Select Committee on European Union Minutes of Evidence


Memorandum by National Grid

INTRODUCTION

  1.  National Grid plc owns and operates the high voltage electricity transmission system in England and Wales, and as Great Britain System Operator (GBSO), we operate the Scottish high voltage transmission system. National Grid also owns and operates the gas transmission system throughout Great Britain and through our low pressure gas distribution business; we distribute gas in the heart of England, to approximately 11 million offices, schools and homes. In addition National Grid owns and operates significant electricity and gas assets in the US, operating in the states of New England and the state of New York.

  2.  In the UK, our primary duties under the Electricity and Gas Acts are to develop and maintain efficient networks and also facilitate competition in the generation and supply of electricity and the supply of gas. Our activities include the residual balancing in close to real time of the electricity and gas markets.

  3.  Through our subsidiaries, National Grid also owns and maintains around 18 million domestic and commercial meters, the electricity Interconnector between England and France, and a Liquid Natural Gas importation terminal at the Isle of Grain.

  4.  National Grid is pleased to have the opportunity to contribute to this inquiry. Our submission will deal with:

    —  the ability of changes to the transmission access regime to increase the amount of renewables in the Great Britain fuel mix;

    —  the need for planning reform to speed up delivery of energy infrastructure; and

    —  issues with the current regulatory regime.

BACKGROUND

  5.  The European Commission has outlined in its package of measures to deliver a reduction in carbon emissions of 20% and a 20% share of final energy consumption from renewable sources by 2020. This target breaks down by Member State and by sector. UK power generation is likely to have a target of around 40% of electricity produced from renewables.

  6.  Great Britain's current electricity generation mix is heavily reliant on carbon based fuel. Coal and gas currently provide over 70% of the primary fuel source for electricity generation, with nuclear providing around 20%. Electricity generation from renewables sources is currently around 2%.


  7.  Over the next 12 years to 2020, much of this generation infrastructure will reach the end of its engineering and economic life and will require replacement. The impact of the Large Combustion Plant Directive will see much of the heavy carbon based plant come off the system, while the case for replacement of the current nuclear fleet has been made elsewhere; it is worth reiterating that by 2020, even with life extensions, much of the current nuclear plant will need to be replaced by new generation plant.

CURRENT PROGRESS AND EXISTING OBSTACLES TO THE INCREASED USE OF RENEWABLE ENERGY SOURCES FOR THE GENERATION OF ELECTRICITY

  8.  The current installed electricity generation capacity in Great Britain is around 77GW, with peak demand between 55GW and 60GW. Since the privatisation of the electricity industry in the early 1990's over 22GW of new electricity generation has connected to the high voltage transmission system. This is a significant churn and compares especially well with other countries.

  9.  Since the introduction of the British Electricity Transmission and Trading Arrangements (BETTA) in 2005, unprecedented numbers of applications to connect to the system have been processed. National Grid, as Great Britain System Operator has made around 170 offers to connect to the transmission system, with connection dates to 2015 and beyond. Throughout Great Britain, we are currently managing 47GW of signed connection contracts for new generation. 16GW of this is for renewable energy projects—7GW of which is in England and Wales and 9GW is in Scotland.

  10.  Planning consent is the most significant blocker to the timely connection of these projects and the development of network capacity to accommodate the transfers around the system. Of contracted wind projects in Scotland only 16% has consents and only 23% across Great Britain. We fully support reform of the planning regime and in particular the proposals that the Government have come forwards with which will allow more certainty in shorter timescales in the delivery of essential transmission infrastructure to deliver power from point of production to end use.

TRANSMISSION ACCESS REVIEW11.  Changing the arrangements for access to the transmission system is a key element of the work National Grid is undertaking to increase the amounts of renewable electricity in Great Britain. We are playing a pivotal role in driving this forward with BERR and Ofgem within an industry wide discussion on reform of the current transmission access arrangements. There are currently three proposals; "Connect and Manage" (whereby the user pays for additional system management costs) "Connect and Socialise" (whereby the costs of connecting are spread across all industry participants) or an auction of existing rights. Two of the most significant issues are: Who pays the cost of the connection, and; who owns the property rights in the existing capacity? This is an issue that all of the industry as well as National Grid and Ofgem need to consider and so consideration through the appropriate governance arrangements is essential. We have put forward modifications to the industry code and these modifications proceed according to plan changes to the access system could be delivered by the end of 2008.

REGULATORY REGIME

  12.  The change in fuel mix to accommodate 40% of renewables by 2020 will mean a locational and geographic shift in where electricity is generated and where it needs to be transported from. The network in areas where renewables, especially wind, are most abundant either does not exist, such as offshore, or has only been built to serve small amounts of demand, such as in the Highlands and Islands of Scotland. This will require significant investment in the transmission system to both connect locally and to upgrade the wider system to accommodate larger flows.

  13.  One of the major issues that National Grid is concerned with is whether the current regulatory regime will facilitate the scale of investment in the timescale required. The regulatory regime currently requires firm financial commitments from users who trigger infrastructure investment before National Grid can effectively start construction work. This regime has served Great Britain's energy markets well since privatisation where there has been relatively little need to increase transmission capacity on a large sale basis, and an incremental approach has been fit for purpose.

  14.  This transmission investment still needs to be carried out in the most economically efficient way to ensure consumers are protected, given that other factors within the market are increasing the wholesale energy prices are rising. However, given the scale of the challenge and the short time that the industry has to deliver solutions, new approaches need to be harnessed. One example could be "no regrets investment", whereby the regulator and network companies consider what network developments are likely to be required ahead of definite and confirmed customer needs to upgrade and reinforce the network. Such an approach is rare but not without precedent. National Grid is in active discussions with Ofgem around different regulatory models to ensure that the required investment is made in order to help deliver renewables and ensure security of supply is maintained. One key issue to be worked through is the effect any changes may have on the risk and reward profile under new regulatory models and how this impacts upon the wider market and upon consumers.

OFFSHORE TRANSMISSION REGIME

  15.  Due to limited space and planning considerations onshore, the bulk of the renewables needed to meet the EU target will need to be accommodated offshore. It is, therefore, critical that the Government get the offshore regime right. Ofgem and BERR have proposed a competitive tender approach to appoint Offshore Transmission Owners, ie the companies that will make investments and build transmission infrastructure to connect offshore windfarms, in order to deliver a regulated solution that introduces competitive benefits to end consumers. This will encourage single radial links for windfarms, rather than co-ordinated offshore networks to develop. While at the time this decision was made this was an appropriate solution and fit for purpose, clearly the picture has changed significantly since then, most significantly with the EU targets for c.40% renewable generation by 2020 and BERR's announcement of their aspiration for around 30GW of offshore renewables to be in place by 2020.

  16.  However, National Grid does not believe that the proposed regulatory regime for offshore transmission can deliver the UK Government's aspirations. The proposed regime is overly complex with many areas of the regulatory arrangements still uncertain and undecided. Further, we do not share the Ofgem/BERR view on the consumer benefits in terms of cost reductions that this regime will produce. In National Grid's view, the deployment of simple, co-ordinated, regulated transmission build is a more effective approach to help meet the significant challenge which is ahead of us in the next 12 years. The quickest, simplest and most effective option is to extend the current regulated onshore transmission franchises offshore, but other options are available.

  17.  That said, National Grid has a key role to play as Great Britain System Operator and has a significant responsibility in delivering any offshore transmission regime, as well as many other key programmes which will be critical to the delivery of renewables. We are absolutely committed to supporting the Government and BERR in the delivery of any regime that they choose.

23 April 2008



 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008