Select Committee on European Union Minutes of Evidence


Memorandum by Ofgem

INTRODUCTION

  1.  Ofgem is the regulator of the gas and electricity industries in Britain. Protecting consumers is our first priority. We do this by promoting competition, wherever appropriate, and regulating the monopoly companies which run the gas and electricity networks. Other priorities and influences include:

    —  helping to secure Britain's energy supplies by promoting competitive gas and electricity markets—and regulating them so that there is adequate investment in the networks;

    —  contributing to the drive to curb climate change and other work aimed at sustainable development by, for example:

    —  helping gas and electricity industries to achieve environmental improvements as efficiently as possible; and

    —  taking account of the needs of vulnerable customers, particularly older people, those with disabilities and those on low incomes.

SUMMARY

  2.  The target is achievable but very challenging both for the UK and for the EU. It is likely to require unprecedented levels of investment and technical innovation in a relatively short space of time. This will be required in all areas of the supply chain: the generation market, the transmission and distribution networks and the retail market.

  3.  The electricity transmission networks—the wires which carry electricity from generators to customers—do not have enough capacity or appropriate access rules to meet the target. New lines need to built in order to help connect more renewables, and better use needs to be made of existing lines. Ofgem is playing its part by allowing a 100% increase in investment in the energy networks and by reviewing the arrangements for allowing generators to gain access to the networks.

  4.  The biggest single obstacle faced by renewable generators and transmission owners will remain planning provisions—particularly for major electricity infrastructure. It is estimated that there are currently 8 gigawatts (GW) of renewable generation capacity delayed within the onshore planning system. Whilst we recognise that the UK Government's Planning Bill aims to improve the planning process for major infrastructure projects, this legislation would apply only to England and Wales, where planning delays are less acute at the moment.

  5.  Meeting the target will not be cheap. It is vital that the policy instruments designed to meet it also protect customers from facing excessive or inefficient costs. This is particularly important given the context of rapidly rising energy prices and increasing fuel poverty. The experience of other EU Member States provides evidence on the cost-effectiveness of different policies. However, their relative performance will be influenced by other factors too, such as the lack of planning constraints and the availability of spare transmission capacity.

Question 1—How achievable are both the EU's general 20% and the UK's national 15% renewable energy targets?

  6.  The target is achievable but very challenging both for the UK and for the EU. It is likely to require unprecedented levels of investment and technical innovation in a relatively short space of time. This will be required in all areas of the supply chain: the generation market, the transmission and distribution networks and the retail market as it responds to the pricing signals likely to emerge from an electricity network with high penetration of intermittent generation.[2]

  7.  We think it is vital that the policy instruments designed to meet the target also protect customers from facing excessive or inefficient costs. This is particularly important given the level of investment required and the context of rapidly rising energy prices and increasing fuel poverty. Lessons can be learned from the existing support mechanism for renewable energy—the Renewables Obligation (RO). The RO was designed to sit alongside the competitive wholesale market and allow subsidies to fall away as technologies became competitive. The proportion of Britain's energy coming from renewables has increased since the RO was introduced but by far less than is required to meet the target and there are questions about its cost effectiveness. The Government is now considering what form the RO should take in the future. Given the risks and uncertainties in meeting the very challenging EU target, any new policy instrument needs to be robust to any future obstacles. There could be continued problems with planning if Government's reforms take time to implement or are unsuccessful. In addition, for the next few years there may be bottlenecks in the renewable manufacturing supply chain (for example for wind turbines) as EU and global demand surges and manufacturers seek to increase their manufacturing capacity.

  8.  It is important to note that the 15% target relates to energy. Much of Britain's energy use is in transport, where the scope for renewable energy is more limited, and in the use of natural gas in businesses and domestic homes. This means that the proportion of electricity that must be generated from renewable sources in order to meet the UK's target is likely to be much higher than 15%. Many estimates put it in the region of 35 to 40%. To see what this means in practice, a renewable electricity target of 38% would equate to an electrical output of around 135 terawatt hours (TWh) compared to a total GB output of around 355TWh. Assuming a generous load factor of 35% for renewable generators,[3] this would require renewable generation capacity at around 44 gigawatts (GW), equivalent to 56% of existing installed generating capacity in Britain (78GW). To achieve this target in the next 12 years is immensely challenging, given the number of potential barriers to increases in renewable electricity capacity. These include:

    —  obtaining planning consents (for generation sites and for grid connections/upgrades);

    —  obtaining access to the electricity transmission grid;

    —  constraints in the supply chain for generation (eg wind turbines) and connections (especially offshore);

    —  sourcing finance from investors and debt suppliers;

    —  cost-effective support mechanisms; and

    —  achieving the best balance between the heat and electricity sectors.

  9.  Some of these barriers are outside Ofgem's statutory responsibilities and powers. For example, Ofgem does not have responsibility in respect of planning decisions. It is estimated that there are currently 8GW of renewable generation capacity delayed within the onshore planning system. A further 3.2GW is currently awaiting consent offshore.

  10.  Ofgem has an important role to play in helping to meet the target through the way we regulate the monopoly transmission and distribution networks which carry electricity from generators to customers. We set price controls for all of the network companies every five years and these create the financial incentives on network companies to invest to expand capacity on their networks to connect new generation. We also have the power to approve or reject any changes to the way they charge for use of their networks and any changes to the commercial rules that govern how generators connect to and access the networks through various industry codes. In addition, we can hear and settle any disputes between a network company and a generator over the terms of their connection to the network.

Question 2—How coherent are these proposals in the context of the EU's energy policies in general and the Third Energy Package in particular?

  11.  The European Commission emphasised in its Strategic Energy Review in January 2007 that its clear policy direction is to work towards sustainable energy markets. The Commission listed a number of options aimed at achieving sustainable, competitive and secure energy supplies in the EU. The "Green Package" and the "Third Energy Package" provide the legislative basis for delivering this vision. The two packages must be seen together and are very important, significant and welcome initiatives by the Commission. The Third Package initiatives are a vital step in delivering a fully liberalised EU energy market. The Green Package sets out a clear and significant commitment to promoting renewable technologies, reducing carbon emissions and increasing energy efficiency measures in the EU. Taken together, these initiatives, when agreed, will allow for a paradigm shift in the EU energy market which should include a buoyant market in renewables.Where there are specific overlaps between the two initiatives it is important that they be consistent with each other and with the overall policy objective of securing sustainable and competitive energy markets.

Question 3—To what extent are these targets capable of improving the EU's security of energy supplies?

  12.  An increase in the amount of energy from renewable sources could increase the overall generation capacity available, as well as delivering a more diverse energy mix and lowering reliance on imported fossil fuels. This could improve security of supply.

  13.  However, there are potential risks to security of supply. Wind is an intermittent resource and there is limited experience of the operational challenges of running an integrated transmission system reliably and within existing quality standards with such a high proportion of intermittent generation. The scale of the 2020 target and the limited time available to meet it could also reduce security of supply. Ambitious renewables targets, especially if supported by attractive financial incentives, could divert investment away from other generation technologies. In addition, the short space of time may require the use of similar technologies or the same manufacturing design for a significant proportion of our generation fleet. This reduces diversity and increases the risks associated with "type faults" being discovered with a particular turbine design. There are also risks associated with some technologies that are not yet fully tested in operational conditions such as offshore wind.

  14.  Nevertheless, an overall reduction in security of supply could still be justifiable given the carbon savings and other benefits associated with action to tackle climate change.

Question 4—How effective has the existing legislation (2001/77/EC) been in encouraging grid access for renewable energy generators?

  15.  The Internal Market in Electricity Directive requires that grid operators do not discriminate in the terms they offer for connection and access to their networks. If properly implemented, this should create a level playing field and prevent, for example, grid operators owned by vertically integrated companies[4] stopping new entrant renewable generators being denied access to the system on reasonable terms.

  16.  The Renewables Directive allows renewable generators to be given priority access to electricity grids ahead of other forms of generation but it does not require Member States do so. This is a matter for each Member State.

Question 5—To what extent does grid access remain a significant barrier to increased consumption of renewable energies? Is it consistently a problem across all Member States?

The Transmission Access Review

  17.  Ofgem is undertaking jointly with the Government a review of the charging and commercial arrangements to gain access to the transmission network and we will publish our final report in May.

  18.  We originally called for reform in 2000 and primary legislation was introduced by the Government to enable changes to be made. However, the industry argued at the time that reform was unnecessary as the transmission system was unlikely to be constrained for the foreseeable future. Since then, a large queue has emerged of generators waiting to connect to the transmission system or to receive an offer to connect.

  19.  Ofgem and BERR hope that the necessary reforms can be designed and implemented under the existing industry code governance framework, even though previous attempts to implement reforms have been very slow and piecemeal. National Grid has announced that it will raise a suite of proposed modifications to the current arrangements based around three distinct models of reform. The proposals will be analysed by the industry before coming to Ofgem for decision. The Government has made clear that it will consider primary legislation if the industry does not improve its performance and bring forward appropriate reforms quickly.

Why transmission access needs to be reformed

  20.  The current arrangements for access to the transmission network were designed for fossil fuel and nuclear generation with relatively high load factors. They do not allow low load factor plant such as wind to share existing capacity with conventional generators. Nor do they provide the transmission companies with enough information about the plans of new and existing generators in order to build infrastructure and allocate capacity in a certain and timely manner. Major reforms of the existing arrangements are therefore necessary to allow significant volumes of new renewable and other low carbon generation to connect to the system.

  21.  Requests for connections to the transmission network are dealt with on a "first come, first served" basis. This means that generators who have finance and planning permission may be further down the queue than generators who do not have either in place but who may have approached National Grid first. Transmission companies therefore lack certainty over new users' plans to proceed to connection, as well as existing generators' intentions to continue to use the transmission system for a defined period. Without user commitment it is difficult to present a robust case as to why the transmission licensees should risk building large infrastructure substantially ahead of need. If the transmission licensees predict the need for a new line incorrectly, investment could be wasted and the costs would have to be paid by consumers. We are also concerned at the level of asset stranding risk that customers could face.

  22.  Conversely, appropriate user commitment would allow the transmission licensees to proceed and build projects several years in advance of need so that the major reinforcements could be delivered to coincide with generators' wishes to connect. In the case of existing generators, if a more appropriate level of user commitment was provided, the transmission licensees would have better information on when a particular generator would exit the system, and when its capacity would be available for others to use. This is a prime example of how existing infrastructure could be used more efficiently.

  23.  The connection of renewable generators represents an additional challenge. Transmission companies have traditionally adopted an approach of "invest then connect" when dealing with new generation connection requests. They will not allow a generator to connect until they have invested to increase capacity in the transmission system. This work can take several years. Generators are only able to connect quickly to the transmission system if they choose to connect in an area of the system that has spare capacity. However, renewable generators only have intermittent output and low load factors and when connected will displace existing fossil fuelled generation. This is because Britain has very limited export capacity and electricity demand is not very sensitive to changes in price, so the extra electricity is unlikely to be absorbed by additional demand in Britain or on the continent. Transmission companies could therefore take a different approach and connect renewable generators without investing to increase overall network capacity substantially. Renewable generators and fossil fuelled generators would then share capacity on the system.

  24.  However, this may not work in all locations. For example, it may not be possible where the transmission system is already constrained and there is not enough capacity to allow existing generators to export their power to other parts of the system, such as in Scotland. If two generators wish to dispatch their electricity to the same part on the network at the same time, one must be paid a premium for not being able to do so (ie it is constrained off). If no generators wish to dispatch their electricity, but National Grid estimates that more power is needed in order to balance supply and demand, it can force a generator to dispatch in return for being paid a premium (ie it is constrained on). Simply connecting more generation will add to the existing costs of constraints on the system and raise customers' bills.

  25.  As part of the Transmission Access Review, BERR and Ofgem will be assessing what the potential benefits (primarily a reduction in carbon dioxide emissions) and costs (higher constraint costs for electricity customers) if we moved from the existing approach to a "connect and manage" approach where the transmission company simply allowed all renewable generation to connect on request and then managed any resulting transmission constraints.

  26.  Regardless of the improvements that are made to the transmission access regime, the single largest difficulty faced by renewable generators and transmission owners will remain planning provisions—particularly for major electricity infrastructure. This can be illustrated by the case of the upgrade to the Beauly-Denny line. This project was referred to a public inquiry by the relevant planning authorities and has already undergone a two year consultation process, prior to a further period after which Scottish Ministers will take their decision on whether to allow planning permission for the line. Whilst we recognise that the UK Government's Planning Bill aims to improve the planning process for major infrastructure projects, this legislation would apply only to England and Wales, where planning delays are less acute.

Funding to renew the energy networks

  27.  Ofgem has played its part in providing the necessary funding for the transmission companies to invest to increase capacity to connect new renewable and other low carbon generation. In recent price reviews Ofgem has allowed an unprecedented 100% increase in investment in the energy networks to upgrade the existing pipes and wires and connect new generation, much of it from renewable sources. The Transmission Price Control Review for 2007-12 allows the electricity transmission companies to invest £3.8 billion to maintain and upgrade their networks. The funding is flexible and transmission companies' funding will increase automatically if more generation seeks connection than was assumed when the price control was set.

  28.  Prior to that, in 2004 Ofgem approved £560 million of additional investment in transmission capacity outside the normal price control process to avoid delay in the upgrade work necessary to connect renewables. The main project affected was the upgrade to the line running from Beauly, west of Inverness, to Denny, west of Falkirk: a key part of transmission network in Scotland where much proposed renewable generation is located. This allowance has not been used because of major difficulties in gaining planning permission. In 2006 the Scottish Executive referred the project to a public inquiry.

  29.  There is the potential for more investment as more generation comes forward. For example, we are facilitating more "localised energy" (smaller-scale distributed energy and household-scale microgeneration) which we are addressing through our work on the next Distribution Price Control Review for the period 2010-15.

A new offshore electricity transmission regime

  30.  Offshore, there is the potential for over 30GW of renewable offshore wind generation to connect to the system, potentially operating at a load factor higher than 35%. Together with BERR we have been developing and implementing a new regulatory regime for offshore transmission to make sure this generation can access the onshore market. Offshore transmission has different technical characteristics and it costs much more to build lines offshore than onshore. BERR and Ofgem have therefore decided to base the arrangements around competitive tenders for major offshore transmission projects. Ofgem will organise tenders and appoint the most competitive bid to build, own and maintain the offshore transmission lines. Subject to the Energy Bill becoming law, the first tenders are likely to commence in the first quarter of next year.

  31.  The challenge lies in rebuilding the transmission system to accommodate this major change in the location and nature of flows across the transmission system. Funding of onshore reinforcement works should not present difficulties since Ofgem can allow the expenditure provided it is efficiently incurred. However, the sheer magnitude of the task will place an immense burden on the planning system.

  32.  Our discussions with other energy regulators through the Council for European Energy Regulators suggest that grid access and planning constraints for new transmission lines are also significant issues in many other Member States.

Question 6—How does Use of System charging affect grid access for renewable energy generators? How far can the different levels of renewable energies take-up in different Member States be attributed to Use of System charging and cost sharing rules?

  33.  In line with the European Commission's position on promotion of markets in energy, the GB mechanism for use of system charging is designed to reflect the costs of locating at different points on the network. Under this approach, if a generator is located far from a centre of demand, or connects in a part of the system where generation already exceeds demand in that location, it will pay a higher transmission charge, reflecting the cost of the transmission lines necessary to move power from where it is produced to where it used. This promotes competition between generators (for example between renewable and other low carbon forms of generation) and helps them to make economically efficient decisions. For example, it enables offshore wind farms to trade off the costs of onshore and offshore transmission when deciding where to connect to the onshore system. As more renewable generation comes onto the system, displacing existing fossil fuel plant, it encourages generators to examine the costs and impact on the transmission system when considering which fossil fuel power stations to close. Finally, it promotes a more sustainable energy system as the transmission system has its own environmental impact through its visual amenity and carbon footprint.

  34.  There is no evidence that locational charging in the UK has yet proved a barrier to renewable deployment—even in Scotland where the locational charges are highest. There is currently a total of over 13GW of renewable generation that is connected or is seeking to connect to the transmission system in Scotland at today's charges. Wind farm developers in the remotest and most expensive parts of Scotland (including the Scottish Islands) have indicated to Ofgem that the subsidy provided by the Renewable Obligation is sufficient to make projects financially viable at current wholesale prices and transmission charges.

  35.  It is difficult to determine whether the increased penetration of renewable generation in other Member States can be attributed to different use of system arrangements. The degree of penetration is more likely to be affected by the financial support mechanism in place; the ease of obtaining planning consent for renewable technologies such as wind; geographical factor such as the availability of hydro resources; whether there is spare capacity on the transmission system; whether planning is a problem for major expansions of the transmission network; and whether renewables are given priority access to the grid. Ofgem has not seen any studies or evidence to suggest that different transmission charges in different Member States are a major factor in explaining why some Member States have a much higher renewable energy penetration than others.

Question 7—What impact do the various systems of reinforcement planning and work have on encouraging renewable generation? How important is the issue of constraint in increasing Member States' renewable generation?

  36.  The main challenges faced by developers as a consequence of the way in which reinforcements are planned and delivered fall into two main areas:

    —  a mismatch in timing. It often takes longer to get planning consent for the necessary grid reinforcements than it does for the renewable generation itself; and

    —  a lack of certainty about which generators will connect to and stay connected to the grid.

  37.  Ultimately both issues can be resolved by new and existing generators providing an appropriate level of user commitment to use the transmission system. Our Transmission Access Review sets out this analysis and considers the issue of constraints. More information can be found in our answer to Question 5.

Question 8—To what extent is further co-ordination of National Regulatory Authorities needed to encourage grid access for renewable energy generators?

  38.  The EU Third Energy Package of internal market measures currently under negotiation is designed to provide reinforced coordination between national energy regulators. The measures include the establishment of an Agency of EU regulators to help facilitate the development of the internal market, especially on cross border issues and other areas most critical for market entry.

  39.  Whilst there are significant legal and political difficulties in agreeing the powers and responsibilities of the Agency, once agreed, these improvements in regulatory coordination would not be specific to any one type of energy generation and will help address the current "regulatory gap" on cross border issues. To the extent that a specific renewable grid access situation is a cross border issue, it will benefit from this enhanced regulatory coordination. There are other elements of the third package where an element of enhanced regulatory coordination is envisaged and which should encourage new entrants and connections. Amongst others, these include: addressing problems in market concentration and vertical foreclosure; better coordination of investment in capacity; overseeing development of compatible network operation codes; improving access to interconnectors; and improving transparency of information.

Question 9—How far do current regulations inhibit access to the grid?

  40.  The existing transmission licence regime broadly ensures that all generators who apply for a connection are given an "offer" setting out, amongst other things, the costs and terms associated with connecting in their particular location. In this sense there are no direct barriers to applying for a transmission connection. There are, however, issues relating to the queue of generators wishing to connect which need to be addressed. This is discussed in further detail in our answer to Question 5.

Question 10—At what level should the EU be involved in harmonising or regulating support schemes offered by Member States to encourage renewable energy generation?

  41.  A variety of support mechanisms for renewables are in operation across Member States. Whilst harmonisation would be desirable, we think that a higher priority at this stage is to make real progress in integrating the EU's energy markets. Harmonisation at this stage could be onerous and expensive because of the variety of schemes and the variety of market conditions in which they operate.

Question 11—What impact have the various schemes in operation across the Member States had on encouraging renewable energy? How have these schemes affected take-up both by producers and commercial and domestic consumers?

  42.  There are four main types of support schemes for renewable energy currently used in various Member States. These include feed-in tariffs; obligations or quotas; tenders; and tax incentives or rebates. A feed-in tariff is an additional premium (fixed or variable) paid on top of the electricity market price that renewable energy producers receive. An obligation or quota system normally involves a finite set of renewable energy generation certificates being generated and traded, with penalties in place for not possessing them, when it is mandatory to do so. Tenders involve inviting companies to bid for the right to get involved in renewable energy investments. Finally, tax incentives or rebates provide tax advantages for those choosing to generate renewable energy.

  43.  These schemes have had varying levels of success in encouraging renewables and at very different costs to customers and costs per tonne of CO2 emissions avoided. A recent evaluation of their relative effectiveness concluded that feed-in tariffs were generally more effective at encouraging larger volumes of renewable generation at generally lower costs than the other options.[5] However, these studies are very context specific and a policy that is ineffective and/or expensive in one Member State may be more effective and cheaper in another Member State if, for example, there are fewer planning constraints and more spare transmission capacity.

  44.  The mandatory nature of obligations means that is the costs are largely passed through to business and domestic customers. This has been the case in Britain, where the Renewables Obligation currently adds around £10 to a domestic electricity bill per year and is set to rise to around £20 a year by 2015. Even so, there remains a significant gap between renewable generation targets under the scheme and actual renewable output in Britain.

Question 12—Will cross-border renewables markets be genuinely affected by the existence of a variety of support schemes? Is necessary investment hampered by lack of market harmonisation?

  45.  In the short term there may be an impact if there are bottlenecks in the renewable manufacturing sector. If a relatively small number of wind turbines are available, these are likely to be deployed in countries with the most attractive support schemes. However, even in the short term, there are a range of other factors which will affect investment decisions in renewables, eg ease of access to grid and planning constraints will be of major significance. Any constraints in the manufacturing base should ease over time as new manufacturing capacity is built and any support scheme that offers commercial rates of return to windfarm developers and does not have other significant barriers (such as delays in obtaining planning permission or access to the grid) will attract significant investment in renewable generation.

Question 13—To what extent would the enhanced use of Guarantees of Origin certificates require the harmonisation of support schemes?

  46.  The trade of Guarantees of Origin certificates (GoOs) between Member States will generally be limited to those countries who have met their interim targets. We do not consider that harmonisation of support schemes is required in order to trade GoOs between Member States. Together with BERR, we are committed to working to ensure that issues arising in negotiations on the Renewables Directive are addressed in an appropriate and timely manner. The Council of European Energy Regulators is also reviewing the use of GoOs.

25 April 2008




2   High wind penetration and current typical demand patterns could lead to more volatile wholesale electricity prices. Demand during night time in summer can fall to 30% of winter daytime peak levels. Prices may even fall to zero at night time when there is more wind generation than demand. Suppliers will therefore have a strong incentive to offer new services and tariffs to encourage customers to spread their demand across the day by, for example, using more time controlled domestic appliances. Back

3   Much of the new renewable energy is likely to come from wind power which, depending on location, can have load factors lower than 35%. Back

4   Vertically integrated companies may have interests in more than one part of the supply chain in energy: generation, transmission and distribution networks, and supply. Back

5   Feed-in Tariffs and Quotas for Renewable Energy in Europe, CESifo DICE Report, 4/2007. Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008