Memorandum by the Energy Policy Group,
Department of Geography, University of Exeter
INTRODUCTION AND
CONTEXT
It is with great pleasure that we submit our
written evidence to the Inquiry. We have answered a number of
questions below which were set out in the Inquiry Call for Evidence.
However, there are a number of other points which we would also
like to highlight.
The EU 20% renewable energy target relates to
energy consumption in 2020. Because of this and the wide range
of projections for energy use at that time, it is difficult to
be exact about what amount of renewable energy will be required
to meet the UK's 15% target. In very general terms, BERR's Updated
Energy Projections estimate 2020 demand at 137 mtoe. This excludes
international aviation. If the demand reduction targets of the
EU Directive are included, the 137mtoe falls to around 110 mtoe.
The 15% renewable energy target would therefore be around 15 mtoe.
There are two key points:
if energy demand falls, the required
renewable energy component will also fall. In this way, instituting
successful demand reduction and renewable energy policies is vital,
are firmly linked and are of equal importance as energy supply
policies; and
the UK has delivered around 1.5 mtoe
(according to Eurostats set out in Table 1) between 1994 and 2005.
Germany has delivered about 10 mtoe in that time. The UK therefore
has to do ten times as well as it has done over the last ten years
and even better than the Germans.
FUNDAMENTAL REQUIREMENTS
TO ACHIEVE
THE 15% TARGET
The UK's record of delivering renewable energy
is very poor. Eurostat figures in Table 1 and Figure 1 highlights
the UK against the best performers in Europe (Germany and Spain).
It could be argued that this is an unfair comparison since the
UK is ranked 8th in the world (and 5th in Europe) in terms of
adding new wind capacity in 2006,[1]
although it doesn't make it into the top 10 for any other technologies.
However, it clearly is a dismal record in terms of absolute amounts
of renewable energy, coming 12th in Europe according to Energy
Trends in terms of consumption of renewable energy; and 26th out
of 28 countries in terms of percentage share of final energy consumption
from renewable sources.
This poor record occurs despite the UK having
a wonderful set of renewable energy resources. This is a direct
result of the UK's renewable energy policy, which in turn is part
of the UK's innovation policy. We are convinced that more renewable
energy can be delivered more quickly, and with additional benefits,
if the renewable energy policy in the UK is changed.
This renewable energy policy requirements are
taken to comprise four areas:
a new direct support policy (ie a
move from the renewables obligation to a feed-in tariff combined
with other mechanisms such as capital grants);
changes to the rules and incentives
within the economic regulatory arena to improve grid access for
renewable energy and to implement a strategic plan for infrastructure
development;
making the planning process more
streamlined and efficient; and
implementing a supply side strategy,
to include an effort to improve our manufacturing ability of renewable
energy.
The key to successful renewable energy delivery
is to "make it easy", thereby attracting as wide a number
of investors (of any size) as possible. "Making it easy"
requires unravelling the inter-linking hurdles and constraints
at play in the UK for renewable energy deployment while at the
same time doing this quickly enough to make a difference to meeting
the challenges of climate change.
There are disagreements about why renewable
energy deployment is so poor in the UK. However, it is clear that
policy; planning; infrastructure and access; and skills development
all have to change, improve and work together. No one area is
to be blamed and no one area can overcome all the difficulties.
However, some policies reduce the difficulties of the other areas.
It is in this way that the UK has been so poor. Despite evidence
since 1990 of what policies have been successful in terms of deployment
(or not), the UK has so far (including the recent 2007 EWP) only
taken limited steps to try and incorporate those factors.
THE RENEWABLES
OBLIGATION
We were asked in our oral evidence session to
clarify why it is that the RO has been as unsuccessful as it has
been. This section is therefore rather longer than the other sections.
We argue for a sensitive change from the renewable obligation
to a feed-in tariff as the main mechanism of support for renewable
energy which is sold or re-enters a grid in the UK.[2]
We argue that a move to a feed-in mechanism will reduce difficulties
in the three other key areas set out (planning; infrastructure
and supply side). These areas still need to be worked on and these
issues are discussed in the various answers to Inquiry questions
below.
It is our view that the RO is a poor mechanism
which is unfit for purpose. This has been written widely about
elsewhere[3]
but in brief this is because:
it is an inflexible mechanism which
places all the risk of development on developers; it cannot be
used as the basis for obtaining finance, which minimises new entrants;
and
it benefits the incumbent suppliers
by placing them in a powerful market and political position as
the executors of UK renewable energy policy.
The RO is inflexible because of the incentives
created by the RO rules, but in particular relating to the recycling
payment. The obligation is placed on energy suppliers. They can
meet their obligation either by buying renewable electricity directly
from a renewable energy generator; by buying a renewable obligation
certificate from someone else; or by "buying out" out
of their obligation. The "buy out" payments go into
a fund which is re-distributed to the energy suppliers in proportion
to the percentage that each energy supplier has met the annual
obligation. So if an energy supplier has met 5% of the annual
obligation, they will receive 5% of the buy-out fund. The energy
suppliers effectively count this payment as part of the payment
they expect to receive for their investment in renewables. This
incentivises companies to keep a close track of new renewable
energy deployment in order to know what percentage of the annual
RO will be met; what the recycle payment will be; and hence what
the ROC value will be in future. Any change to any rule or incentive
within the RO alters the percentage of the RO which will be met;
in turn this alters the ROC value as well as the revenues of all
parties involved. This establishes a preference for no change,
which is far greater than the normal business preference for certainty.
The RO is a risky mechanism because, unlike
any other of the 40 or so obligations that exist in the world,[4]
the only requirement of the RO is the obligation on suppliers
to purchase a certain percentage of their previous years total
energy supply to their customers. There is no requirement on the
suppliers to buy the renewable electricity at a minimum price
or to provide a minimum contract length and so on. Suppliers tend
to buy from their subsidiaries; or from large competitors. Suppliers
are in a position of market power with respect to new entrants
or small companies. Not only is the RO contract unsuitable for
raising finance but it has the knock on effect that there have
been very few new entrants entering into the renewable energy
industry in the UK. It is exclusive in its mode of operation:
and it is hard to become part of it. The suppliers are in a very
strong political position with respect to the Government, since
they are the primary executors of not only the renewable energy
policy, but also other sustainable energy policies, such as the
Energy Eficiency Commitment (EEC) and now Carbon Emission Reduction
Target (CERT). The companies are able to develop renewables at
the pace which suits their wider energy portfolio.
However, for those companies which are involved
in the RO, it is an acceptable mechanism. The renewable energy
projects tend to be developed by corporate finance on the basis
of corporate assets. The suppliers are able to work out in a reasonably
risk free manner what profit they will receive after having bought
and sold their electricity; and new entrantspotential competitorsfind
it hard to enter. The energy suppliers are able to "buy out"
if they wish, hence their ability to deliver the renewable energy
at their preferred pace at no extra cost to themselves. It is
customers who finally picks up the bill.
It is not an innovatory mechanism because, in
general, it is new entrants that can be expected to provide innovation.
Large energy companies are providing energy to very large numbers
of customers. In a perfect world, those large companies will not
only provide their millions of customers with secure energy but
incorporate new technologies which improve the efficiency of their
supply and de-carbonise the energy system while at the same time
increasingly connecting individuals to their energy use, thereby
encouraging those individuals to be more responsible about their
sustainability footprints. Not only would these energy providers
incorporate those technologies but they would do so quickly, in
tune with the planetary needs of the environment.
However, in general, innovation or change tends
to occur through niches or by new, nimble, usually small, companies.
Those companies may develop into large companies or, as is often
the way, the large companies in that field buy them out and roll
out the new innovation. This is the more "typical" way
for large companies to innovate. However, because the RO does
not encourage new entrants, this type of innovation is blocked,
or at the very least undermined (and this can be argued for energy
efficiency and energy network as well). This is extremely serious
at a time when we, as the UK, needs to rapidly change our energy
system to meet the challenges of climate change.
The RO is complex, and it is getting more complex
as it incorporates banding. So far, the RO has not supported diversitywhether
of technologies, size of plants, types of investors, new entrants
to the energy industry; or use of geographical resource. Banding
has been introduced to overcome this accepted fault. Banding is
when the generation from different technologies is assigned a
different ROC value. In theory, if the value of the different
ROCs is set at the right level, it will incentivise the suppliers
to buy electricity from a greater diversity of renewable energy
technologies. Even if this works, and that is not certain, the
other problems of the RO being an exclusive mechanism remain.
The RO is also expensive to administrate. Moreover,
while the UK spends considerably less in total than countries
like Germany on renewable energy[5],
the RO pays more per kWh of wind electricity than the German equivalent,
the feed-in tariff.
The Government has to make it easy to invest in
renewable energy
The EU target is a huge challenge. If there
is any hope of getting anywhere near meeting it, the Government
has to make it easy for all investors to become involvedin
other words, it has to reduce the risk for investors by taking
that risk themselves. The renewable energy policy has to become
inclusive, as opposed to the exclusive nature of the RO;
it has to be straightforward to be involved with; and it has to
by-pass areas which enable delay to creep in. We argued it has
to do this in 4 key areas:
1. Policy. We support a move to
feed-in tariff, in conjunction with capital grants for micro-generation.
Evidence shows that its inclusivity attracts investors from all
walks of society; all sizes of developments; all technologies
and all geographical resources.
2. Infrastructure Access. A feed-in
tariff by-passes the access difficulties related to grid and infrastructure,
enabling the economic regulatory arena to continue to work through
the access issues. Arguably, this will lead to a quicker delivery
of a network suitable for a sustainable energy future. Both Denmark
and Germany are now discussing system change to a sustainable
future because so much renewable energy has been deployed. We,
in the UK, are still talking about to regulate our electricity
system in the most efficient way for this sustainable future,
without having moved forward in any meaningful way to the wider
energy system.
3. Planning. A feed-in mechanism
helps with obtaining planning permission because:
there is more local involvement by
investors;
it involves more people and more
companies it creates a tier of mentors for renewable energy. These
mentors are a powerful support for renewables and begin to be
able to counteract the inbuilt momentum of the conventional energy
system;
it enables more diversification and
therefore a wider geographical resource is used, thereby minimising
pressure on the better resource sites; and
it broadens the incentive to go to
the best resource sites. The incentive is still to go to the best
resource sites since the payment is per kWh and the best resource
sites maximise those kWhs. However, if a developer does not go
to the best resource site, they still know they will receive a
payment, whereas they may not be able to obtain a contract within
the RO if their costs are too high.
4. Skills. Finally, diversifying
renewable energy deployment will promote more jobs and skills
both in, and across, the UK, thereby reducing the supply side
problems. The extent to which we maximise those jobs and skills
will depend on the extent to which we develop a domestic market.
Denmark, while having an almost complete decline in their domestic
market since 2000, are still successful in the global market on
the back of their domestic successes in the 1980's and 1990's.
Germany and China are increasingly dominant in the global market
because of the great strides with their domestic markets in the
1990's and 2000's.
There are also three other areas which the Government
has to be mindful of if it is to be easy to invest in renewable
energy:
Establishing a long-term, low-risk
strategic plan to deliver a sustainable economy, of which energy
is just one part.
Make sure that their policies enable,
rather than constrain or channel, all developing technologies
necessary for the sustainable economy.
Be mindful of the big, long term
picture when assessing the costs of moving to a sustainable energy
economy.
A strategic approach: renewable energy has to
be linked in with grid and infrastructure needs, planning, waste
resource policy, food policy and wider sustainable development
criteria
Long-life equipment such as infrastructure clearly
requires a strategic approach. However, the broad move to a sustainable
future has to be part of a much more integrated and strategic
approach. The UK had a White Paper in May 2007, which hardly mentioned
the EU Directive which it had signed up to in the previous March.
The UK then had a Nuclear White Paper in January 2008, and then
immediately (at the end of the month) announced a Consultation
on the Renewable Obligation, including the place of renewable
heat. A Renewable Energy Strategy Consultation is expected at
the end of June 2008. However, there are now suggestions that
there will be a Consultation on Energy Efficiency and Heat in
the Autumn of 2008, with the output of both being published in
2009. None of this gives any confidence that a long term strategic
energy policy capable of meeting the challenges of climate change
is evolving.
The importance of enabling rather than channelling
or constraining technology development
The transition to a sustainable future is made
more difficult by a combination of inter-locking constraints which
arise from such issues as regulation not keeping up with technical
developments; technological immaturity; not understanding why
individuals consume and behave as they do; poor economics of certain
renewable energy technologies; and so on. As the UK attempts to
remove those constraints, it may be easier for some technologies
to develop rather than other ones. For example, the RO was put
in place to enable renewable energy technologies to develop but
it has effectively enabled onshore wind technology. This is an
example of a policy enabling and channelling a technology while
constraining others. Any future policy must enable all technologies.
It therefore has to be an inclusive mechanism which does not pick
winners but enables them, as much as any other technology and
leaves it up to investors to choose which they prefer to invest
in. Feed-in tariffs, in practise, allow more choice because only
those investors who wish to be involved have to be.
The cost of moving to a sustainable energy future
There have been a great many estimates of the
costs of the renewable energy policy. We would argue that the
central points to keep in mind is the planetary environmental
imperative of moving to a sustainable energy future, and the cost
of not doing so. This was thoroughly set out in the Stern Review.
The Review argued that the cost of not taking action was about
five times greater now, and for every future year and possibly
as much as 20 times higher. Moreover, Sir Nicholas Stern recently
gave a lecture at the University of Exeter where he said that
he thought that the Review was, if anything, conservative about
the costs of inaction.
INQUIRY INTO THE EU'S 20% RENEWABLE ENERGY
TARGET
GENERAL
1. How achievable are both the EU's general
20% and the UK's national 15% renewable energies target? Will
other EU energy policies facilitate the EU achieving its target?
This is a very challenging target. The UK (meaning
the mechanisms in England and Wales, Scotland and Northern Ireland)
has been trying to promote renewables since 1990. In that time,
the UK has added slightly under 3% of electricity and about 1%
of energy. The UK Energy Research Centre has submitted evidence
to the Inquiry which shows that the UK's 15% target can be translated
roughly into 40% of electricity demand provided by renewables;
as well as 10% of both heat and transport demand being provided
by renewables.
The percentages from electricity, heat and transport
can be argued about but the key point is that the target is challenging
and will need a significant increase in renewable energy support
policies, which are both stragetic and directed in order to make
them more cost effective in terms of speed, and success, of delivery.
These policies will have to reduce risk significantly to attract
investment and bring in new entrants into the industry. As discussed
above, the RO is not capable of this. There is no hope of the
UK meeting it's EU target unless changes its primary mechanism
of support.
Table 1 and Figure 1 at the end of this evidence
uses Eurostat figures to compare UK renewable energy deployment
against Spain and Germany in millions of tonnes of oil equivalent.
As discussed above, the 15% renewable energy target is the equivalent
of at least 15 mtoe by 2020. Germany has added about 10mtoe since
1994. The UK has added about 1.5 mtoe in the last 10 years. Thus,
the UK has to do better than that of Germany in about the same
length of time.
The UK Government should not be looking for
"quick fixes" but should be putting in place a set of
low risk, long term mechanisms which are inclusive (thereby bringing
in as many people or companies as possible as investors or new
entrants), which stimulate innovation within companies and the
energy system, and which change the relationship of individuals
to energy so that they take more personal responsibility. This
has been called positioning themselves as a country on the right
side of the innovation fault-line[6].
The discussion of the how to make the move to
a feed-in tariff as the primary means of supporting renewable
energy has been dealt with above and in Question 8.
2. How important do you believe micro-generation
will be in meeting the targets? What additional measures should
be considered to support small scale technologies such as PV,
small wind and renewable heat?
Micro-generation could be very important for
meeting the UK's renewables target but also in the move to a sustainable
energy system. The Energy Saving Trust study (2005) indicates
that micro generation (including heat and power from fossil micro-generation)
could make a significant contribution in reducing UK CO2 emissions
(up to 7%) and meeting electrical energy requirements (up to 14%)
by 2030. By 2050, micro-generation may provide about 25% of UK
domestic electrical demand, thereby reducing carbon emissions
from the domestic sector by around 30%.
The EST report highlighted that different policy
mechanisms had very different outcomes. The most successful policy
they had found was net-metering (where the value of the electricity
per kWh exported to the grid from the micro-generator was the
same as that paid for each kWh imported to the house). Net metering
is a more complex version of the feed-in tariff discussed below.
The Government's 2006 Microgeneration Strategy[7]
also points out that "microgeneration" has a wider contribution
to make in helping to win the battle for hearts and minds that
is crucial in terms of encouraging people to change their behaviour
and move towards reducing their overall consumption of energy.
They cite a recent Sustainable Development Commission publication
in support of this.
The barriers to micro-generation set out by
the EST and DTI publications are those related to the high cost
of available technologies and the need for support measures to
allow economies of scale to reduce costs, planning consents, technical
standards for grid connection and commercial issues around export
reward, metering and interfacing with the energy markets.
In terms of technical standards, the DTI Microgeneration
Strategy sets out a need to consider extending the principles
set out in Engineering Recommendation G83/1, which applies to
devices with an output of less than 16A/ph, to larger installations,
in order to reduce the cost and complexity of connection.
Commercial issues are related to the modest
output of micro generation technologies and the difficulties of
interfacing with an electricity market designed to accommodate
big players and high-volume supply. The low level of revenue produced
by micro generation make the costs of metering and supplier-involvement
difficult to support. Means need to be found of supporting deployment
or by improving the economics of micro generation.
We support a combination of capital grants and
either net metering (which would recognise the value of producing
energy at the point of demand) or, our preference, a feed-in tariff.
In the short term and at a small scale, net metering may be the
easiest way forward. Ofgem has reviewed the payments made to domestic
generators for the electricity they inject back in the grid. This
has shown a huge diversity.
However, our preference, while more complicated
in terms of administration, is a feed-in tariff for all injected
electricity and capital grants. This is because a feed-in mechanism
enables the cost to be socialised, thereby reducing supplier concerns
that they will be competitively disadvantaged if micro-generation
is particularly successful in their areas. It also allows a more
formal mechanism which is not at the whim of the private companies
and which reduces the risk for investors. Again, encouraging innovation
in this area and the development of new entrants will be central
to the opportunities and skills available to carry it out.
The current micro-generation policy reflects
the glacial pace at which Government policy proceeds. As importantly,
Government policy is in the process of "channelling"
renewable energy development because Government primarily supports
large scale, currently cheaper, technologies via the RO, although
there have been recent moves to make it more accessible to smaller
generators. Arguably, micro-generation has as great potential
as nuclear power. It has the additional value of involving individuals
with their energy and sustainability decisions. Individuals are
responsible for about 42% of carbon emissions which result from
their choices if transport, food and energy consumption. Involving
individuals may be a key tool in enabling the move to a sustainable
energy system. Micro-generation appears to be one step in stimulating
a new connection with energy.
Not only does the UK not support micro-generation
sufficiently but it does so in a stop and start manner, which
further aggravates the difficulties.[8]
In early 2007, the £0.5 million grants from the Low Carbon
Building Programme for March ran out after the first half an hour,
showing the level of demand. BERR has recently extended the end-date
(it was end 2008) to June 2010 or until funds run out, but have
reduced the maximum payment. Those funds sum from various pots
of Government money to around £85 million. The UK needs to
build on this by increasing the amount of grants available, ensuring
they are big enough to be meaningful, and ensuring their continuity.
These grants should be given in combination with a feed-in tariff.
3. Is intermittency likely to be a significant
issue if the EU achieves its renewable energy target? What measures
will need to be taken at an EU and national level to ensure reliability
of supply?
Intermittency will clearly be an issue with
the deployment of technologies such as wind, particularly for
GB, which has limited interconnection with mainland Europe. However,
the costs seen by the electricity customer of providing additional
spare capacity to deal intermittency and ensure that standards
of security are maintained are likely to be relatively modest.
For example, having reviewed available evidence UKERC conclude
that the intermittency and additional reserve costs seen by consumers
of accommodating around 20GW of wind generation in the UK would
be around 0.1 to 0.15p/kW, some 1-2% of retail energy prices.
Although low, these estimates could be considered higher than
may actually occur as other non-intermittant renewable technologies
are likely to make a significant contribution to the achievement
of EU and GB targets.
On a European scale there is an increased opportunity
to take account of geographic diversity to mitigate the impacts
of intermittency and, for example, to use hydro storage capacity
in Scandinavia to smooth variations in supply and demand. However,
this would require adequate interconnection between national systems,
market arrangements that allowed trading close to real-time and
enhanced operational coordination between national electricity
networks.
4. Concerns have been expressed recently
in some quarters about "supply chain" bottlenecks. For
example, the availability of appropriate offshore engineering
facilities. The EU target will increase demand further and could
lead to competition for resources and capabilities. How should
the Government and Commission seek to address these issues?
We highlighted in our introduction to this written
evidence that supply side issues is one of the four areas that
Government has to work on to enable a rapid increase in renewable
energy delivery. We would argue that the Government has the wrong
"direct" policy; is trying to do things on planning,
although not enough; has at least recognised that grid access
is a problem, although again is not doing enough nor is going
down the right path; but seems to be doing very little at all
on the supply side.
Although, there is little hard data around,
from our own experience we can say that the UK used to produce
the majority of things needed in the UK- turbines, cables, switchgear
etc. However, now the UK has to import the majority of inputs
to exploit our huge renewable resources. For example, wind blades
are manufactured in the UK, but the "high-tech" content
of a wind turbine such as generators, gearboxes, convertor-rectifier
units etc, are sourced abroad. The UK is generally restricted
to competing in areas such as steel, construction, offshore expertise
and so on.
At the end of the 1980s and early 1990s, the
UK was competitive in the early stages of wind development, certainly
in no worse a position than Germany. The Non Fossil Fuel Obligation
(NFFO), the UK's first renewable energy mechanism, allowed other
countries, such as Germany to overtake us.[9]
In the case of electrical equipment, most manufacturers had a
hard time in the 1990s, but the effects of the economic regulation
of our energy industry as a result of privatisation in the UK
were very undermining of our domestic industry. The overseas manufacturers
who survived those years, ie ABB, Seimens, Areva, are now doing
very well because investment in infrastructure is now strong but
it is not primarily UK companies which are benefiting.
We would support a policy intended to increase
UK's capability within renewable energy technologies. While companies
like Rolls Royce might be "obvious" targets for such
a capability, at root, an important parallel policy is the strength
of the domestic renewable energy market. If that domestic market
is strong, then domestic companies are more likely to succeed.
It is no surprise that the UK has fared so badly in terms of supply
issues given both its poor deployment record and the competitive
basis of the NFFO[10]
and RO.
GRID ACCESS
5. To what extent does grid access remain
a significant barrier to increased consumption of renewable energies
in the UK and across the EU? How can access be improved?
Grid access clearly presents a significant barrier
to increasing output from renewable sources in the UK, as evidenced
the connection dates out to 2020 being offered in congested parts
of the system (ie Scotland). We have been asked to answer a number
of inter-related questions: grid access arrangements; locational
pricing; and reinforcement planning. These are addressed in the
following three answers but are all related to the need for a
strategic policy for renewable energywhether in terms of
direct policy (such as feed-in tariff); planning rules; strategic
market and infrastructure development; and supply issues.
We also highlight that in our view network and
market development have to occur along two parallel and connected
lines. Firstly, we support a feed-in tariff and this is described
in more detail below. However, this works by ensuirng connection
and priority access to the grid and, in the short-term, avoids
to some degree the difficulties for renewables within our economic
regulatory framework. However, in parallel that economic regulatory
framework has to evolve to be complementary to renewable energy
generation (and heat). Our answers reflect these two parallel
concerns.
Article 7 of the existing EU Directive on Renewable
Energy does allow priority to be given to renewable generation
in gaining access to the grid. It is notable that member states,
such as Germany, which give priority to the connection of renewable
projects, have connected much higher levels of renewable generation
than has the UK. It is also noted that the draft EU Renewable
Directive proposes that priority access should be mandatory, rather
than optional.
Article 14.2 says "Without prejudice to
the maintenance of the reliability and safety of the grid, Member
States shall ensure that transmission system operators and distribution
system operators in their territory guarantee transmission and
distribution of electricity produced from renewable energy sources.
They shall also provide for priority access to the grid system
of electricity produced from renewable energy sources. When dispatching
electricity generating installations, transmission system operators
shall give priority to generating installations using renewable
energy sources insofar as the security of the national electricity
system permits".
In parallel, access to the grid could be improved
by moving away from current access arrangements, where access
is permitted only when any necessary grid reinforcements have
been completed, to an arrangement whereby any renewable generation
project could connect prior to reinforcements being in place,
with the cost of any consequent constraint cost being either socialised
or targeted on the connecting generators.
All the proposals that are currently being considered
in terms of access reform, ie connect & manage, trading access
rights, auctions, would allow earlier access to some extent. These
possibilities within the regulation of access to networks are
generically known as "early access". Early access to
the grid should be affordableie attractive to developershowever
their costs could be very high to renewable energy developers.
It is likely that the non-locational element of Transmission Network
Use of System (TNUoS) charges will be paid by those obtaining
early access plus any local TNUoS (to cover the cost of local
connections). In addition, it is likely that some or all of the
resulting operational costs will be targeted on generation connecting
early, unless that generation is able to purchase access rights
from incumbents. In either case this is likely to be expensive.
Operational costs as calculated by the British Electricity Trading
and Transmission Arrangements (Betta) are arguably higher than
necessary and this will be reflected in the value of purchased
rights. This could all add up to early connection being a very
costly option, which might deter renewable investment.
It should be noted that connecting generation
ahead of reinforcements being completed will have no impact on
security of the energy system, it will just mean National Grid
having to constrain plant more often. However, if the constrained
plant is conventional, then that is what we are trying to achieve.
If, on the other hand, allowing more renewables to connect just
results in other renewables being constrained, then there is not
much point.
6. Is there a tension between the aim of
encouraging renewable energy generation and locational pricing?
In GB, locational pricing principles are applied
to charging for use of the transmission system. This results in
high charges for renewable generation connecting in Scotland (circa
£20/kW) but lower or even negative charges for renewable
generation connecting elsewhere. The fact that there is currently
a queue of some 12GW of renewable generation wanting to connect
in Scotland suggests that locational pricing can be accommodated
within the economics of most renewable projects. However, it may
well be a significant issue for projects sited on the Scottish
islands, due to the particular costs of reinforcing or establishing
connections to those islands. We understand that the Government
is considering whether a scheme to adjust transmission charges
in those areas should be made under section 185 of the 2004 Energy
Act.
It should also be remembered that locational
use of transmission pricing helps many renewable projects in E&W
and that the principle should ensure that those projects that
have the best economics overall, are progressed first.
7. What impact do the various systems of
reinforcement planning and work have on encouraging renewable
generation? Should the UK adopt a "connect and manage"
approach?
The GB electricity energy market assumes a "commercially
infinite" transmission system, in other words energy is traded
without any regard to the physical capability of the system. To
be able to trade in the energy market however, a generator must
have transmission access rights (TEC), which are only awarded
once reinforcement has taken place and the transmission system
is compliant with industry planning standards (the Security and
Quality of Supply Standards or SQSS). The operational costs that
arise from the need to reconcile the generation schedule delivered
by the energy market with the finite capability of the transmission
system in real time are "socialised" and ultimately
borne by electricity customers.
Due to the time required to gain consents for,
and construct, transmission infrastructure, the current arrangements
can lead to lengthy delays in connecting new generation project,
as evidenced by the connection queue in Scotland. One idea put
forward is to have a "connect & manage" approach
to access which would allow earlier connection of renewable and
other generation projects and would give clearer signals to the
GB System Operator (SO) and Transmission Operators (TOs) in terms
of the need for transmission investment. However, it would give
rise to the higher operational costs referred to above, as generation
would have the opportunity to connect before transmission reinforcement
was completed. Ofgem and others argue that continuing to "socialise"
these costs would amount to a cross-subsidy and that there is
a case for targeting all or some of the incremental operational
costs on the generation that gives rise to those costs.
There is also the issue of whether a "connect
& manage" approach should apply to all generation, or
just renewablesrecognising the particular replacement role
that renewable generation has with fossil fuels. Applying "connect
& manage" to renewables alone goes some way towards a
feed-in tariff but not completely. The basic feed-in tariff design
discussed below has three parts to it: the grid operator guarantees
to take all the electricity (ie the electricity has priority access)
for a pre-determined length of time (usually between 10-20 years
depending on country); the grid operator pays a certain pre-determined
price for the renewable electricity (which is then sociaised across
all customers with the exception of major users who are exempted);
and there are clear rules for connection. In this way, the investor/generator
knows that their electricity will be bought at a certain price;
that they can sell their output; and that there are clear rules
for immediate connection.
"Connect and manage" would give priority
in terms of connection access to the grid, but the project would
still have to trade energy in the market and might be exposed
to the high short run costs of access entry. In this sense, connect
and manage is a very poor relation of a feed-in tariff.
In terms of reinforcement planning there is
also the issue of whether National Grid's current arrangements
adequately reflect the characteristics and role of emerging generating
technologies. The replacement role of renewable generation and
the variable nature of energy produced by renewable technologies
such as wind, tidal etc, suggest that these technologies should
"share" transmission capacity with conventional generating
technologies. This issue has been recognised by National Grid
who are conducting a review of their security standards in relation
to intermittent generation. However, there is concern that National
Grid will conclude that their existing arrangements are essentially
appropriate and will not introduce necessary changes. The implications
of not adequately recognising that different generating technologies
place different demands on the transmission system and the need
to share transmission capacity, will lead to unnecessary transmission
being developed and unnecessary cost and delay in connecting renewable
generation.
There is a need for a more strategic approach
to delivering infrastructure. The Government has attempted this
to some degree with the White Paper Planning for a Sustainable
Future.[11]
It includes a section on Nationally Significant Energy Infrastructure.
However, its legislative base is the Electricity Act. As such,
it only deals with renewable energy projects over 50MW.
Despite this, electricity infrastructure developments
can take time to deliver, ie around 12 years for the 2nd Yorkshire
transmission line and the continuing delays over the BeaulyDenny
transmission line in Scotland. Ofgem believe that customer commitment
should be obtained before expenditure is allowed to avoid the
risk of stranded assets which would be picked up by end users.
This is a problem for wind (particularly small) developers who
are unable to commit meaningful sums to development until they
have consents (including planning) and financial closure. However,
when faced with the timescales associated with delivering major
electrical infrastructure, wind developers can not seek planning
consents as these consents, once granted, are for a limited period.
This is a catch 22 situation and could result in infrastructure
not being available in time to meet our 2020 targets.
An alternate approach would be allow National
Grid to commit expenditure on new infrastructure on the basis
of renewable resource in a particular area, local targets or expressions
of interest. Take mid-Wales as an example. Renewable targets have
been announced via TAN8 but, because individual developers do
not know whether they will be successful in terms of planning
permission, they can not commit to the infrastructure, so the
infrastructure may not get built and the renewable projects are
delayed.
There have been discussions about a strategic
approach to infrastructure development but there has been no obvious
movement forward. This is despite other infrastructure projects,
such as road and airports, being built on the basis of estimated
demand.
SUPPORT SCHEMES
8. Can the existing Renewables Obligation
deliver the level of expansion of renewable electricity that the
target for the UK implies? Should the UK consider other mechanisms,
such as Feed in Tariffs?
No, the RO will not deliver the level of expansion
required by the EU. Yes, the UK should transfer, sensitively and
over time, to a Feed-in Tariff. This was discussed earlier on.
It should be used in conjunction with various other research,
development and demonstration mechanisms, including capital grants
for micro-generation.
The basic feed-in tariff design has three parts
to it: the grid operator guarantees to take all the electricity
(ie the electricity has priority access) for a pre-determined
length of time (usually between 10-20 years depending on country);
the grid operator pays a certain pre-determined price for the
renewable electricity (which is then socialised across all customers
with the exception of major users who are exempted); and there
are clear rules for connection. In this way, the investor/generator
knows that their electricity will be bought at a certain price;
that they can sell their output; and that there are clear rules
for immediate connection.
It is the coherence of the feed-in which makes
the whole thing "easy" which is why its so successful
and attracts in such a broad amount of investmentwhether
from large companies or small, domestic investors.
However, a feed-in tariff is only as good as
its coherence. If any of the three parts are not included in a
renewable energy policy, then it will undermine if not destroy
its success. Moreover, if the feed-in payment is too low it will
not stimulated the required investment. Thus, a feed-in tariff
is, in our view, the appropriate tool for increasing the rate
of deployment of renewable energy. However, the details of that
feed-in tariff are also very important.
9. Should the EU be involved in harmonising
or regulating support schemes offered by Member States to encourage
renewable energy generation?
No, the EU should not attempt to harmonise support
mechanisms. However, it should concentrate on:
ensuring that each member state deploys
a certain amount of renewable energy; and
ensuring that there are minimum payments
for renewable energy and that priority access, in the sense it
is intended within the various EU Directives, is in place.
| | 1994
| 1995 | 1996
| 1997 | 1998
| 1999 | 2000
| 2001 | 2002
| 2003 | 2004
| 2005 |
| Solar
| | | |
| | | |
| | | |
|
| Germany | 36
| 41 | 57
| 70 | 83
| 78 | 96
| 150 | 184
| 241 | 269
| 365 |
| Spain | 24
| 25 | 26
| 23 | 26
| 29 | 33
| 38 | 43
| 48 | 66
| 68 |
| United Kingdom | 6
| 6 | 6
| 6 | 7
| 7 | 11
| 13 | 16
| 20 | 25
| 30 |
| Biomass and wastes
| | | |
| | | |
| | | |
|
| Germany | 4,427
| 4,447 | 4,619
| 5,880 | 6,362
| 6,384 | 6,830
| 7,300 | 7,929
| 8,719 | 9,564
| 12,186 |
| Spain | 3,545
| 3,563 | 3,608
| 3,660 | 3,806
| 3,894 | 4,049
| 4,149 | 4,328
| 4,736 | 5,055
| 5,129 |
| United Kingdom | 1,396
| 1,494 | 1,553
| 1,652 | 1,763
| 1,897 | 2,069
| 2,070 | 2,247
| 2,462 | 2,538
| 2,691 |
| Geothermal |
| | |
| | | |
| | | |
|
| Germany | 9
| 9 | 10
| 10 | 10
| 10 | 10
| 124 | 128
| 132 | 134
| 138 |
| Spain | 7
| 3 | 3
| 4 | 4
| 5 | 8
| 8 | 8
| 8 | 8
| 8 |
| United Kingdom | 1
| 1 | 1
| 1 | 1
| 1 | 1
| 1 | 1
| 1 | 1
| 1 |
| Hydro |
| | | |
| | | |
| | | |
| Germany | 1,714
| 1,873 | 1,888
| 1,492 | 1,480
| 1,689 | 1,869
| 1,955 | 1,988
| 1,656 | 1,812
| 1,684 |
| Spain | 2,408
| 1,987 | 3,393
| 2,989 | 2,924
| 1,966 | 2,534
| 3,527 | 1,981
| 3,530 | 2,713
| 1,681 |
| United Kingdom | 438
| 416 | 289
| 355 | 450
| 461 | 437
| 349 | 412
| 277 | 424
| 427 |
| Wind |
| | | |
| | | |
| | | |
| Germany | 123
| 147 | 179
| 261 | 395
| 475 | 804
| 899 | 1,363
| 1,622 | 2,193
| 2,341 |
| Spain | 15
| 23 | 29
| 62 | 116
| 236 | 406
| 599 | 748
| 1,038 | 1,341
| 1,825 |
| United Kingdom | 30
| 34 | 42
| 57 | 75
| 73 | 81
| 83 | 108
| 110 | 166
| 250 |
| Total renewables production
| 1994 | 1995
| 1996 | 1997
| 1998 | 1999
| 2000 | 2001
| 2002 | 2003
| 2004 | 2005
|
| Germany | 6,309
| 6,517 | 6,753
| 7,713 | 8,330
| 8,636 | 9,609
| 10,428 | 11,592
| 12,370 | 13,972
| 16,714 |
| Spain | 5,999
| 5,601 | 7,059
| 6,738 | 6,876
| 6,130 | 7,030
| 8,321 | 7,108
| 9,360 | 9,183
| 8,711 |
| United Kingdom | 1,871
| 1,951 | 1,891
| 2,071 | 2,296
| 2,439 | 2,599
| 2,516 | 2,784
| 2,870 | 3,154
| 3,399 |
| Final energy consumption
| 1994 | 1995
| 1996 | 1997
| 1998 | 1999
| 2000 | 2001
| 2002 | 2003
| 2004 | 2005
|
| Germany | 217,285
| 222,374 | 231,214
| 225,641 | 224,004
| 219,564 | 218,177
| 224,059 | 219,228
| 222,749 | 221,826 (p)
| 217,925 (p) |
| Spain | 62,279
| 63,536 | 65,259
| 679,86 | 716,83
| 74,271 | 79,422 (p)
| 83,286 (p) | 85,405 (p)
| 90,437 (p) | 94,311 (p)
| 97,169 (p) |
| United Kingdom | 142,334
| 142,429 | 149,925
| 147,427 | 148,431
| 151,022 | 151,665
| 152,949 | 148,371
| 150,422 | 151,979
| 151,580 |
Figure 1

15 June 2008
1
http://www.ren21.net/pdf/RE2007_Global_Status_Report.pdf Back
2
Others renewables, for example renewable energy from solar
water heaters should be supported through capital grants and other
regulated mechanisms. By sensitive we mean that a feed-in has
to be implemented alongside the RO, which has to remain in place
long enough for those currently involved not to feel economically
threatened. Back
3
C Mitchell, 2007, The Political Economy of Sustainable Energy,
Palgrave, UK. C Mitchell, D Bauknecht, et al. (2006). "Quota's
versus Subsidies-Risk Reduction, Efficiency and Effectiveness-A
Comparison of the Renewable Obligation and the German Feed-In
Law". Energy Policy 34 (3): 297-305. C Mitchell
and P Connor (2004). "Renewable Energy Policy in the UK 1990-2003".
Energy Policy 32 (17): 1935-1947. Back
4
http://www.ren21.net/pdf/RE2007_Global_Status_Report.pdf Back
5
See www.ren21.net Back
6
C Mitchell, 2007, The Political Economy of Sustainable Energy,
palgrave, UK. Back
7
DTI, 2006, Our Energy Challenge Power from the People, DTI Microgeneration
Strategy, p8. Back
8
See Low Carbon Building Programme, BERR; or Brenda Boarman, 2007,
Home Truths, Chapter 6, pages 58-69. Back
9
C Mitchell, 2000, The Non-Fossil Fuel Obligation and its Future,
Annual Review of Energy and Environment, Vol 25, pages
285-312; C Mitchell, 1995, The Renewable NFFO-A Review, Energy
Policy, Vol 23, No 12, pages 1077-1091. Back
10
For Information, the May 2007 Energy White Paper said in para
5.3.20, page 148 that the NFFO was a feed-in scheme, This is totally
incorrect. Please see papers referenced above. Back
11
DCLOG, 2007. Back
|