Select Committee on European Union Written Evidence


Memorandum by Ecotricity—Further information following the Committee's visit to Bristol Port Wind Park, on 23 May 2008

1.  ONSHORE WIND—POTENTIAL CONTRIBUTION TO TARGETS

  Ecotricity's view is that onshore wind could provide at least 10% of the UK's electricity.

  Current UK consumption is 350,000 GWh per annum, 10% would be 35,000 GWh.

  A typical onshore wind turbine will produce around 3 GWhs per MW installed and typical turbine sizes are rapidly approaching the 3 MW installed level. Using these figures we would need, in total, about 4,000 wind turbines to provide 10%.

  Allowing for the 1+% that wind already provides in the UK, we would need an additional 3,600 turbines to bring the total contribution of wind up to the 10% level. Although within the likely timeframe of this happening (up to 10 years) typical turbine sizes will increase. 3,600 new turbines therefore represents the higher end of the probable outcome in that respect.

2.  BARRIERS TO ONSHORE WIND

  Without question, the biggest single barrier to onshore wind energy is the planning system. Wind energy finds itself in a planning system not designed for it and not fit for purpose.

  Wind energy is the only major generating source which requires planning approval from District Councils. The Government takes the planning decisions for all other forms of generation, and for good reason. District Councils are (and have amply demonstrated themselves) not capable of balancing national strategic interests with those at the parish level.

  Under current circumstances, and often against planning officers recommendations, two thirds of all planning applications for wind projects are turned down and two thirds of all subsequent appeals are upheld. That's a lot of bad decisions being overturned eventually, but at great cost in time and money to the developer and council alike.

  All other major forms of generation are consented through the Section 36 process. This process was conceived before wind energy (and renewable energy) became possible on a commercial scale, and it is designed to take all but the very small conventional generators out of the hands of local councils and into the hands of the government. The cut off threshold, below which a project is in the hands of the local council, is 50 MW. For conventional generation that is indeed a very small project—very few gas and no coal or nuclear power stations exist at this size and nor will they. However 50 MW is a very large wind farm.

  The Section 36 process could easily be adapted with a different threshold for onshore wind to reflect its different size characteristics.

  Ecotricity believes that wind projects of up to 3 turbines or 2 MW total installed capacity could be dealt with by district councils. County councils could readily manage wind applications of up to 20 MW, since they are already used to dealing with strategic issues, such as waste. Applications above 20 MW should go straight to the new streamlined section 36 process that is intended to commence operation next year.

  Whilst there are a small number of very large (in excess of 100MW) wind projects in the UK, these are the exception. These large sites (predominantly north of the border) are all but fully utilised and future emphasis will naturally fall on the smaller sites and those in England. Factors such as nearby housing, designated land (eg SSSIs, AoNBs, etc), proximity to grid, available wind resource, access to site and landowners' willingness to host wind projects, all act to restrict the size of potential wind sites. This is true universally but more apparent in limiting site size in England.

  The bulk of England's potential sites are below 50 MW, and considerably so. It will not be utilised in a timely fashion if it remains in the current planning process. It is imperative that the anomaly of wind energy being the only generation technology to be consented by District Councils is brought to a timely end.

3.  OFFSHORE WIND

  Against the backdrop of onshore planning problems, offshore wind has often been touted as the answer to the UK's renewable energy issues. Offshore wind however costs around twice as much per installed MW as onshore wind. The principal additional cost is incurred installing the turbines and transporting the power back to shore.

  A key claim for offshore wind (other than easy planning) is the high potential load factor, often cited to be 30% higher than onshore projects (40% for offshore v 30% for onshore). But offshore projects have yet to deliver on that promise.

  Round One offshore projects have been subject to annual reporting and a recent government report shows that none of these projects delivered anything close to the 40% load factor promise and most performed no better than a good onshore project (at 30%)—in some cases a good deal worse than onshore.

  There are a number of reasons for this, perhaps the greatest and most obvious is indicated by the availability factors of these machines—which are very low by onshore standards (in the low 80 percents rather than the high 90s). Putting aside the question of whether offshore machines are as reliable (in such a tough environment) as onshore ones, it is clear that what may be a simple maintenance task onshore can take dramatically different proportions offshore—with the need to operate within weather windows and with available barges and other equipment.

  Ecotricity has no doubt that more productive winds exist offshore but we believe that this possible upside has been outweighed considerably by the realities of operating machinery in the offshore environment—and perhaps this has been overlooked to date by offshore's various ardent proponents, not least of which is the government.

4.  THE POTENTIAL OF MICRO GENERATION

  What potential does micro generation have to contribute to our national energy needs? Ecotricity believes the answer is in the question—it is Micro.

  Whilst micro generation undoubtedly engages people to think about where their energy comes from, and makes them use it more wisely, this is perhaps it's only saving grace.

  On purely economic analysis it has no rationale— it is the most expensive way to deliver renewable energy targets by a very long way and it is probably the most expensive way to deliver carbon reduction targets—possibly more so than new nuclear.

  Micro Generation technologies available today fall into just two camps—Solar PV and micro Wind.

  A typical PV installation will cost £5k for 1kW installed and that 1kW will produce about 1MWh per annum. These are broad but reasonable numbers.

  A typical micro Wind turbine of 1kW will cost £2k to install and will produce virtually nothing. This is the situation with the first generation of micro wind.

  Ecotricity believes that second generation micro wind turbines will be available for around £3k per kW installed, and each kW installed will produce roughly 1 MWh per annum—on a par with 1kW of solar.

  We offer these two examples of micro generation to demonstrate our point regarding costs and cost effectiveness for any given budget. Existing PV and second generation micro wind—compared to onshore macro wind;

  A large wind turbine of 2 MW will cost around £1.8 Million to install today, and will produce roughly 5,000 MWh each year.

  To match this output with solar PV would require 5,000 kW of solar (on up to 5,000 roofs) at a cost of £25 Million.

  To match this output with micro wind (version 2.0)—will require 5,000 1kW machines at £3k each—£15 Million total cost.

  In both cases an order of magnitude greater cost to achieve the same result with micro as with macro. Do we really have that much money to spare?

  Germany is often held up as a great example of how micro generation can be (aided by FITs). It is often said that Germany has 13% of it's electricity from wind and solar projects and the inference given is that micro generation (which means solar in Germany) plays a significant role in that 12%. But it does not. Examination of the figures from German Federal bodies shows that solar (for which read micro generation) contributes 0.3% and large scale projects contribute 11.7%. That is the truth behind the statistics.

  0.3% may be considered by some to be nonetheless an achievement—but consider that at 30p per unit, had the money instead been spent on large scale wind energy, rather than 0.3% resulting from that spend - Germany could have had six or more times the renewables contribution, more like 2% of national consumption. The multiple would be far greater in the UK where we have a much better wind resource than in Germany.

  Ecotricity believes that micro generation is an emotional distraction from real energy policy, an easy conversation for politicians to engage in, it being hard to find someone who is against it (it's like "motherhood and apple pie")—it appears an easy answer. Until you examine the numbers.

  Our suggestion is that government policy at the household level should focus on energy saving, where significant in roads to consumption could be made for economic sums—and energy policy should focus on macro generation where significant scales of economy will pay real dividends.

5.  DOES THE UK NEED FEED IN TARIFFS TO SUPPORT MICRO GENERATION?

  It is not always appreciated by people when discussing FITs and micro generation that there is currently no economic way to meter the power from a micro generator and consequently the power is "spilled" into the local distribution network where it reduces losses on the system. No electricity supplier can have the export from a micro generator "notified" to their "account" and therefore micro generation has no actual value to electricity companies individually—they can't get their hands on it, put simply.

  The reason for this is that "settlement meters"—the only meters that the UK electricity settlement system allows to be used to notify generator output—cost many times more per year to operate than the value of the export from a typical micro station.

  It's a popular misconception that FITs would apply to electricity suppliers, and that this is how it works elsewhere.

  An obligation to provide FITs in the UK would need to be on the Distributions Network Operators (DNOs)—not the electricity suppliers themselves.

  DNOs charge all suppliers to use the local distribution system, and one of those charges is for losses—pro rata according to the volumes each supplier puts through the network.

  Thus if a DNO paid for the micro export, the cost would fall evenly on all suppliers operating in that part of the network—pro rata to their volume. The costs of FITs would be shared equally between the beneficiaries—the suppliers whose losses are reduced by micro spill.

  FITs would require an obligation on DNOs, and a new piece of legislation.

  The job of FITs is to pay enough money for micro generation to stimulate more of it. This can be done through the RO, by giving more multiple ROCs to micro than the two currently proposed.

  To emulate German levels of around 30p per unit we would need to give 6 ROCs per unit, maybe more.

  If policy is to support (and pay for) micro generation, irrespective of its economic shortcomings, Ecotricity believes that FITs are not the best way to do this.

  Ecotricity believes this because although FITs could be made to work in the UK, this would require new legislation on DNOs—whereas existing RO legislation could do the same job, more quickly and more easily.

7 July 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008