction plan to suitable weather and tidal conditions. More importantly there are supply chain constraints. All energy generators will be affected by rises in copper and steel prices but there are particular supply chain problems for renewable energy. For example, during the construction of Scroby Sands E.ON used turbine piles made by two different manufacturers. These firms no longer exist and Robin Rigg will use parts made by only one company. Similarly, specialist vessels needed for offshore construction are in short supply. The uncertainty created by these conditions can be seen in the price for construction. Whilst Scroby Sands cost around £1.2m per MW, future projects will cost at least £2.4m per MW.

In order to stimulate the necessary industrial infrastructure clear and stable policy signals are required from Government. All three of the representatives welcomed the proposed re-banding of the Renewables Obligation (RO) scheme to provide 1.5 RO Certificates per MW for offshore wind and stated that without this change the construction of offshore wind farms would not be possible.

John Beresford then gave a presentation discussing some of the practicalities of keeping the wind farm operational. The turbines can generate power with wind speeds as low as 4 m/s and will generate at their full potential at speeds of 14-25 m/s. Above this point the blades are turned from the wind to avoid damage. For around 90% of the time the turbines will be generating at an overall load factor of around 30%.

As with the construction of the wind farm, maintenance is affected by weather conditions and lack of specialised vessels. Maintenance is not possible for around 120 days a year due to weather conditions and the two existing vessels suitable for large scale maintenance work are frequently in demand for other projects. This increases the cost of the running of the wind farm in comparison to an onshore installation.

The Committee then took a boat out to the wind farm. During discussions on the boat the current state of offshore farm development was characterised as needing to evolve from a "cottage industry" to a full industrial size. This move is apparent in the difference in generating capacity of Scroby Sands (60MW) and Robin Rigg (180MW). It was noted, however, that the gas-fired power station in Great Yarmouth can generate around 400MW with a higher load factor than wind farms. Another issue related to this increase in scale was that the operation of Scroby Sands has provided lessons in matters relating to offshore wind farms. For example, some of the original gears in the Scroby Sands turbines were found to be too fragile despite being tried and tested over some years on onshore wind farms. The Robin Rigg site is now being built with more hard wearing gear boxes.

The issue of planning was also discussed. Whilst no specific planning problems were discussed in relation to the Scroby Sands site, it was suggested that to facilitate the planning system a target for renewable generation should be set for local authorities (as exists for waste recycling) rather than simply encouraging them to work towards a national target.


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008