Select Committee on European Union Written Evidence


Memorandum by the Energy Networks Association

INTRODUCTION

  1.  The Energy Networks Association is the energy industry body funded by UK gas and electricity transmission and distribution licence holders and operators.

  2.  ENA supports the promotion of renewable power, in order to tackle climate change and enhance security of energy supply, and we welcome this opportunity to provide some context and background on the EU and UK renewable energy targets, as seen from the networks' viewpoint.

  3.  Networks companies, both transmission and distribution, have been very active in facilitating the connection of renewables to the electricity grid. Nevertheless, the EU has set an ambitious target of 20% of energy from renewable sources by 2020. Meeting the UK's own share of this target, 15% of our final energy demand to be met by renewable energy, could mean that up to 40% of electricity consumed would need to be generated from wind power and other renewable energies by 2020. This huge increase in renewable generation represents a significant planning and techno-economic challenge for the networks.

ROLE OF ELECTRICITY NETWORKS

  4.  Transmission networks play a fundamental role in meeting the UK's energy policy goals, especially in terms of accommodating renewables and potential new nuclear build. All UK Transmission Owners and the GB System Operator have been actively and directly engaged in assessing the capacity and utilisation of existing transmission system infrastructure, considering innovative approaches to network management and operation, and upgrading the existing electricity transmission system in order to connect additional generation.

  5.  Distribution Network Operators (DNOs) have similarly been very active in accommodating renewable distributed generation, (DG), connected directly to the distribution network.

  6.  In doing so, all the network owners and operators have reviewed the technical rules and standards and commercial arrangements for access and connection, whilst continuing to ensure the efficient and economic design and operation of the networks.

PLANNING ISSUES

  7.  Lengthy planning procedures for renewable generation projects, transmission lines and distribution networks present a major obstacle to the development of renewable sources of energy. Reform of the planning system is needed if we are to connect up new, remote renewables generation in time to meet the 2020 targets. The requirement to transport new and diverse energy from remote areas and between communities calls for a new approach to planning. The sources of much of the renewable energy needed to meet the EU targets are remote and currently unconnected to the electricity network. The Yorkshire transmission line took over 10 years to complete thanks to the planning process and the Beauly to Denny transmission line, essential to transporting new wind energy generation, has already been delayed by a number of years.

  8.  We believe the Infrastructure Planning Commission proposed by the Government's Planning Bill will have a vital role to play in delivering these objectives, provided it is sufficiently and expertly resourced. We welcome the proposal for pre-agreed timescales, and are urging the Government to set time-limits for each stage of the planning process in order to provide maximum certainty for developers and affected communities.

  9.  We also believe that the legitimate needs and concerns of local communities must be a central consideration. The effectiveness and transparency of decision making are fundamental to underpinning community engagement and ensuring that developments move forward effectively and in a responsive way. As a result, local communities must have a full opportunity to express their views and be heard. Central to this will be enhanced duties placed on developers to ensure that local communities are effectively consulted before an application is made. The energy sector continues to strive for the very best practice in this area and has already had discussions with groups such as the Campaign to Protect Rural England to ensure standards are continually improving.

SHORT TERM TECHNICAL CHALLENGES FOR THE NETWORKS

  10.  In operating transmission and distribution networks most emphasis to date has been placed on increasing the use of the existing electricity networks, and identifying opportunities to connect additional generation capacity within the existing regulatory and commercial frameworks.

  11.  Network owners and operators have actively been seeking more innovative engineering approaches to network management and operation, including the deployment of new network technologies to manage the volume of network constraints and allow network access. However, the scope for further improvements is relatively limited and often site specific. Consequently increasing attention is being given to the development of new analytical and operational methods to deal with the present and future technical challenges presented by renewable generation, including offshore transmission infrastructure.

  12.  A further important consideration when connecting renewable generation is the level of security required, and the appropriate level of investment to maintain such system security, whilst continuing to ensure the economic and efficient operation of the system. In the case of offshore electricity transmission in particular, this has meant an assessment of the relevance of the existing technical rules governing onshore networks for offshore networks, and the development of a range of feasible alternative options for offshore security standards. Similarly, network operators have been offering terms for a less firm connection than that normally required. Even when these connections are attractive to generators, the lowering of technical and security standards should only be done following careful consideration of the likely implications for overall system reliability and security.

LONGER TERM CONSIDERATIONS

  13.  The EU's general 20% and the UK's national 15% renewable energy targets will have a profound impact on the need for new network capacity and the associated network investment needs. The consequences which increasing levels of renewable energy with intermittent or variable output could have on the overall stability and security of supply and system back-up and balancing will also present technical challenges.

A.   Capacity needs

  14.  Technical evaluations of the networks adequacy against likely generation patterns in Scotland and Wales have already been conducted and various development options investigated eg the Transmission Investment for Renewable Generation (TIRG) projects, the Renewable Energy Transmission Studies (RETS 2003 and RETS Revisited 2005), and Technical Advice Notes (TAN).

  15.  Ofgem is undertaking a review of credible generation scenarios to meet the 2020 targets eg the Long Term Electricity Network Scenarios (LENS) project, which could be used to identify not only the expected generation patterns, but also future infrastructure and technological needs.

B.   System Balancing

  16.  Wind power, both on-shore and offshore, is presently the principal commercially available and scaleable renewable energy technology in the UK. Wave and tidal generation technologies are at an earlier stage of development but are expected to be developed for commercial use within the next decade, and will also need to be accommodated into the networks.

  17.  When considering wind power, there is a need to identify the nature of wind variations in national and regional generation and demand groups, and then assess the implications of such variations given the flexibility available from responsive generation and load locally and, via interconnections, more remotely.

  18.  Increased levels of intermittent generation, such as wind, will significantly increase the need for capacity of other generation that would need to be kept in service to operate on low wind days. A close monitoring of the margins is needed to ensure that there is always sufficient flexible generation or demand side response to meet demand cycles, plant breakdowns and frequency control requirements.

C.   Network Investment Costs

  19.  It is clear that substantial investment in the networks will be essential, to pay for the renewal of infrastructure, the connection of greater levels of renewable generation, and to allow the networks the flexibility to respond to the needs of network users and consumers.

  20.  ENA Member Companies are now beginning a programme to replace more than two thirds of the existing network as it nears the end of its design life, and to shape it for these new and increasingly complex and diverse patterns of generation. In building new infrastructure, the aim will be to maximise the opportunities for integrating green energy/low carbon designs.

  21.  The Regulator also has a fundamental role to play in setting the market and regulatory frameworks based on a full and detailed analysis of the options to facilitate efficient and timely investments in infrastructure. A forward looking and supportive regulatory regime is required. A stable investment target is needed to ensure that the required future investment is put in place, and policymakers must then retain a strong commitment to meeting these targets.

D.   Pan European Research

  22.  In 2005 the SmartGrids European Technology Platform for Electricity Networks of the Future was established. Its aim is to formulate and promote a vision for the development of European electricity networks looking towards 2020 and beyond.

  23.  The Platform includes representatives from industry, transmission and distribution system operators, research bodies and regulators. It has identified clear objectives in the context of the drive for lower carbon generation technologies and greatly improved efficiency on the demand side that will enable customers to become much more interactive with the networks.

  24.  Network technologies are able to contribute to the further improvement of network efficiencies in operation and investment, but they can also facilitate the implementation of a range of alternative future electricity developments, from centralised to distributed generation.

E.   Skills

  25.  The large scale network development to accommodate renewable energy will require a substantial increase in qualified and skilled workers to build and operate the new infrastructure. There is a need for innovative and highly qualified engineers to design new systems that push at the boundaries of network technology.

  26.  As a responsible industry, our members are actively involved through the Sector Skills Council (EU Skills) in collectively looking at the skilled resource challenges for the sector. We need to make the networks sector more "career attractive" to young people and ensure that we have good, and experienced, academic and sector specific trainers.

23 April 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008