Select Committee on European Union Minutes of Evidence


Supplementary memorandum from the Department for Business, Enterprise and Regulatory Reform

INTERMITTENCY

  First, it might be helpful to clarify the terms that are used in relation to the characteristics of renewable generation such as wind. All generating technologies are to some extent variable ie output may move up or down and intermittent ie output may stop altogether. We generally use "intermittent" to express both these characteristics. The key issue in relation to wind and some other renewable technologies is that this intermittency is relatively unpredictable (although sufficiently predictable in the short term to allow "on the day" balancing of the system) and relatively uncontrollable (whilst output can be curtailed, it cannot be increased in response to changes in the supply-demand balance).

1.   What implications does the problem of intermittency have for conventional generation?

Increase in generation capacity margin

  Wind generation has a low capacity credit—ie the extent to which it can be relied on to meet demand in system planning timeframes is low, generally estimated to be between 10%-20% of the installed capacity. This means that the deployment of wind is largely to displace fuel rather than generation capacity. Responsive (thermal) generation capacity (largely fossil fuel, but could include renewable biomass) must be maintained (ie not retired) to support system reliability. This does not have to be on a full one-for-one basis, but the low capacity credit of wind generation means that even with a large amount of wind capacity, our need for conventional capacity is unlikely to reduce much below the levels we now have and the capacity which is soon to close under the Large Combustion Plants Directive will still need to be replaced.

   A consequence of this is that with significant penetrations of intermittent generation some thermal plant will have to act solely as "back up" capacity, running principally at peak demand when there are low wind speeds. This plant will, therefore, have very low load factors and be able to recover its investment and fixed operating costs only at limited (and unpredictable) times throughout a year. In the near-term, it is likely that older plant will be relegated to operating in this way as the level of wind penetration grows.

Balancing: increase in need for flexibility and reserves

  An increased penetration of variable and difficult to predict renewable power will place an additional duty on the remaining generating plant with respect to balancing supply and demand. Increased variability will increase the need for flexibility required from conventional plant, while increased uncertainty in wind output will increase the need for various forms of reserve services, generally provided by a combination of synchronised plant operating part-loaded, demand and standing reserve.

  The cost of this additional flexibility and reserve will be driven by conventional plant flexibility and plant efficiency when operating part loaded. However, non-generation solutions, such as demand response and interconnection technologies may be used to provide balancing services. Analysis of alternative options in terms of their costs and benefits in different systems requires more work.

2.   What differences, in terms of intermittency, are there between different sources of renewable electricity?

  There are a number of technologies that are classed as renewable: these include wind, hydro, tidal, wave, biomass, solar PV and landfill gas. Each has different characteristics in terms of its intermittency and predictability.

  Wind turbines are intermittent being dependent upon the wind blowing at a minimum speed to enable operation. Similarly, waves are generated by the wind and so the availability of waves sufficient to enable generation will vary over time. Solar PV is dependent on sunlight so will vary over the year and with daily conditions. Hydro is dependent upon levels of precipitation so will vary, though in a more predictable manner than wind.

  Tidal technologies (both stream and range)—are also intermittent but are totally predictable.

  The ability of these technologies to generate at any given time will vary, as will the level of output that can be achieved as a percentage of total rated capacity as these both depend upon the available resource at that time, which is variable.

  Biomass and landfill gas are controllable and able to respond in a similar way to other forms of thermal generation.

3.   It has been suggested that to achieve the target of 20% of final energy it will be necessary to achieve between 35-40% of electricity generation from renewable sources. In evidence we discussed intermittency being a containable problem up to around 20-30% of renewable electricity generation. What would be the impact of a higher percentage of renewables penetration?

  There is good evidence of the impacts of renewable penetration at 20-25% levels. The UK Energy Research Centre produced a helpful synthesis of this evidence. They found that there were no technical barriers to accommodating this penetration of renewable generation and that the costs of maintaining system reliability and system balancing were relatively modest (0.1-0.15 p/kWh spread across all demand).

  However, this analysis was based on the assumption of a highly flexible generation system and is valid for relatively small levels of penetration. In relation to higher levels of penetration, such as 40%-50%, we need to do further analysis. The indications are that the challenge is an economic rather than technical one, ie ensuring that sufficient capacity of all technologies has the right incentives to remain on and join the network to support the deployment of intermittent renewable technologies and ensuring the economic and efficient operation of the balancing mechanism.

  Looking further ahead there are measures that may mitigate the effects of intermittency eg:

    —  Demand-side measures:

    —  flexibility: there are a number of aspects to this, including dynamic demand providing remotely controlled short-term response (eg in fridges or air conditioning) and longer-term response through shifting demand in response to price and/or weather conditions.

    —  Increasing electricity demand: moving non-electricity demand into the electricity sector (eg using electricity to supply demand that has been traditionally supplied by gas).

    —  In a system characterised by high penetration of intermittent (eg wind) and inflexible (eg nuclear) generation there is an increased requirement for flexible generation capacity to maintain the balance between supply and demand. To ensure its availability as reserve, many of these flexible generators will have minimum output limits. A combination of these factors (intermittent and inflexible generation plus high levels of reserve generation) will result in significant periods of power surplus; when low demand coincides with high wind output causing power prices to drop to near zero. At high penetrations of intermittent generation this may occur during a significant proportion of the year and could represent a sizeable amount of total output. Increasing electricity demand (beyond just peak shifting) during these periods not only creates a market for the surplus (low-carbon) power and prevents spilling / constraining-off of renewable plant, but also facilitates cost-effective switching of energy services away from other (more polluting) energy vectors (eg gas).

    —  Geographical diversity. As deployment of renewables increases we will see greater geographical diversity that could mitigate some of the effects of intermittency; for example there is likely to be a high level of on-shore wind in Scotland combined with off-shore wind installations further south.

    —  A greater degree of inter-connection. The larger an electricity system, the greater the scope for fluctuations in the total supply-demand balance to smooth themselves out. A greater degree of interconnection with the Continental mainland and with Ireland may therefore help to address the challenge. New interconnectors to the Netherlands and to France are already in the development process.

    —  Energy storage: BERR has supported the development of flow battery technology through the Technology Programme and its predecessors, ie Regenesys and more recently with Plurion. Success has been limited so far but the technology does seem promising, largely because it is scaleable to utility size (tens of megawatt hours) and its energy storage can be separated from its power output, unlike a conventional battery.

  Understanding the impact and efficiency of these measures under various future development scenarios will require further work. However it will be difficult to make an appropriate selection of the above technology solutions a priori, given the uncertainties in a number of key driving parameters (cost of alternative measures, dynamic and cost characteristics of the future generation mix, level and responsiveness of demand etc). It may thus be appropriate to ensure that the market framework is able to facilitate the emergence of the most cost efficient portfolio of solutions.

SEVERN TIDAL POWER

4.   The Committee would appreciate further information on the forthcoming feasibility study into the Severn Barrage project. What issues will this study look into?

  Tidal range technologies—barrages and lagoons—have the potential to make a significant contribution to our energy needs. They work by making use of the height difference between high and low tides to generate electricity by creating a differential in the water levels either side of the structure and then passing this water through turbines. The Severn Estuary has the second highest tidal range in the world at roughly 14 metres on a spring-tide.

  The feasibility study (which was announced in September 2007) aims to enable the Government to decide whether, and if so, on what terms it could support a tidal range power project or scheme in the Severn Estuary.

  The terms of reference were published in January 2008 and are attached at Annex 1. The study will cover all tidal range technologies, including barrages and lagoons. It will assess in broad terms, engaging stakeholders and the wider public, the costs, benefits and impact of a project or projects, including environmental, social, regional, economic and energy market impacts.

  It will run for roughly two years and will be a two stage process with a decision point at the end of each. A high level work plan for the feasibility study is attached at Annex 2. The first stage work, likely to run until late 2008, will focus on high level issues and reach a first view on whether there are any fundamental issues that mean the project can not proceed. Subject to the decision at the end of the first phase, the second phase will look at the issues in more detail and culminate in a full public consultation in early 2010.

  The study will include a Strategic Environmental Assessment (SEA) to ensure a detailed understanding of the Estuary's resource; there will be a consultation on the scope of the SEA in the autumn following the first phase decision on whether to proceed.

  A Parliamentary Forum has been set up, chaired by the Secretary of State for Business, Enterprise and Regulatory Reform, John Hutton, to provide all interested MPs, members of the House of Lords, Welsh Assembly Members and MEPs the opportunity to engage with the study. This forum first met on 20 February and meetings will take place on a quarterly basis. Details of the next forum will be placed in the libraries of the House of Commons and the House of Lords once a date has been arranged.

  Further information about the study (including regular updates) will be available from www.berr.gov.uk/energy/severntidalpower

5.   What is the estimated impact of the Severn Barrage project on the UK's renewables target?

  Estimates from previous work suggest the Cardiff-Weston scheme would have a generation capacity of some 8640 MW and an annual electricity output of 17 TWh/y or some 5% of UK annual electricity demand and would take five to seven years to construct once planning consent had been granted. The Sustainable Development Commission report Turning the Tide, published on 1 October 2007, estimates that the Russell Lagoon concept could capture around 6.5TWh of energy a year from lagoons totalling 2,835 MW. However, it is difficult to estimate how much energy lagoons can produce as there are differences of opinion on whether they are able to achieve a higher load factor as a result of ebb-flood generation, rather than ebb-only generation and as there are no existing examples of tidal lagoons. We will be gathering further evidence on both barrages and lagoons as part of the feasibility study.

  A Severn Tidal Power scheme would be a way of helping meet the renewable energy target and the Severn Tidal Power feasibility study is being considered in the context of both the development of the UK Renewable Energy Strategy and the UK's wider climate change and energy objectives.

  Article 5(2) of the proposed European Directive on the promotion of the use of energy from renewable sources is helpful for the UK as it gives partial credit to very large renewable projects with long lead times and significant risks. The Government supports this measure as we see one role of the 2020 renewables target as being to encourage large innovative projects as part of a long-term move to a low carbon economy. Whether large projects are in operation by 2020, or a little later, is secondary to our long-term goal. We expect the Commission to take into account how near to 2020 the actual generation takes place, or is expected to do so, when assessing the amount of credit that partially built projects receive.

SUPPORT SCHEMES

6.   The Committee would be grateful if BERR could suggest two or three Member States' support schemes that it would be useful to study

  The 27 EU Member States all operate different national support schemes for the promotion of renewable energy using a wide range of market based instruments. The differences reflect Member States' individual approaches to both renewables and their electricity markets in general.

  For interesting case studies of Member States' support schemes, we suggest it would be useful for the Committee to study the different systems in place in Spain, Italy and France. These are all large Member States but provide differing schemes and levels of support for renewable energy and have had varying degrees of success in facilitating growth in the renewable sector. They also represent examples of a feed-in tariff regime (Spain and France), a green certificate scheme (Italy) and a tendering approach (France). The German approach to feed-in tariffs has also been much studied recently.

  Issues which the Committee may want to consider in looking at the alternative support schemes might include: how network costs are treated by the various schemes and how the schemes work within a competitive electricity market.

  There is more information available on EU Member States' support schemes in the Commission's working document, The support of electricity from renewable energy sources published alongside the 23 January draft renewables directive. This can be found at:

  http://ec.europa.eu/energy/climate_actions/doc/2008_res_working_document_en.pdf

Annex 1

SEVERN TIDAL POWER FEASIBILITY STUDY—TERMS OF REFERENCE

  Building on the work of the Sustainable Development Commission and earlier studies, the feasibility study will:

    —  assess in broad terms the costs, benefits and impact of a project to generate power from the tidal range of the Severn Estuary, including environmental, social, regional, economic, and energy market impacts;

    —  identify a single preferred tidal range project (which may be a single technology/location or a combination of these) from the number of options that have been proposed;

    —  consider what measures the Government could put in place to bring forward a project that fulfils regulatory requirements, and the steps that are necessary to achieve this; and

    —  decide, in the context of the Government's energy and climate change goals and the alternative options for achieving these, and after public consultation, whether the Government could support a tidal power project in the Severn Estuary and on what terms.

  The work will be carried out by a cross-Whitehall team led from the Department for Business, Enterprise and Regulatory Reform, including representatives of the Welsh Assembly Government and the South West Regional Development Agency, taking external advice as necessary and engaging stakeholders and the wider public. The study is expected to last roughly two years.

  The study will look at the range of options for power generation from the Severn Estuary tidal range, including barrages, lagoons and other technologies. It will include a Strategic Environmental Assessment of plans for generating electricity from the Severn Estuary tidal range to ensure a detailed understanding of its environmental resource, recognising the nature conservation significance of the Estuary.

  The feasibility study team will report to the Secretary of State for Business, Enterprise and Regulatory Reform supported by ministers from DCLG, Defra, DfT, Treasury, Wales Office, the Welsh Assembly Government and the Minister for the South West.

  If the outcome of the feasibility study is a decision to proceed, extensive and detailed further work would be needed to plan and implement a tidal power project, and secure the regulatory consents that would be required.

ANNEX 2-SEVERN TIDAL POWER F EASIBILITY STUDY – INDICATIVE HIGH LEVEL WORKPLAN





 
previous page contents

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008