Memorandum by PB Power
PRESENTATION MADE TO THE COMMITTEE ON 23
JUNE 2008 SUMMARY OF MAIN TIDAL RANGE PROPOSALS REVIEWED BY THE
SUSTAINABLE DEVELOPMENT COMMISSION IN 2007
Sustainable Development Commission
Brief
To review tidal power in the UK
Process
Focus on Tidal Range (Barrages /
Lagoons) and Tidal Stream Technologies
Published Reports and Recommendations
Output
"Turning The Tide"-main
report
5 Supporting Research Reports
For the Severn Estuary|.
SDC Findings
1. There is no conflict between Tidal Stream
and Tidal Range Technologies
2. Strong Case for Tidal Lagoon Demonstration
Project
3. Strong Case for a sustainable Severn
Barrage
4. Climate change adaptation may present
an "environmental opportunity" when considering compensatory
habitats
5. Should be publicly led with innovative
financing to allow public risk / reward to be in balance
MAIN OPTIONS
Cardiff Weston Barrage
17TWh per year electricity generation
costing £15 billion
Shoots Barrage
2.75TWh per year electricity generation
costing £1.5 billion
Tidal Lagoons
Swansea Bay Lagoon generates up to
187 GWhper year at a cost of £250 million
ISSUES
Environment
Water Framework Directive
Appropriate Compensation
Commercial
Cardiff Weston Tidal Barrage
8640 megawatts installed capacity
17,000 million kilowatt hours annual
output, equal to 4.4% current UK electricity demand 216 turbine
generators, 9 metres diameter, rated at 40 megawatts each
166 sluices, total area 35,000m2
2 locks for pleasure craft
480m2 enclosed area of basin
LOCATION
Between Brean Down and Lavernock
Point
COST
NON ENERGY
BENEFITS
Potential for new Road and Rail Crossings
OPERATION
Generates on the Ebb Tide
Predictable but intermittent energy
Requires additional national grid
infrastructure


Shoots Tidal Barrage
1050 megawatts installed capacity
2,750 million kilowatt hours annual
output, equal to 0.8% current UK electricity demand
30 turbine generators,7.5 metres
diameter, 35 MW
42 sluices, total length 1.26km
1 lock for ships and pleasure craft
93 sq km enclosed area of basin
OPERATION
Generates on the ebb tide
Refills on the flood tide
Downstream: Tidal levels similar
to today's
Upstream: Upper tidal levels marginally
reduced and tidal range approximately halved
Large number of sluice gates to allow
tidal basin to be recharged using only the upper water levels
where silt load is lowest
Navigation upstream of barrage through
ship lock requirements determined by Gloucester Harbour Trustees
COST
NON ENERGY
BENEFITS
Flood Defence -Gloucestershire
Rail Link adjacent to existing Severn
Tunnel
CONSTRUCTION PROGRAMME
Tidal Lagoons
MANY DIFFERENT
PROPOSALS
Other shallow locations within the
Estuaryeg Bridgewater Bay
4500MW potential capacity identified
in the Severn
SWANSEA BAY
LAGOON
Promoted by Tidal Electric Limited
Estimated Capital Cost:£81.5
million
(Tidal Electric Limited Figures)
NB: A separate DTI Review however challenged
these figures, giving a total cost estimate of £255 million
and energy yield of 124GWh per year.
A more recent npower study in Liverpool Bay
for a similar sized scheme estimated constructions costs of £108-£135
million
COST BENEFIT
| Option | Capital Cost (£m)
| Annual Output (GWh) | Cost per kWh at 8% (p/kWh)
|
| Cardiff Weston Barrage | 15,000
| 17,000 | 8.54 |
| Shoots Barrage | 1,500 |
2,750 | 6.80 |
| Swansea Bay Lagoon (TEL) | 81.5
| 187 | 4.15 |
| Swansea Bay Lagoon (DTI) | 255
| 124 | 18.39 |
23 June 2008
|