Select Committee on European Union Minutes of Evidence


Memorandum by E.ON

SUMMARY

    —  E.ON believes that renewable energy can make a significant contribution to meeting EU and UK energy demand and to climate change targets.

    —  However, the UK's proposed share of the renewable energy target poses major challenges, particularly given the relatively short period between now and 2020 and the limited contribution renewable sources currently makes to UK final energy consumption.

    —  The extent to which it is delivered will depend on whether some major barriers to investment can be overcome and sufficient incentives exist to attract the very large capital investment required not only in renewable capacity but also the fossil plant required to back up intermittent generation from wind and tidal resources.

    —  Even if a renewable share of electricity of some 40% is achievable (which is not yet clear), the implications of this for grid investment and performance are potentially very significant and need to be clearly modelled, explained and understood.

    —  To ensure the most efficient delivery of the target the UK's heat and transport sectors must contribute a level of renewable energy commensurate with their cost effective potential to avoid an excessive burden falling on the power market.

    —  The renewable targets are only credible if the directive gives Member States flexibility in delivering them; in particular trading in renewable allowances from a Guarantee of Origin (GOO) trading scheme should not be unnecessarily restricted.

    —  The Government should publish its estimate of the full cost to the consumer of meeting the target in each sector.

    —  The main barriers to completing renewable electricity projects are the time required to achieve planning consent and the construction of major grid upgrades.

    —  Turbine manufacturing capacity will need to be scaled up and vessel availability increased if the level of offshore wind projects required to meet the target are to be delivered.

    —  Changes in transmission access arrangements are likely to be required but these must balance the need to connect new renewable generation with the need to avoid inefficient constraint costs.

  1.  E.ON UK is one of the UK's largest retailers of electricity and gas. We are also one of the UK's largest electricity generators by output and operate Central Networks, the distribution business covering the East and West Midlands. In addition, our E.ON Climate and Renewables business is a leading developer of renewable plant in the UK with 21 onshore and offshore wind farms and a dedicated biomass power station currently operational, and more in development.

  2.  Across the E.ON Group we currently have renewable generation capacity in excess of 7,300MW. We have recently doubled our investment budget into renewables to €6 billion between 2007 and 2010. E.ON is looking to increase its overall share of renewable electricity significantly by 2030 which will assist the company in meeting its target to be 50% less carbon intensive by 2030 (based on 1990 levels). Our answers to the Committee's questions are as follows.

How achievable are both the EU's general 20% and the UK's national 15% renewable energies target?

  3.  The UK's proposed share of the renewable energy target poses major challenges, particularly given the relatively short period between now and 2020 and the limited contribution renewable sources currently makes to UK final energy consumption. In 2007 renewable energy accounted for approximately 2% of UK final energy consumption. Renewable electricity has grown significantly since the Renewables Obligation was put in place in 2002 but nevertheless accounts for only about 5% of electricity consumption at present. Given that the Government estimates that the UK is likely to have to meet 25% of the total EU additional cost, meeting the target in full may be more difficult for the UK than for the EU as a whole although particular Member States may have different issues arising from their particular energy mix.

  4.  The extent to which the target is delivered will depend on whether some major barriers to investment can be overcome and sufficient incentives to attract the very large capital investment required not only in renewable capacity but also the fossil plant required to back up intermittent generation from wind and tidal resources. However, this will require a very rapid acceleration in investment in renewable energy sources over little more than a decade, bearing in mind that the directive may not be agreed until well into 2009.

  5.  The implications for the electricity sector are significant given that a very substantial contribution—possibly in excess of 40% of electricity consumption—may need to be met from renewable electricity sources, largely in the form of onshore and offshore wind and some biomass generation. This level of target will require a number of significant barriers to be overcome including grid access, planning and supply chain constraints. In addition, a robust long-term policy framework which will attract the necessary investment to the UK is required. Such a large penetration of renewable generation also poses some very major issues for the power system as a whole. These need detailed assessment but given that wind generation is variable in output, a relatively inflexible source of power and only a small proportion of total capacity can be relied on to meet peak demand, a large volume of more flexible fossil generation will be needed to maintain system stability. These issues will need to be addressed in the strategy which the Government has indicated it will publish next year after the directive has been agreed.

  6.  The full potential of renewable heat and transport sources will need to be utilised to avoid an excessive burden falling on the power market. The heat sector is currently the largest consumer of energy and accounts for approximately 43% of the UK's final energy demand. This sector has historically received little attention. However, there is substantial renewable potential from heat technologies which BERR is currently addressing following its Call for Evidence.

  7.  Given that the targets are expressed as a percentage of final energy consumption, a key objective must be to ensure that effective energy efficiency policies are in place to ensure that total energy consumption is reduced or at least growth contained, which would reduce the absolute level of renewable investment required to meet the targets.

  8.  The deliverability of the targets would be improved if the Directive allowed flexibility in how the target is met. We support provisions in the directive for importing renewable energy from states adjoining the EU, provision to take account of investment in large tidal schemes, and for trading of Guarantees of Origin (GOO) certificates across the EU, although, as currently drafted, trading will be largely at the discretion of Member States. If the targets are to be met in a sustainable way which is acceptable to consumers, a key component must be the cost effectiveness of delivery which will be enhanced by the ability to trade renewable energy effort via GOO certificates. We note the conclusions of the recent Pöyry report on behalf of BERR on the compliance costs of meeting the 2020 renewables target which states: "On the basis of the Commission burden sharing, the cost to the UK increases by around 34% from €5.0 billion to €6.7 billion if trading is not a viable alternative."[1] Trade in GOOs must not be unnecessarily restricted.

  9.  In addition appropriate financial support mechanisms will be required to incentivise investment. It is imperative that current renewable investment plans are not delayed or discouraged by uncertainty about the policy framework. On this basis, E.ON UK would prefer to see a continuation of the Renewables Obligation (RO) as the primary financial support mechanism for renewable electricity which will need to be developed further if the target is to be met. However we do not rule out other forms of support for very large long lead-time capital projects such as the Severn Barrage.

How coherent are these proposals in the context of the EU's energy policies in general and the Third Energy Package in particular?

  10.  The renewable energy targets could have the effect of diverting investment from other potentially more economic means of delivering carbon savings. Under this scenario, it would raise the overall cost of achieving the EU's climate change targets, which would not be consistent with the EU's objective of maintaining an internationally competitive economy. It will be important to ensure that support for renewables results in reductions in technology costs which reduce the long term cost of renewables. Furthermore there must also be adequate incentives to invest in other low carbon technologies and Member States must aim to meet in full the targets set out in the Energy Efficiency Action Plan.

  11.  It is important that all the elements of the green package form a coherent whole. In particular the EU's 20% renewable energy target and the 20% GHG emissions reduction target and the associated reductions in emissions required under the EU ETS have to be consistent. An unexpectedly high level of carbon abatement from the renewables target could deliver the reduction effort expected of the EU ETS. This could significantly reduce demand for EU emission allowances (EUAs) and result in a low or zero carbon price, reducing incentives to invest in or operate other lower carbon technologies. As the green package is considered by the Council and European Parliament, it will be important to ensure that the targets maintain a credible price for carbon.

To what extent are these targets capable of improving the EU's security of energy supplies?

  12.  E.ON UK agrees with the Commission that achievement of the Renewable Energy target would improve the EU's security of energy supply in that renewable energy will reduce dependence on imported gas and oil and contribute to diversity. However, this may to some extent be balanced to the extent that the EU or the UK becomes reliant on a large proportion of relatively new technologies, such as offshore wind, which may be less reliable in operation in its early stages of commercial deployment. Policies to deliver the target should include a focus on ensuring long-term reliability.

GRID ACCESS

How effective has the existing legislation (2001/77/EC) been in encouraging grid access for renewable energy generators?

  13.  In general the existing legislation has had little effect in encouraging grid access as its provisions state that Member States "may also provide for priority access to the grid system of electricity produced from renewable energy sources".[2] Whilst the existing Directive does state that the transmission operator should give priority to renewables when dispatching plant, this is not relevant to the self dispatch market based approach within the UK which allows renewable generators themselves to determine when they want to generate. The UK's current access arrangements are technology neutral and seek to prioritise those projects that are able to use the system the soonest. The transmission operators have obligations in their licences that do not allow them to discriminate between technology types.

  14.  Growth of renewable generation that is connected to the distribution network has been steadily achieved. The main issue with obtaining a distribution connection is overcoming local project specific connection and grid reinforcement issues.

To what extent does grid access remain a significant barrier to increased consumption of renewable energies? Is it consistently a problem across all Member States?

  15.  The main transmission-related barrier to the growth in renewable generation is the lead time associated with achieving planning consent for, and the construction of, major grid upgrades. This can often be many years longer than the development and construction time required for an onshore renewable generation project. BERR and Ofgem have commenced a review of transmission network access in the UK, to look at ways in which the capacity of the existing network can be further shared between existing and new generation projects in advance of and in parallel with the need for further upgrades to the electrical network infrastructure. The main balance to strike is between the ability to connect additional generation, the costs to the consumer associated with constraining off generation owing to insufficient network capacity and the need to maintain network reliability and safety for security of supply.

How does Use of System charging affect grid access for renewable energy generators? How far can the different levels of renewable energies take-up in different Member States be attributed to Use of System charging and cost sharing rules?

  16.  The level of use of system charging in the UK is determined on a cost reflective basis. This means that parties that are seeking to use the transmission system bear their appropriate share of the costs that they impose on the transmission network. This provides a locational signal that helps to ensure the long term economic efficiency of the network, where generation that is located further away from demand must pay more as more network is required to transport the energy to the demand centres.

  17.  In the UK the main demand centres are in the south of the country, with the majority of the onshore renewable development occurring in Scotland. There is presently a ∼10GW queue of renewable generation projects in Scotland that are at various stages of development and seeking to connect to the grid. In the context of the overall UK energy market, the higher use of system charge in Scotland does not itself appear to be a barrier to bringing these projects forward. Conversely renewable generation projects seeking to connect in the south, closer to the demand centres, are encouraged to do so as they would incur lower use of system charges.

What impact do the various systems of reinforcement planning and work have on encouraging renewable generation? How important is the issue of constraint in increasing Member States' renewable generation?

  18.  In the UK, the transmission companies have a licence obligation to plan reinforcement and operation of the network in accordance with the Security and Quality of Supply Standard (SQSS). This is a deterministic standard that ensures that an appropriate balance between the requirements to connect additional generation, the costs associated with constraining off generation owing to insufficient network and the need to maintain network reliability and safety for security of supply is achieved. It is worth noting that a cost benefit analysis supplements the deterministic standard to aid determining an appropriate and acceptable level of constraint costs.

  19.  The SQSS is presently being reviewed by the three transmission licensees in the UK to determine the appropriateness of the assumptions made in the standard for modelling intermittent generation sources, such as wind. The extent to which the SQSS can accommodate additional renewable generation depends on the assumptions made on the diversity and load factor of the renewable generation sources, particularly intermittent generation, and the difference in cost between additional network reinforcement and network constraint costs arising from insufficient network to secure demand.

  20.  In order to connect to and use the transmission system in the UK, a party must hold an agreement with the transmission operator for Transmission Entry Capacity (TEC). The TEC is provided on an "invest and connect" basis, whereby appropriate network reinforcement is completed before a generator is permitted to connect and export to the network. This ensures that the level of network constraint costs will not be unduly increased, as these costs may not be borne by the party that is connecting, but instead are paid by other market participants that are not deriving a direct benefit from the connection of that generation, giving rise to an indirect subsidy. The issue of constraint costs is significant in the UK pay as bid market mechanism for managing network constraints.

To what extent is further co-ordination of National Regulatory Authorities needed?

  21.  In our view, it should be left to national regulators to approve national grid access arrangements in light of the requirements of EU legislation, guidance or codes developed at the EU level, except where trade across Member States is an issue. Coordination of approach can be achieved through the European Network for Transmission System Operators (ENTSO) and the Agency for Cooperation of Energy Regulators (ACER) proposed in the third package.

How far do current regulations inhibit access to the grid?

  22.  The primary cause of delay in terms of grid access has been the extended timescale for securing planning approval and for construction of transmission upgrades. Some improvements in transmission access arrangements are possible but these need to be at an acceptable cost to the consumer, as discussed above.

SUPPORT SCHEMES

At what level should the EU be involved in harmonising or regulating support schemes offered by Member States to encourage renewable energy generation?

  23.  The EU should in principle move toward a more harmonised approach to renewable support as this would be consistent with an efficiently functioning internal energy market. However, shifting to a fully harmonised approach now would create uncertainty for investors and render the targets more difficult to achieve. Therefore we can expect both quota based systems such as the renewable obligation and feed-in tariffs to continue to operate across the EU to meet the 2020 targets. Nevertheless the draft directive does enable, subject to certain conditions, trading between Member States despite different support schemes being in operation. Allowing the trading of GOOs will not only provide the flexibility to facilitate credible and efficient renewable investments, but will lead to a degree of convergence over the value of the renewable support schemes across the EU. However the extent to which this occurs will be down to the market rather than through regulation.

What impact have the various schemes in operation across the Member States had on encouraging renewable energy? How have these schemes affected take-up both by producers and commercial and domestic consumers?

  24.  In the UK, the RO has successfully stimulated growth in the lowest cost renewable technologies including landfill and sewage gas, co-firing of biomass and onshore wind. Before the RO was introduced in 2002, the UK had less than 2% electricity from renewable sources. Today renewables represents around 5% of electricity. However the limited support available for renewable heat to date has prevented this sector from fulfilling its potential.

  25.  The growth in renewables particularly from onshore wind would have been substantially greater if the planning system was more efficient, and we are supportive of the government's reforms contained in the Planning Bill which are designed to increase the efficiency of the process for larger scale projects in particular. Furthermore growth in renewables has been held back by grid constraints. Clearly this needs to be addressed to ensure that projects can connect to the grid in a timely and efficient manner. Without a significant investment in the grid infrastructure, the UK will not be able to deliver the 2020 targets.

  26.  The introduction of banding to the RO has been required to stimulate investment in offshore wind and dedicated biomass, two renewable technologies that have the potential to make a significant contribution to the energy sector. Without the changes contained in the current Energy Bill, offshore wind would require additional financial support such as capital grants to enable such projects to be sanctioned.

  27.  Renewable development in Germany has been supported through feed-in tariff and this has led to a substantial development in onshore wind capacity as well as other technologies such as photovoltaics. However there has been limited offshore development hitherto. This approach has been in place for longer than the UK and planning and transmission constraints have been less significant issues. Given that the UK has adopted the Renewables Obligation which is incentivising large volumes of renewable development, that its structure has been amended to support a range of technologies, and that transmission and planning constraints are being addressed, we see no point shifting at this stage to a different support mechanism given the disruption and uncertainty this would cause for investors. Support for some technologies in Germany, for example photovoltaics, have been extremely generous and we question whether this would be seen as an effective use of customers' or taxpayers' money in the UK.

Will cross-border renewables markets be genuinely affected by the existence of a variety of support schemes? Is necessary investment hampered by lack of market harmonisation?

  28.  The challenge of delivering the renewable energy targets will require a significant level of domestic effort in each Member State. Nevertheless the ability to trade via GOOs will help to minimise the cost of meeting the target. The development of GOO trading is not conditional upon a harmonisation of support mechanisms. The draft directive permits trading of GOOs even though Member States will be operating different renewable support schemes. In our view there are other more fundamental barriers which must be addressed which we have discussed above.

To what extent would the enhanced use of Guarantees of Origin certificates require the harmonisation of support schemes?

  29.  The trading of GOOs can operate alongside mixed national support mechanisms. Therefore we believe that the Renewables Obligation in the UK can operate alongside other support mechanisms whilst still permitting the trading of GOOs.

  30.  As the directive is currently drafted, a producer in Ireland who sold a GOO certificate to the UK market would not receive the income stream from the feed-in tariff. Instead the producer would be entitled to the value of the GOO which would be determined through negotiation with the counter-party from the UK. The GOO would count towards the UK contribution but would be excluded from the production of renewables within the Irish market. This demonstrates how two different support mechanisms can operate whilst enabling the trading of the GOO certificate.

21 April 2008




1   http://www.berr.gov.uk/files/file45238.pdf Back

2   http://eur-lex.europa.eu/pri/en/oj/dat/2001/l_283/l_28320011027en00330040.pdf Back


 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008