Select Committee on European Union Minutes of Evidence


Supplementary memorandum by Ofgem

  1.  On 28 April 2008 Ofgem's Managing Director of Networks, Steve Smith, gave oral evidence to the Committee as part of its inquiry into the EU Renewable Energy Target. Subsequently the Committee took evidence from other witnesses who, like us, have focused on the challenges facing the energy networks. This supplementary memorandum contains further information that may be useful to the Committee.

  2.  On 26 June we published, jointly with the Government, the conclusions of the Transmission Access Review. This will see major reforms of the grid access rules to make it easier for new generators to connect.1 We hope to see the new regime in place by 2010. In parallel, we will develop and implement a new incentive framework for the transmission companies that will allow them to invest in new capacity ahead of contractual commitments from new renewable generators. This is necessary because the Government has not yet put in place financial support mechanisms to deliver the 2020 targets, and developers may not be able to make financial commitments to the transmission companies. Given the long lead times for new transmission build, this will make sure that the physical capacity of the network keeps up with demand for capacity. However, our framework will also protect customers from paying for inefficient investments in capacity that is not required or is under-utilised. Under the proposals, the returns on transmission companies' investment will be linked to how much generation connects post-construction. Shareholders will, therefore, take on some of the risk of inefficient network investment in return for being able to earn higher returns.

  3.  In addition, we have identified short term measures which can be implemented before these new arrangements are in place to deal with the existing queue of renewable generators waiting to get onto the grid. This may enable up to 1 gigawatt (GW) of renewable generation with planning consents to connect to the grid faster than under the current rules. Furthermore, the wider context of high energy prices and rising fuel poverty means it is particularly important for Ofgem to ensure that consumers, especially the vulnerable, are protected from excessive and inefficient costs as the industry strives to meet the target.

REFORMING ACCESS TO THE GRID

  4.  A vital requirement for meeting the Government's renewable energy target is to change the rules governing access to the electricity transmission network. (See Ofgem's initial memorandum, paras 20-26.) The long overdue reform of the access regime has, however, been blocked in the past by the electricity industry. The Commons Innovation, Universities and Skills Committee recognised this in its recent report on renewables. "[Our] frustration is compounded by the knowledge that Ofgem attempted to pilot transmission access reform in 1999 and 2000 but, under threats of legal action, was unable to proceed." At the time, many in the industry argued that reform was unnecessary. In addition, existing conventional generators have had an incentive to oppose reform as they do not want to share their access rights with, for example, new renewable generators.

  5.  We want a new grid access regime which requires all generators to make a clearer financial commitment of their future demand for capacity—or else give up their access rights to new renewable generators who may be more willing to make such a commitment. This approach has two significant advantages. First, it gives National Grid a lot more information about generators' demand for access to the network, which in turn allows them to invest in new capacity to meet that demand where necessary. Second, it allows for much greater sharing of capacity. For example, much renewable generation is intermittent, and if a wind farm and a conventional power station use the same lines on the network, the conventional generator can start running when the wind is not blowing.

  6.  We are pleased that the industry is now making much more positive comments about access reform and we hope they will follow these with real action to amend the industry rules. As the transmission access review draws to a close, National Grid (NG) has raised a suite of proposed changes to the key industry codes to reform the current arrangements based around three distinct models of reform. The proposals are now being analysed and discussed and NG will present its recommendations to Ofgem in September. We will then carry out an impact assessment on the proposals before reaching our final decision on which model to implement. We aim to have new arrangements in place by April 2010, which will also time for the necessary IT system development, though the timetable may be threatened if any of our decisions are subject to legal challenge. The Government has made clear that it will consider primary legislation if the industry does not improve its performance and bring forward appropriate reforms quickly. Ofgem is doing all in its power to facilitate the reforms.

SHORT TERM MEASURES TO BRIDGE THE GAP

  7.  The signs of progress on transmission access reform are promising. However, the 2020 target is too pressing for us to wait for a new regime to be in place. A lot can be done in the meantime to help bridge the gap. For example, we have encouraged National Grid to move away from a "first come first served" approach to dealing with the queue for grid connections. At present, generators who have finance and planning permission may be further down the queue than generators who do not have either in place but who approached National Grid first. National Grid is now taking a more robust approach to removing unviable or purely speculative projects. National Grid is also progressing an amendment to the industry codes which would make it easier for existing and new generators to share access to the grid.

  8.  We estimate that these shorter term measures are capable of bringing forward 1GW of new renewable connections including just under 600 MW of projects that already have planning consent. We remain open to any other ideas which will accelerate longer term investment in the grid to meet the target.

LONGER TERM MEASURES LOOKING TO 2020

  9.  Even with transmission access reform, there are still significant challenges ahead. For example, the Government has not yet put in place the subsidy mechanisms to deliver the 2020 targets. This means that renewable generators may not be able to signal their future capacity needs to National Grid and sign contracts because of the uncertainty over what financial support they will receive. By the time the subsidy mechanism is clear, there may not be sufficient time to build the capacity early enough to meet the target.

  10.  Ofgem is therefore engaged in several projects to help ensure the grid can be properly configured for the renewables challenge. We have asked the transmission companies to produce an investment study to identify the options to invest to provide the extra transmission capacity that will be required to deliver the 2020 targets. We are also working with the companies and will implement a new investment incentive framework that will allow them to reach decisions on the necessary investments given the long lead times for significant transmission investment. This will make sure, subject to the planning regime, that we have the necessary grid capacity in place in time to meet the 2020 targets. The framework will allow this investment to take place whilst protecting customers from the risk of having to pay for substantial investment in new transmission that is not required. This is clearly important given the context of rising energy bills.

  11.  All this is in addition to Ofgem's existing work through our price controls. For example, we are allowing a 160% increase in investment in the onshore electricity grid, with flexibility for the network operators to go beyond this amount in response to demand for additional capacity. We are also implementing, with the Department for Business, the new offshore electricity transmission regime which will allow the potential of marine renewables to be fully and quickly achieved.

  12.  These contributions should allow a significant expansion in renewables by eliminating undue network barriers.

PROTECTING CONSUMERS

  13.  The measures needed to meet the renewables target will not be cheap. This raises particularly important choices at a time of high energy prices and rising fuel poverty. The companies understandably wish to protect their shareholders from as much risk as possible, and to transfer the risk and potentially more of the costs to the consumer. However, at a time when around 4.5 million households could be in fuel poverty, we believe it is vital that consumers are protected from excessive or inefficient transmission costs.

  14.  That is why, for example, our new incentive package encourages the transmission companies to manage some of the stranding risk that there is not enough demand from generators to use the new capacity once it has been built. In return for taking on more of this risk, the companies will be allowed to invest early and earn higher returns. Measures such as this allow us to be more confident, on customers' behalf, that the investments requested by the transmission companies are genuinely required. At the same time, we want to see more long term commitments from generators to use their capacity rights—or else make way for new renewable generators who are ready and willing to connect.

OFGEM'S DUTIES

  15.  Some witnesses have raised the issue of Ofgem's statutory duties and whether they are appropriate for the challenges ahead. Our primary duty is to protect consumers. Sustainable development features in our secondary duties. The above actions have all been taken under our existing suite of powers and duties.

  16.  It is for Parliament to decide whether these duties are right, or whether they need to change. We can offer some general thoughts that may be helpful as you approach this issue:

    —  We are keen that our duties should be broadly consistent over time. This is because unprecedented investment will be needed in the energy sector over the next few years. This in turn requires a stable regulatory regime that gives investors confidence.

    —  Some proposals for changes to our duties are based on creating twin principal objectives. This approach could involve granting the responsibility to make potentially difficult trade-offs. In this context it is for Parliament to consider the scale of the discretion it wishes to grant an unelected regulator.

    —  Finally, if we are granted additional duties, it is important for policymakers to consider the powers that are needed to fulfil them.

  17.  We would be happy to answer any further questions or provide any additional information that the Committee may find useful.

30 June 2008





 
previous page contents

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008