Select Committee on European Union Minutes of Evidence


Memorandum by Centrica

GENERAL QUESTIONS

1.   How achievable are both the EU's general 20% and the UK's national 15% renewable energies target?

  The UK objective of 15% renewable energy by 2020 represents a challenging but achievable target. As yet is unclear precisely how this figure will be achieved as the capacity of the three different sectors (heat, transport and electricity) to deliver is still being assessed. Centrica's interests in the sectors contributing to the UK target are predominantly large-scale wind projects, and microgeneration technologies, particularly those providing heat. We offer the following brief comments on the potential in each of these areas which are expanded on elsewhere in this response.

Large-scale wind

  It is our understanding that around 40% of the UK's total electricity requirement will need to be generated from renewable sources. Wind power is currently the most economically viable and scaleable renewable technology and will play a major role in meeting the target.

  Centrica has already made a significant commitment to develop renewables assets as part of our energy portfolio. In July 2003 we announced plans to invest in our own renewable generation assets, primarily offshore wind farm developments although we continue to keep other forms of renewable energy generation under review.

  We are currently investing in six offshore wind farm developments, one of which, Barrow Offshore Wind, is now operational. Two others, Lynn and Inner Dowsing (LID), are in construction, and are expected to be fully commissioned by the end of the year. This is currently the world's largest offshore wind construction project.

  Of the remainder, Lincs had its application for consent submitted in January 2007, and we are awaiting determination, whilst Race Bank and Docking Shoal will have their consent applications submitted this year, based on detailed environmental impact assessments. Barrow is a joint venture development with the Danish energy group DONG; all other projects are wholly owned by Centrica.

  We have two operational wind farms onshore in Scotland, the wholly owned Glens of Foudland wind farm in Aberdeenshire, and Braes of Doune wind farm in Stirlingshire in which we acquired a 50% ownership from Airtricity in July 2007.

  We are also investing in a range of power purchase agreements with renewable electricity developers which will increase the amount of green electricity that we buy through offtake contracts in the UK over the next five years. These projects cover a diverse range of technologies such as wind, landfill gas and biomass generation.

  Centrica believes that the UK electricity sector is capable of rising to the challenge of deploying renewable projects at scale over the next decade, though this will require significant effort from all stakeholders to remove barriers to investment. It also requires that firm investment decisions be made in the very near future on areas such as grid and in elements of the supply chain. For this reason it is of utmost importance that investors are clear of the Government's ambitions in this area, and have confidence that these ambitions will be unswerving.

  Building offshore wind costs around three to four times that of gas-fired plant. To meet the targets, therefore, industry will need additional government support through a strengthening of the existing Renewables Obligation targets and extending the timeframe past 2027. This will signal the long-term nature of the UK renewables sector and, if set at the right level, should encourage the necessary investment in projects, skills and in growing a UK supply chain. A high and visible carbon price going forward would also help the economics of renewables.

  In addition, an effective, streamlined planning system which allows the delivery of both offshore and onshore infrastructure is crucial. A new consenting regime will need to better manage stakeholder conflict which has characterised many developments in the past. Fishing, shipping and radar concerns from MoD and NATS are all potential barriers to the early implementation of new wind projects.

Microgeneration

  The sheer size of the heat market as a proportion of the overall energy market (around twice the size of the electricity market in energy terms) means there is significant scope for the heat market to make important contributions to both the 2020 Renewable and 2050 Carbon Targets, both through continued energy efficiency improvements and through the deployment of low carbon and renewable microgeneration.

  In order to stimulate the widespread deployment of microgeneration technologies, an appropriate support framework is vital. Any effective support mechanism for microgeneration will need to recognise the specific deployment issues involved, and the differing needs of different microgeneration technologies.

  Barriers to microgeneration include the often high up-front capital costs, as well as regulatory issues (including problems with planning and high transaction costs for accessing ROCs), and a lack of consumer understanding about what can be achieved in this area. All of these barriers will need to be addressed.

  The Government currently provides support to some technologies such as offshore wind in excess of the price of carbon avoided. This is done when these technologies offer additional benefits such as diversity of supply, technological learning, and creation of a UK export industry. Where other technologies provide similar benefits then a similar level of financial support should be available. We believe this is the case for a number of renewable heat technologies.

  Whilst the 2% additional innovation band for microgeneration in CERT is a positive step, we do not believe that this is sufficient to bring about a market transformation in this sector, and do not believe that CERT should be viewed as the primary support mechanism for microgeneration. Additional assistance will therefore be required.

  Assistance could be in the form of either capital support or revenue support. We see merit in both and would work within either framework to deliver products to our customers. The most often mooted revenue support mechanism is a feed-in tariff. The effectiveness of this mechanism is likely to depend on the level at which it is set, and its operation.

  Suppliers, who have an existing relationship with customers, are best-placed to administer a feed-in-tariff scheme. Allowing suppliers to reclaim revenue paid out to customers from a central fund is crucial. If the scheme is not funded centrally, suppliers may be disproportionately disadvantaged and unwilling to promote microgeneration technologies as a result. The scheme could be funded from general taxation, although we note the significant revenues that are likely to be raised from auctioning emission allowances in the future and believe that this could be a source of future support.

  A feed-in-tariff would provide an ongoing revenue stream for a defined period. We believe that if the appropriate revenue were guaranteed, suppliers and others would actively consider introducing services designed to lower the capital cost of relevant technologies.

Trading of Guarantees of Origin

  There is scope for part of the UK requirement to be delivered via trading with other countries but at this stage it is unclear how much trading will take place. Trading across the EU could be a cost-effective way for the EU as a whole to meet its targets, but this needs to be reconciled with the need to keep existing investments in home countries on track. The Directive allows for limited trading with countries outside the EU under strict conditions including the import of the electricity generated. Centrica does not oppose this level of trading, but we strongly oppose any amendment of the EU Directive to allow more widespread international trading. We believe this would undermine some of the objectives of the Directive, particularly in reducing dependence on fuel imports, and security of supply, and could significantly undermine investment within the EU.

  Furthermore, meeting the UK target predominantly from projects within the UK will have additional benefits in terms of improving security of supply and building a domestic capability and capacity in the renewables sector, bringing value to UK plc. These benefits will be lost if the domestic target is diluted through trading. Potential UK investors will need to be confident that the UK government is serious about meeting the target before committing resource in this country.

  We also have a concern that the potential for trading within the EU will not be known until the middle of the next decade. As we have already stated, we believe that the scale of the deployment required is extremely challenging, and requires firm action to be taken in the short term. Anything that throws doubt on the necessity for such deployment will undermine chances of achieving changes of the scale necessary.

2.   How coherent are these proposals in the context of the EU's energy policies in general and the Third energy Package in particular

  There are four areas of the EU's energy policies that will have an important bearing on the renewable energy targets. These are the Emission Trading Scheme, energy efficiency, energy liberalisation and energy security of supply.

  Investment in lower-carbon technologies including power generation will depend ultimately on a strong and visible carbon price. The European Commission's proposals setting out a framework for Phase III of the Scheme beyond 2012 strengthens the ETS significantly.

  Centrica welcomes those measures and hopes the UK will use its considerable influence in Europe to ensure that the Scheme is not weakened during its forthcoming negotiation phase.

  The most cost-effective solution to climate change is to improve energy efficiency. The government has provided a strong impetus for action in the UK, notably through the suppliers CERT programme which will see energy companies spending £1.5 billion over the next three years promoting reductions in carbon emissions and installing energy efficiency measures in customers' homes.

  At the EU level more action may be required to ensure that other member states take greater advantage of this underdeveloped source of lower carbon emissions.

  The European Commission identified a number of pre-requisites for adequate new entry by electricity generators that do not exist in many continental energy markets. These include access to electricity networks on non-discriminatory terms as well as ensuring that the necessary network investments are carried out.

  The removal of these deficiencies is being driven forward by the EU via its Third Energy Package. The Commission's proposals for ownership unbundling remain the cleanest and surest way of ensuring the necessary cross-border investments to deliver security of supply, liberalised markets and the delivery of a low carbon future. The UK is to be congratulated for its support of the Commission's proposals.

  Care will be needed at the EU level to ensure that delivery of the EU targets for renewable energy does not undermine the EU ETS which could be the basis of a global carbon market, and the source of support for low carbon technologies in the future.

3.   To what extent are these targets capable of improving the EU's security of energy supplies

  Renewables could have a significant positive impact on security of supply in the UK and elsewhere in the EU.

  At the current time, around 25% of Europe's gas needs are being met from east of the EU. Over the coming decade both the UK and the EU are forecast to be increasingly dependent on imported gas. By 2015 the UK will be importing as much gas as it produced in 2007, although meeting the EU renewable target will have some impact on this. Moving to a renewable electricity target of around 40% would drop load factors for coal and gas plants dramatically—gas fuel use could drop by around 50% from 2007 levels by 2020/25 from a combination of wind and new nuclear build.

  This reduced UK gas dependency will increase the diversity of the UK's fuel mix, and furthermore will mean that a large proportion of its energy requirements come from sources where the fuel is free. Given the need for conventional back-up to renewables, additional conventional generation will need to be planned for going forward.

GRID

4.   How effective has the existing legislation (2001/77/EC) been in encouraging grid access for renewable energy generators

  Directive 2001/77/EC on the promotion of renewable electricity covers a number of areas, including renewable targets, support schemes and grid system issues. With regards to grid system issues, the UK has opted to provide non-discriminatory grid access for all forms of generation and does not give preferential treatment to renewable generation.

  However, in practice renewable generators do have priority with regards to the transportation of electricity because by putting in expensive (unattractive) bids and offers in the Balancing Mechanism, these generators are unlikely to be constrained off when National Grid has to take action to balance the transmission system.

  It is important that a balance is met between conventional and renewable generation, not least because the former is still required to provide back-up for renewable energy which is mostly of a variable nature. Renewable generation without adequate reserve or backup would have security of supply issues.

5.   To what extent does grid access remain a significant barrier to increased consumption of renewable energies? Is it consistently a problem across all member states?

  As identified by the Energy White Paper and confirmed by the Transmission Access Review carried out by Ofgem and BERR, access to the transmission system is a significant barrier for both renewable and conventional generation. Currently there is more than 40GW of projects (both renewable and conventional) waiting to connect to the transmission system with connection dates which extend beyond 2018.

  To replace existing conventional generation, and to provide necessary back-up to new renewable generation, around 22.5GW of conventional power stations will need to connect by 2020 in locations which are often remote and distant from centres of demand and/or current generation locations. Centrica believes that new access arrangements should support the connection of renewable generation, but at the same time not undermine investment in existing and new conventional generation, in particular as intermittent renewable generation requires back-up from conventional generation.

6.   How does Use of System charging affect grid access for renewable energy generators? How far can the different levels of renewable energies take up in different member states be attributed to Use of System charging and cost sharing rules?

  Both renewable and conventional generators pay for the use of the transmission system (Transmission Network Use of System (TNUoS) charges) and for balancing services provided by National Grid as System operator (Balancing Services Use of System (BSUoS) charges).

  The TNUoS charge has a both a locational and a non-locational element. The locational element is to encourage generators to connect in areas close to demand as this would require less transmission infrastructure than generation located in more remote or peripheral areas. The further away from demand, the higher the TNUoS charge and in addition the more electricity is lost as a result of transporting electricity over long(er) distances. This is true for both renewable as well as conventional generation.

  Centrica believes that the locational element of the TNUoS tariffs is non-discriminatory and gives a transparent investment signal.

  In the UK constraint costs are already considerable, in particular because of the high level of (renewable) generation in Scotland compared to Scottish demand and the limited capacity of the Scottish interconnectors. Under the current regime, these constraint costs are socialised via BSUoS charges across all generators and suppliers. A further increase in generation in Scotland will most likely exacerbate the problem and result in even higher BSUoS charges.

7.   What impact do the various systems of reinforcement planning and work have on encouraging renewable generation? How important is the issue of constraint in increasing Member States' renewable generation?

  As much of the UK transmission system is coming to the end of its asset life, in addition to the work needed to extend the network for new projects, National Grid also has to replace the existing network. This puts pressure on resources and equipment. This has been exacerbated by the Regulatory requirement to only invest in efficient and economic reinforcement, as signalled by signed connection agreements.

  The Transmission Owners have not been allowed to invest strategically, ahead of the predicted growth in renewables, and this is now impacting the ability to provide connections in the required locations. Consideration should be given to allowing Transmission Operators funding for planning and public inquiry costs and perhaps even network reinforcement costs before individual connection agreements are in place.

8.   To what extent is further co-ordination of National Regulatory Authorities needed?

  It is important that the UK takes into account the regulatory regime in other EU countries. There is a danger that if the UK regulatory regime becomes too complicated and/or creates uncertainty (for example the proposed offshore regime), investors and developers will spend their money elsewhere.

9.   How far do current regulations inhibit access to the grid?

  Getting planning consent is also a major issue for both generators and National Grid and is being addressed by the Planning Bill currently before Parliament, although it is uncertain how effective this bill will be in addressing the problem.

  As part of the Transmission Access Review the industry, with National Grid, is making a number of improvements to the existing transmission access regime. For example, changes to the transmission access queue process have been made recently, moving away from a solely first come first served basis to one that also reflects a generation project's progress. This should help a number of renewable projects, with consents, to leapfrog other connections delayed due to issues such as planning.

SUPPORT SCHEMES

10.   At what level should the EU be involved in harmonising or regulating support schemes offered by Member States to encourage renewable energy generation?

  The EU target places a collective responsibility on member states to tackle climate change. Each country has very stretching targets with an appropriate share the burden of delivery and the legally binding element of the framework ensures that there is a significant penalty for inactivity. This means that the EU regulation of the renewable energy framework is central to ensuring that all countries deliver.

  Individual member states can choose how to meet their targets through a combination of relative effort on, for example, energy efficiency, electricity and transport. This allows each country to maximise the indigenous renewable resource and ensures the most cost-effective delivery of the target. Having decided how to meet the target, each country can implement national support mechanisms that will best deliver the targets, taking into consideration additional and non-fiscal barriers and the extent to which they can be overcome. The RO, for example, works particularly well in a liberalised market as in the UK.

  The EUETS has taken a similar approach in setting a national target, and then allowing individual member states to deliver the target as they see fit, an approach we support and which we believe to be successful.

  We note that a major barrier to the delivery of an increase in renewables is the need to ensure public acceptability for both the costs of meeting the targets, and the physical impact of, for example, significantly more wind turbines. This may be more difficult to achieve if a forced harmonisation gives the misleading impression the targets are a Brussels initiative.

11.   What impact have the various schemes in operation across the Member States had on encouraging renewable energy? How have these schemes affected take-up both by producers and commercial and domestic consumers?

  There is no doubt that there is a marked difference in the level of take-up of renewable energy across member states. Fundamentally, we do not believe that this is a measure of the effectiveness of the national support schemes, but is a reflection of other barriers to deployment such as grid connection, planning permissions and public engagement.

  Each country has varying motives for implementing renewable energy programmes, with climate change and security of supply being sometimes conflicting strategic objectives. In the same way there are a wide variety of barriers to development that exist across member states with grid constraints, local planning consent, national planning decisions, consumer engagement, renewable resource availability, and supply chain issues each having a different impact in different countries.

  The lack of development in the UK is often compared to a high take-up in Germany where a system of feed in tariffs is seen to have been effective in bringing on significant renewable investment against a "failing" RO in the UK. We believe that it is wrong to assume that this is because feed-in tariffs work and the Renewables Obligation does not as other factors are at play.

  This fundamentally understates the additional encouragement that German developers receive in the form of easy and cheap access to the grid, low cost finance for developments and relaxed planning constraints. By contrast, each of these three areas represents significant barriers to development in the UK.

  Indeed, there are around 8 GW of developments that are held up in the UK planning system, many renewable projects have grid connection dates that extend out to 2018 (for which developers have to securitise the costs), and there are no additional finance benefits offered to developers outside the RO.

  Centrica believes strongly that the development of large-scale renewables should continue to be supported under a reformed and banded RO.

  Maintaining but reforming the existing system will allow a continuous flow of investment, will maintain investor confidence, and is consistent with the parameters of a competitive market. Under a banded RO, suppliers will remain obligated to deliver renewable generation, thus encouraging their participation in renewables.

  We believe that the RO provides a mechanism that works well in our liberalised energy market and is not the source of construction delays. We believe that with some modification it is capable of being extended to meet the EU requirements. Any move to radically change the support mechanism is likely to result in a market damaging hiatus in renewable build, as investors struggle to get comfortable with new parameters. This would occur just at the time when we are trying to accelerate the development of projects and could jeopardise the UK's achievement of the EU targets.

  Mega-projects, such as the proposed Severn Barrage project which have limited potential to be copied elsewhere and are characterised by their enormous size, should be supported outside the RO. If allowed into the RO scheme, these projects will either produce a significant amount of generation thus potentially flooding the market with ROCs (and causing a price crash), or no generation, potentially starving the system of ROCs (and causing a price spike). Either way, the existing system would be destabilised, threatening existing investments.

12.   Will cross-border renewables markets be genuinely affected by the existence of a variety of support schemes? Is necessary investment hampered by lack of market harmonisation?

  There is currently a significant volume of renewable power traded across EU borders and between member state and non-EU countries. In principle, Centrica does not believe that this cross-border renewables market will be affected by the existence of a variety of support schemes. However we are mindful that as a price is attached to Guarantees of Origin, it would be inappropriate for existing projects to receive high windfall benefits resulting from the EU mechanism. We therefore support the EU framework in restricting the tradable GoO to new plant only. This would not prevent the trade of renewable power from existing projects, but the GoO would not be transferred.

  We do not believe that investment is hampered by a lack of market harmonisation. The barriers to investment in the UK are well understood and include difficulties in securing consent to build, connecting easily to the grid, and sourcing generators and ancillary equipment in an appropriate timescale, and are not to do with the support scheme.

13.   To what extent would the enhanced use of Guarantee of Origin certificates require the harmonisation of support schemes?

  Centrica understands that the design of GoO trading arrangements is such that it does not require the harmonisation of support schemes. In the long run, we would expect harmonisation to occur as all low-carbon technologies are supported by the carbon price.

  However, the system as devised enables each country to continue and through the system of "Prior Authorisation" protect the national support mechanism. In the UK, once a project has opted for the RO as its support mechanism, it continues to get support until the end of the RO (2027). If the project receives ROCs, the Guarantees of Origin are automatically presented for cancellation and cannot be traded.

  This therefore requires the developer of a new UK renewable project to decide between the RO support and the opportunity to trade Guarantees of Origin on the European market (provided the UK Government has granted Prior Authorisation). In this way, we believe that the EU mechanism does not require harmonisation of support schemes.

21 April 2008




 
previous page contents next page

House of Lords home page Parliament home page House of Commons home page search page enquiries index

© Parliamentary copyright 2008