Select Committee on Science and Technology Minutes of Evidence


Examination of Witnesses (Questions 740-759)

Ms Gilli Hobbs and Mr Andrew Swain

6 MAY 2008

  Q740  Chairman: Thank you. Where do the primary waste streams in the construction industry arise from? What would you identify as the streams? Equally important, once we have established what you would regard as these primary waste streams, how do you see them in terms of value. Obviously you could waste a lot of energy trying to retrieve waste which is, frankly, not worth it in terms of effort or cost or even environmental benefit. How do you identify these major streams?

  Ms Hobbs: I tend to split them into demolition waste, refurbishment waste, construction waste and then the civil side of things as well. They are all very different waste streams and the composition of the waste within them is quite different as well. The studies that have been carried out to date have focused pretty much on the aggregates aspect of the waste stream, so we have quite good statistics in terms of the amount of waste that is generated that can essentially be converted into aggregates but we have less information on the more active waste. The BRE has been undertaking benchmarking studies with support from Defra. From that, I can give you an idea of the composition for housing waste: for example, 17%, the biggest single component of the waste stream, is packaging waste by volume. Then you have other quite significant wastes: concrete, bricks, plastics and timber. That is the general composition. It is pretty much the case that those that can be processed quite easily tend to be the ones that are recycled the highest.

  Q741  Chairman: We have heard varying claims about the amount of material on site that is wasted and it ranges from 13% to 30%. Do you have information centrally or in terms of your experience, Mr Swain, to suggest whether or not these figures are realistic? It is quite a substantial divergence. What is your take on this?

  Mr Swain: I think it is. I think there is a variety in the percentage of waste because of the types of projects that are carried out and various sizes of project and types of project that are carried out. It is important to make a differentiation between a civil engineering project and a construction project. Within civil engineering, most of the high value waste tends to be bulk aggregates, earthworks material, whereas in construction, house building and office building, it tends to be packaging type waste. It is important to make a distinction there between the two sorts of projects that we are discussing. The figures you have quoted are probably quite accurate. I do not think as an industry we are particularly good at recording the amount of waste that is generated and what we regard as waste in the first place.

  Q742  Chairman: Is that even taking into account the EU Packaging Directive which imposes quite a lot of responsibilities of a costly character on businesses?

  Mr Swain: It does. We are lacking take-back schemes in the industry, for construction projects to take back their waste packing to their supplier and manufacturers. There is a lot of material at the end of the job that goes to waste because there is no local market for it, if you like, to recycle it or to reuse it.

  Q743  Chairman: I realise that Mr Brock from Balfour Beatty would probably have been able to help us on this issue but maybe you can say from your own experience and results. Are large construction companies aware of the financial costs of waste? If they are—and one assumes they would be—in your experience, how can they communicate that down the chain to the second and third tier contractors for whom they have responsibility?

  Ms Hobbs: We have been working with quite a few companies to set benchmarks for the overall amount of waste they are looking to produce compared to the floor area. That seems to be quite a powerful way of getting everybody to focus on waste reduction. It is very difficult to get people to focus on waste reduction because it is not particularly tangible. You can look at how much waste has been recycled. You can look at those costs; they are quite tangible. Waste reduction is not tangible because you are trying to quantify something that no longer is there. Having this measurement is very important, in order to measure waste reduction. You can then say how much money you are saving. The critical thing everybody is trying to work out is: What is the business case? If I invest this much in terms of waste reduction activities, am I going to get the money back myself in terms of reduced waste costs? It is not as simple as that. Sometimes, for example, the site might be undertaking waste reduction activities but somebody else could be benefiting financially. The things I have seen from the industry in terms of communication tend to be when people come onto the site, they have their Site Waste Management Plan that basically tells everybody on the site what activities should be carried out in terms of waste reduction and recycling, and that is then communicated to people through the site induction and also through tool-box talks throughout the project. That ongoing communication might be posters, telling people how they are doing, et cetera.

  Q744  Chairman: It is really exhortation rather than carrot and stick.

  Ms Hobbs: Yes.

  Q745  Chairman: You are really telling us that they are going through the motions but they are not doing very much.

  Ms Hobbs: I would not say they are not doing very much.

  Q746  Chairman: Would they put their hands up and say, "We've told them that they shouldn't do this but we've not done anything about it other than that"?

  Ms Hobbs: I think everybody is going through a learning process at the moment. The Site Waste Management Plans will mean that everything is at least contained within one place. Whereas it has been sort of scattered about, there have been ad hoc activities, the Site Waste Management Plan will at least centralise some of those activities. A lot of companies are doing a lot in order to maximise their resource use on sites. With waste reduction it is more difficult. You really need to go back up the supply chain to reduce waste and there really is not enough information to help people prioritise their actions on waste reduction. In terms of diverting waste from landfill, there is a lot of work going on throughout the construction industry. They are diverting a lot of waste from landfill. In demolition alone we are looking at 90% plus diversion rates from landfill typically. They are doing a lot, it is just that waste reduction is quite a difficult one to tap into.

  Mr Swain: I would have to concur with what Gilli has said: you have to go back up the supply chain and look at the ultimate client and the designers of the whole construction process, because there is a lot of waste that can be minimised through good design and through the influence of the client.

  Q747  Chairman: You say you are working with member bodies or companies to establish best practice. Where would you go to see examples of best practice? Would it be the UK or would it be companies abroad? From what you were telling me (a) there seems to be a somewhat latter day conversation and (b) it has been suggested that there are higher levels of productivity and efficiency outwith the UK in the construction industry. Are you looking within the UK or are you looking outwith to try to find examples of best practice? If nobody here is really all that good, what is the point of trying to find the best of an indifferent lot when you might be able to go elsewhere and have examples of really super best practice.

  Ms Hobbs: I am on an international group, the CIB, for construction product materials stewardship. We had our first meeting last year. It was built upon a previous group that was looking at design and deconstruction. We did a roundtable with this group and I can honestly say that examples and information from the UK were at least as good as anything else that was coming out internationally around the table. That was not just Europe, it was America, China, throughout—an international group. We, the UK, had plenty to talk about in that international group, so I do not think we should be scared of using our own UK examples.

  Q748  Chairman: You would see that as anecdotal evidence rather than hard and fast statistical evidence.

  Ms Hobbs: We were the only ones who were able to supply statistics in terms of the amount of waste that was typically produced on construction sites. Very few other countries seemed to have that information. This is the first step.

  Mr Swain: In the UK we do some best practice small projects, or islands of best practice, if you like, but we do not do it continually on construction projects.

  Q749  Lord Howie of Troon: I should say, first of all, that I am a Fellow of the Institution of Civil Engineers and I have been involved in the construction industry for quite a long time. I was the first of the Committee to query this waste figure of 30 odd per cent, which, to be quite frank, I do not believe. In attempting to support it, I was sent a report by the Sustainable Development Commission. There is a section on construction waste which I would like to turn to. It says, "The construction and demolition industry contributes 33% to the UK's volumes of waste." That is an entirely different figure. It is not 33% of construction waste, it is the whole thing. What is more, it includes both construction waste and demolition waste, and we are told elsewhere that something like 90% of the demolition waste is reused; it is not waste at all. I find these figures confusing and I would like you to de-confuse me. The range of 13% to 30% as an engineer just leaves me cold. I am not interested in a range of statistics of that sort.

  Ms Hobbs: The 30%, I think, relates to the amount of waste. Say you had a load of construction materials delivered to site to do a project, for example, 100 tonnes of material, 30% of the materials are being wasted. I do not agree with that figure either. Each individual product has different wastage rates and we do not know what the wastage rate is overall because nobody has ever undertaken those sorts of studies, those mass amount studies, so it is very much finger in the air job for that. In terms of the 33%, that is basically saying that, of all the waste the UK produces, which is around 335 million tonnes, one-third of that waste is coming from the combined activity of the construction and demolition industries. That is where the 33% comes from and that is globally, compared to the overall amount of waste produced. Demolition waste would still be classed as waste. Until it is converted or reprocessed into a product, essentially it is classified as waste. We still have that amount of waste being produced; it is just that, of the waste being produced, most of it is being recycled.

  Lord Howie of Troon: I will not pursue this, Chairman. I will merely say that I am convinced now that the figures are an illusion.

  Q750  Lord Methuen: Aggregates are often compounds of a variety of wastes. Are there technical limits as to the quantity and quality of the waste material that can be re-used in this way?

  Mr Swain: I would first query the question there because primary aggregates are obviously aggregates that are quarried materials, whereas secondary aggregates or recycled aggregates do consist of a variety of waste streams. Yes, there are technical limits, but that would be applicable to virgin primary aggregates as well, so they are comparable in terms of specification of aggregate. The concern, in terms of the variety of waste streams, is on the quality of the feedstock in the first instance—whether it has plastics or timber mixed in with it. There is a cross-contamination issue. The work that the Waste Resource Action Programme has done in terms of the waste Quality Protocol has been particularly useful for identifying specifications, or a standard, if you like, for recycled aggregates in that area. In terms of reusing aggregates and recycled aggregates, it is the nature of the project and location to market, and the cost of recycling it versus the cost of disposing of it. Unfortunately, it is still sometimes cheaper to dispose of the material than it is to recycle it and take it to the market and reuse it.

  Q751  Lord Methuen: The landfill tax—

  Mr Swain: The landfill tax is beginning to bite quite severely. On some projects it is still more economic to dispose of it than reuse it and you have to remember that the contractors are profit driven and are trying to make as much money as they can with the project and deliver it on time. Unfortunately, materials are wasted in that respect.

  Q752  Lord Methuen: How well do we understand the properties of these aggregate materials which contain waste? Does our understanding limit the functions for which we can use the materials?

  Mr Swain: In terms of construction demolition waste, we have a good handle on what we can and cannot do with recycled secondary type aggregates from a construction project.

  Ms Hobbs: Yes, definitely. There is good data there.

  Mr Swain: In terms of specification, we know how these materials would perform in terms of the civil engineering projects they could be used for.

  Q753  Lord Haskel: You were explaining how the excess is probably best got rid of in some ways. Is there not any arrangement within the industry, as there are in many other industries, where suppliers will take back excess aggregate or building materials or whatever it is? Obviously you cannot calculate to the nearest whatever it is how much you are going to need, so usually suppliers will take it back and use it for another order. Is that not a way of dealing with it?

  Mr Swain: It certainly is and I would like to see more of it. Unfortunately it does not happen a great deal. You have to think of the range of construction projects we might deal with from large to small. Certainly on a smaller project I do not think you would see that unless you had a significant buying power with the supplier. Construction is one of the only industries I know of that over-orders material or calculates a waste percentage into material with a view to wasting that material before it has even been used it. When you open packs of materials you might have damaged materials as well, so it is not just construction and demolition waste, it is damaged materials that are wasted when being stored improperly on site. That makes it difficult for a supplier to come and collect part materials and part packs, but I would certainly like to see more of that in the industry. As a supplier, I would like to be able to offer that to some of our larger customers.

  Q754  Lord Methuen: Is part of the problem in something like the construction industry—and I am thinking of the use of plasterboard, for instance—that the sizes in which materials are sold are not necessarily ideal for the purposes for which they are going to be used?

  Mr Swain: This is true. You have hit the nail on the head there, yes. You are right in terms of how materials are supplied as well. The supply chain needs to look at that. The influence of clients and designers could again be very helpful here, in looking at manufacturers and contractors in trying to drive that improvement forward.

  Ms Hobbs: That comes down to costs again. When you get pre-cut plasterboard there is a cost attached to that. As Andrew said, a lot of it is just down to costs at the end of the day. It is quite often cheaper to buy bulk materials in and waste them than it is to get the pre-cut plasterboard delivered.

  Q755  Chairman: Cheaper for whom?

  Ms Hobbs: Cheaper for the site, through usual procurement routes.

  Q756  Chairman: At the end of the day, we are talking about a customer. We are not talking about a producer. This seems ridiculous, that we, as consumers, whether big companies or individuals, seem to be paying over the odds for more kit and more materials simply because it is inconvenient for an inefficient industry to get its finger out. Is that really what you are telling us?

  Ms Hobbs: It is not a factory line. A construction site is not a factory line. I am not saying I agree with this necessarily, but from the discussions I have had with the industry, the cost penalties associated with delaying the project because you have run out of a bit of plasterboard far outweigh the costs of disposing of that waste plasterboard.

  Mr Swain: I think the nature of contracts is changing, which helps the situation. In a traditional civil engineering project, the client gives a specification and a design for a project and the contractor goes away and builds it at a certain cost. Whatever he can save on the cost is money in his back pocket. Now what is happening is the client, designer and the contractor are working together in terms of cost savings, and value engineering to engineer out waste and other problems with the project. I think that is a step in the right direction, but we still have that gap between the ultimate customer (the client) and the contractor and his supplier of the material, because the contractor is the customer of the supplier rather than the client, if that makes sense.

  Chairman: That is the point I was trying to make.

  Q757  Earl of Selborne: Could you tell us if any research has been undertaken in the different waste streams within the construction industry?

  Ms Hobbs: The BRE is carrying out quite a lot of research in terms of different ways of quantifying. We have also worked with the Market Transformation Programme, where we have looked at particular sectors (roofing products, flooring products, plasterboard, insulation), quantified the amount of waste that is being produced now, and modelled it into the future to see if it there is an increasing or decreasing impact. There are a lot of waste composition studies that either are being completed or are under way that would give us better information in terms of the non aggregate waste aspects.

  Q758  Earl of Selborne: Could you give us some flavour as to which waste streams you think are going to be increasing?

  Ms Hobbs: Insulation particularly is quite a big waste stream that is going to increase in terms of volume. If you think about it, you have the building regs that are requiring increasing levels of insulation in buildings, so if you are then saying that you have millions more metres square of insulation going into buildings and 10% of that is wasted, typically, in terms of off-cut material, then you have an increasing amount of waste from insulation. When those buildings come to be demolished, then you have increasing layers of insulation waste that are going to come out during the demolition side of things. Currently it is quite difficult to see how that waste is going to be diverted from landfill in significant quantities. I would say that insulation is one of the potential waste streams of the future that we are going to have to deal with increasingly.

  Q759  Earl of Selborne: It has been argued to us that past research has focused too much on a limited number of materials in a limited number of construction activities. Is there a need for research into reprocessing techniques, including those that can operate at a site level?

  Mr Swain: The construction industry has been quite proactive, looking at options for reusing materials on site in terms of bulk materials, soils and recycled aggregates, but I think you are right that we need to look at site-specific recycling, or local areas around hotspots, or urban areas, if you like, for recycling centres where small volumes of material which are normally uneconomic to reprocess on site could be taken to be processed. Whether that is on site or at an offsite facility within an urban area, I think that would be very favourable. The industry has also been proactive in looking at non-construction type waste, in terms of replacing primary aggregates and cement replacements and sand replacements in construction materials as well. There is a lot of research and development going on at the moment, certainly within my organisation and others, in terms of non-construction waste within construction products.



 