Select Committee on European Union Minutes of Evidence


Memorandum by the British Wind Energy Association

  1.  The British Wind Energy Association (BWEA) is the leading UK trade association in the field of renewable energy, with over 350 corporate members representing the large majority of the wind energy business in this country. Wind energy is the fastest-growing renewable technology in the UK, and will make an increasingly significant contribution to our electricity supplies over the next decade and beyond. BWEA also represents the interests of the emerging wave and tidal stream energy sector, building on its experience in the development of offshore wind. We therefore welcome the opportunity to submit evidence to the Sub-Committee on the subject of the EU's Renewable Energy Target.

GENERAL QUESTIONS

How achievable are both the EU's general 20% and the UK's national 15% renewable energies target?

  2.  The contribution of renewables to the EU energy sector was 8.5% of overall end use in 2005. Much of this energy was produced by large hydroelectric generators, though there was also a significant contribution from biomass in a number of forms. While there should be some leeway for growth in use of biomass, large hydro is likely to have reached a plateau: apart from a few exceptions at the margin, potential sites are off-limits, primarily for environmental reasons. The growth required for the 20% target to be met in 2020 will have to come from other sources.

  3.  Fortunately, there are a number of technologies that are growing rapidly and will be making very significant contributions in 2020. Sources such as solar, in both thermal and electric forms, geothermal energy, accessed through heat pumps, and biomass and waste technologies are outwith the expertise of BWEA; their proponents will lay out their views on delivery, while we will reserve our comments to the technologies of wind, both on- and offshore, wave and tidal stream. These latter forms will be vital to the UK meeting its share of the target.

  4.  According to figures from the European Wind Energy Association,[1] across the EU, there were 56GW of wind power installed at the end of 2007, 1GW of which was offshore. This capacity generated 119TWh (10mtoe), 3.7% of the Union's electricity demand. Wind was thus generating about one-quarter of the EU's renewable electricity last year. The European Commission has calculated that 34% of the EU's power will have to be renewably-sourced if the 20% target is to be met, given the expected contributions of renewables for heat and transport, so capacity able to provide a further 20% of power demand must be developed in the next 12 years.

  5.  EWEA's projection for 2020 is that 180GW of wind power will be installed in 2020, 35GW of which will be offshore. This capacity will generate 477TWh (41mtoe), equivalent to between 11.6% and 14.3% of EU power, depending on the level of overall demand expected in 2020. Wind will thus be providing about half of the increase in renewable power required. It is reasonable to expect other renewable sources to collectively provide the rest, though BWEA will leave it to others to comment in detail on the feasibility of those contributions.

  6.  In the UK, 41% of our energy is used for heat, 37% for transport and 22% in the form of electricity. We are starting from a very low base of renewable energy use: the current UK share of 2% is mostly in the form of electricity generation, where 5% of our supplies are renewable, while renewable heating and transport fuels only make very small contributions to their sectors. Not only are contributions from biofuels and renewable heating small, the policy agenda to drive their implementation is much less advanced than for power, and so their growth will be slower than is possible in the electricity generation sector. From bases of well under 1% in both cases, the most that can be expected from each is 3-4% of UK energy supplies. Renewable electricity will therefore have to be contributing half of the target, perhaps 7.5%; given that power is only 20% of overall energy, renewable power will have to make up at least 35% of UK electricity supplies in 2020 if we are to meet our target, possibly more.

  7.  Of the available renewable power technologies, wind is the only source that can deliver in the bulk quantities that will ensure the target is met, given the development of the technology and the resource that the UK has—the best in the EU. Other technologies, particularly the marine sources of wave and tidal stream, can make a contribution by 2020, though major growth is likely to be after this date. Were Government to decide that it is desirable to build the Severn Barrage, this could be under construction by 2020, but it is unlikely to be generating.

  8.  Wind is a mature technology onshore and the challenges are primarily about planning and grid availability, though attention will have to be paid to the funding mechanism in order to ensure continuing development through to 2020. Current costs are well-defined for onshore wind, though uncertainty remains as to which drivers of cost will be most prevalent in the future, and thus how the overall cost will develop.

  9.  Offshore wind presents different challenges as the technology will need further development to allow its full contribution to the 2020 target to be realised. This is required to move into the deeper water sites, further offshore, that will be required to reach the maximum contribution. Since the necessary innovations in turbine and foundation technology have not yet been brought forward commercially, the costs to build these developments are unclear. The regulatory regime for the offshore grid is untested as yet, and the reinforcement of the onshore grid necessary to accept the power produced is yet to be planned, let alone procured and built. Efforts are also required to build the industrial capacity in the UK to deliver the volume of equipment required.

  10.  Wave and tidal stream technology is less well developed than even offshore wind, and so presents the most difficulty in forecasting deployment and costs. The UK has a significant opportunity to develop a world-leading industry here, however. The consenting issues for the marine renewables are not dissimilar to offshore wind, and so there are key synergies here that can be exploited.

  11.  In BWEA's view, if the challenges to developing these resources are met, then capacities of 13,000MW, 20,000MW and 1,500MW of onshore wind, offshore wind and marine respectively are entirely possible by 2020. These would contribute approximately 10%, 17% and 1% of UK power in each case. Therefore, nearly 30% out of the over 35% needed to meet the target can be obtained from wind, wave and tidal stream; existing hydro will still be generating then, providing 2-3% of our power, so there will only need to be small contributions from other sources. If the Severn Barrage goes ahead and is counted towards the target, it could be providing a further 5% of the UK's power. Further contributions from wind, wave and tidal stream could be brought forward: for instance, the UK Government has started a process that will see sites for offshore wind awarded that would enable up to 33GW of this source alone to be delivered, though to greatly exceed 20GW will need very strong Government drive, implemented immediately.

How coherent are these proposals in the context of the EU's energy policies in general and the Third Energy Package in particular?

  12.  BWEA believes the renewables proposals are consistent with EU energy policies in general. Most importantly, the increase in contribution from renewables will be vital in meeting the EU's objectives on reducing carbon emissions. The 477TWh of wind power forecast by EWEA for 2020 should mean 328mt of CO2 emissions are avoided, 44% of the amount required to meet the Union's target of reducing emissions by 20%. Development of renewable energy will also reduce the import dependence of the Union, which is a key objective (see below). Wind power in particular has been instrumental in increasing competition in the European power sector, with new players gaining a foothold through development of wind projects. Renewables can also improve the EU's competitive position in line with Lisbon objectives: wind power in particular is an area where Europe shows technological leadership.

  13.  In BWEA's and EWEA's view, the Third Energy Package, and in particular the proposals on ownership unbundling of grids, is entirely complementary to the proposals on renewables: without movement towards the level playing field the Third Package aims to provide, the renewable objectives will be more difficult to reach, while the public policy objectives of requiring more renewable energy on networks can be incentivised without distorting this playing field.

  14.  To what extent are these targets capable of improving the EU's security of energy supplies? The extent to which the EU's security of supply is improved by meeting renewable targets will depend on which sources of energy are displaced. With the emphasis on electricity as described above, the fuels displaced will be mostly coal and gas: the more gas displaced, the more imports are avoided, since a greater proportion of coal is produced within the EU; the more coal displaced, the higher the carbon reduction benefit. In any case, the use of renewables should primarily displace imports, given that these will often be from higher-cost and/or riskier sources. If the increase in renewables from 8.5% to 20% results in 10% of our energy not being imported, that will mean a significant reduction in the EU's energy dependence, which is currently running at 50% and would be 65% in 2030 on current trends.

GRID ACCESS

How effective has the existing legislation (2001/77/EC) been in encouraging grid access for renewable energy generators?

  15.  The existing directive has had mixed results in promoting access to the grid for renewable generators across Europe. While such generators are guaranteed transmission and distribution of their power under the legislation, the weaker provisions on access ("[Member States] may also provide for priority access to the grid system of electricity produced from renewable energy sources"—emphasis added) has allowed EU countries to continue inconsistent systems, leading to patchy promotion of renewable access. In some countries this weakness in the directive has allowed vertically integrated power companies to be obstructive to new renewable generators, where these have been perceived to be a threat to the generation side of their businesses. In general, however, the issue of access is tied up much more with the building of new grid capacity, and the delay that this causes, rather than procedures surrounding grid entry.

  16.  In the absence of a liberalised market across the EU, the UK government must not undermine efforts to promote renewable energies through regulatory incentives relating to grid access (as proposed by the European Commission in Article 14 of the draft directive). Priority access to transmission and distribution grids for electricity from renewable energy sources (as proposed in Article 14) should be interpreted and implemented along the same principles and criteria in the different member states, in consultation with the stakeholders, so as to correct and avoid market distortions. This should be reflected in the relevant harmonised technical and market codes, to be drafted according to the procedure that will be set once the Third Energy Package is agreed.

To what extent does grid access remain a significant barrier to increased consumption of renewable energies? Is it consistently a problem across all Member States?

  17.  On the whole, the issue of access to grids is a lesser problem than the building of new grid capacity to accept renewable generators. What might be tied up with "access" as more of a problem is balancing and stability of networks: directive 2001/77/EC dictates that transmission and distribution for renewables are guaranteed "[w]ithout prejudice to the maintenance of the reliability and safety of the grid". As networks rely on higher proportions of variable renewables like wind power, the effort required to ensure grid stability will increase as a result, and this may be a barrier to full development. As numerous studies have shown, however, this is a manageable issue.[2]

How does Use of System charging affect grid access for renewable energy generators? How far can the different levels of renewable energies take-up in different Member States be attributed to Use of System charging and cost sharing rules?

  18.  Member States have different approaches to charging for use of networks. These range from "shallow" regimes, where generators pay for the connection to the network and other costs are spread across all grid users, through to the situation in the UK where new generators are expected to pay for the full cost of connecting them to the system, as well as locational charges to reflect transmission losses. Clearly the more that charges are loaded towards the renewable generator, the more revenue from power sales will have to be directed to grid costs, and the less the profit for the developer. In general, this is not a problem as long as the support system provides income such that the difference between revenues and costs is large enough, and this is generally the case in the UK: the difficulties in delivery of wind power have not been directly economic in nature. In the north of Scotland, however, the charging regime results in high transmission costs, which are a disincentive; future offshore projects will also be paying high costs for their network service. BWEA supports the principle of cost reflectivity, with generators paying in full for the services they require, but if the income received is not sufficient for them to develop profitably when they are paying these costs, then this situation needs to be examined critically.

What impact do the various systems of reinforcement planning and work have on encouraging renewable generation? How important is the issue of constraint in increasing Member States' renewable generation?

  19.  The issue of expanding grid capacity to accept large quantities of new renewable energy is crucial to the EU and UK meeting their targets. New networks have long planning, procurement and build times, usually well in excess of the project cycle for developers; consequently, grid owners and operators need to think strategically about the reinforcements required to accept these new plant, coping with the uncertainty caused by having to plan for projects that have not yet been brought forward by developers.

  20.  In other European countries, grid companies have been through a process of dealing with the new technology of wind, initially with suspicion and then with acceptance as they have grown familiar its characteristics. In Spain and Ireland particularly, hostile operators (RED and ESB respectively) have moved to be enthusiastic partners in planning new grids; wind developers have accepted the timetables for connection as they have participated in their development. While there are delays in providing the infrastructure, which will be a constraint on delivery of renewables, the issues are being resolved.

  21.  In the UK, however, this has not been replicated, though National Grid is keen to work with new generators to see them connected in a timely manner. The problem here is that Ofgem, as a regulator clearly focused on the cost to the consumer, will not allow new capacity to be planned without connection applications from generators, for fear of stranded assets. Developers are thus placed in a dilemma: either apply early for a connection, before planning consent is gained, with the risk that fees paid for the application are lost if the project fails, or apply after consent is gained, which risks delaying connection by several years. Solutions to this impasse are being discussed, but in general there needs to be more flexibility shown so that National Grid can move ahead with the planning for work on the network which is clearly required if renewable targets are to be reached. This may be facilitated by the National Policy Statement for energy networks that will be produced under the new national planning system currently being legislated on. We do not advocate procurement and installation of infrastructure ahead of firm connection applications, but much desk-based planning and consent work can be done beforehand.

To what extent is further co-ordination of National Regulatory Authorities needed?

  22.  Coordination amongst regulators is required to facilitate further interconnection between Member States: the more systems are interconnected, the more variable renewable generation can be accepted, since the new grid capacity allows exchange of power when the weather provides surpluses in different countries. This is recognised in the European Commission's Trans-European Networks—Electricity (TEN-E) programme and the appointment of a number of "grid coordinators" to promote particular strategic connections, including for offshore wind. Regulators need to work further to ensure that market conditions at either end of the new wires allow free trade of power through them, but this is in hand through the European Regulators' Group for Electricity and Gas (ERGEG).

How far do current regulations inhibit access to the grid?

  23.  Regulatory standards can inhibit grid access, and are a key inhibiting factor to getting renewable generation onto the UK grid. In the UK, the Security and Quality of Supply Standards (SQSS) govern when generators may connect from a technical point of view. These essentially require that grid capacity must be provided to take all of the output of a new generator before it can be allowed to connect. These standards were written based on the requirements of large, dispatchable plant, and do not reflect the needs of variable renewable generators like wind power. The generation pattern of wind, dictated by the weather, means that wind farms do not often need the full capacity of the grid; rather than have developers delay connection until grid companies have provided 100% ability to export the power, BWEA believes that a system whereby generators are allowed to connect within a set time frame, on the understanding that there may be curtailment at certain times due to lack of grid capacity, would be better. We refer to this concept as "connect and manage". The Transmission Access Review that BERR and Ofgem are currently leading is considering this option, and we strongly hope that it is taken up swiftly.

SUPPORT SCHEMES

At what level should the EU be involved in harmonising or regulating support schemes offered by Member States to encourage renewable energy generation?

  24.  Support schemes for renewable energy are, and should remain, the responsibility of Member States, under the principle of subsidiarity. Renewable resources vary between countries, and so it is only right that States decide what is the best way to develop them. The draft renewables directive opens the door to "flexibility" through the trade in renewable Guarantees of Origin (GoOs), and since the targets for each country are partly based on GDP per capita and not renewable potential, this is appropriate. Extreme care needs to be taken, however, so that such trade does not disrupt the national schemes, since the latter will be the primary means of delivering the large increase in renewable energy required.

  25.  The Commission will regulate support schemes through its powers to scrutinise Member States' National Action Plans: if the NAP is judged to be inadequate, including in the area of support schemes, it can be referred back to the Member State. However, the Commission should refrain from attempting to impose a harmonised support scheme across the EU; any such system will inevitably be different in some way from every national scheme in the 27 Member States, and thus introducing a harmonised arrangement will result in uncertainty and disruption, which we cannot afford if the targets are to be met. In any case, it is not sensible to talk about harmonising the system for renewables when the market for electricity generally is not yet harmonised. Until such time as there is a level playing field for trade in power across borders in the EU, then all talk of harmonising support for renewables should be quashed.

  26.  However, BWEA believes that there is leeway for some States to open up borders to free trade in GoOs in so-called "cluster" markets. In this regard, the initiative of Sweden and Norway to set up a common green certificate trade will be an important test. The renewables directive should be drafted in such a way that it allows, but does not mandate, such trading.

What impact have the various schemes in operation across the Member States had on encouraging renewable energy? How have these schemes affected take-up both by producers and commercial and domestic consumers?

  27.  The various support schemes across the Union have been vital in encouraging the new renewable technologies. Policies in the power sector have been most successful, though initiatives on heat and transport are also showing some results.

  28.  The lesson of the UK is that a suitable support scheme will not be successful if the non-economic barriers are not addressed: since the introduction of the Renewables Obligation in 2002, about 15,000MW of onshore wind capacity has been submitted to the planning system in this country—and half is still there; of the successful projects, some are awaiting grid connections. If these two issues had been dealt with effectively earlier, then the RO would be regarded as a very successful system. One of the main benefits of the RO has been the engagement of the mainstream power companies in the renewables sector: arguably, this has led to companies like Eon and RWE changing their opinions of these technologies and thus bringing them into their core international strategies.

  29.  The take-up of distributed renewable generation technologies in the UK under the RO has not matched some other countries, where different support schemes have been in place, notably feed-in tariffs. While BWEA is strongly of the opinion that the RO should be retained for larger generators, in order to retain investor confidence in the UK market, we also believe that a feed-in tariff for smaller generators may be justified. This is due to the failure of the grant-based Low-Carbon Buildings Programme to deliver a thriving microgeneration sector, and the mismatch between a complex system like the RO and the need for a simple mechanism to encourage a multitude of potential small generators to invest.

Will cross-border renewables markets be genuinely affected by the existence of a variety of support schemes? Is necessary investment hampered by lack of market harmonisation?

  30.  As noted above, the prime vehicle for delivering the required renewable energy will be national support schemes; this is particularly true because of the stipulation in the current draft of the directive that countries must meet their interim targets for delivery of renewables before they can export GoOs to other Member States, a position that BWEA fully supports. In the de minimis view of trading, this will be purely an intergovernmental function, with countries that have generated a surplus through a successful national support scheme able to recoup some of the cost through exporting GoOs to countries that have a less successful scheme, less resource, or both. Whether there needs to be cross-border trade by companies is debatable. Given the free movement of capital within the EU, companies can invest wherever they like and receive the return that the relevant support scheme provides. The advantage of cross-border trade would be to allow companies to invest in countries outside of the national support scheme, and this should be encouraged in order to ensure that the 20% target is met at minimum cost. However, as noted above, any move to go beyond intergovernmental trading will need to be done with care to ensure that the national schemes, which are the most important factor, are not disrupted.

To what extent would the enhanced use of Guarantees of Origin certificates require the harmonisation of support schemes?

  31.  It is entirely possible for GoO trade to be undertaken with no harmonisation of support mechanisms, since such trade could operate completely outside of these mechanisms. If Member States move towards the "cluster market" approach referred to above, then there will need to be a quite high degree of harmonisation if there is not to be gaming between the countries' support mechanisms. It is important to note that this harmonisation will have to extend to non-renewable conditions such grid costs: if there is disparity across two countries, with generators having connection costs paid in one but not in the other, then consumers in the former country may be effectively subsidising the latter country in meeting its target if GoOs are cheaper there and thence are exported in volume to the country where generators have to pay in full for their grid service.

23 April 2008




1   Pure Power: Wind Energy Scenarios up to 2030, EWEA, March 2008 Back

2   See, for instance, The Costs and Impacts of Intermittency, UK Energy Research Centre, March 2006. www.ukerc.ac.uk/Downloads/PDF/06/0604Intermittency/0604IntermittencyReport.pdf Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008