Select Committee on Science and Technology Minutes of Evidence


Examination of Witnesses (Questions 788-799)

Mr Cal Bailey, Mr Chris Sexton, Ms Lesley Seymour and Mr Rainer Zimmann

6 MAY 2008

  Q788Chairman: Good morning, ladies and gentlemen. Perhaps we could start as we did before. Mr Zimmann, could you introduce yourself and we will work our way along the line?

  Mr Zimmann: Good morning, my name is Rainer Zimmann; I work for a company called Ove Arup and Partners. We are a multidisciplinary engineering consultancy and business consultancy. I am a civil and environmental engineer by training, and I have been working with the construction industry for 12 years, specifically on construction waste and waste management in general.

  Ms Seymour: I am Lesley Seymour. I am a chartered civil engineer as well and Chairman of the Institution of Civil Engineers in the southwest. I have recently joined Buro Happold as an Associate, working in their sustainability and advanced technology group and the referenced information I will talk about today was done in a previous role.

  Mr Sexton: My Lord, I am Chris Sexton; I am Head of Engineering at Laing O'Rourke. Laing O'Rourke is the biggest privately owned construction company in the UK—30,000 employees and a group turnover of about £4 billion. I have been with Laing O'Rourke only for four months; previously I was Head of Engineering in the Army.

  Mr Bailey: Good morning, my Lords. I am Cal Bailey; I am the Marketing and Sustainability Director of NG Bailey, one of the UK's largest building services firms, and by building services we interpret that very broadly: mechanical and electrical engineering, that is the services—the heating, the cooling, the lighting and the power in buildings. Also the ICT, where we have done a lot of work and we have extended our work recently to include the floors and partitions and ceilings because that interfaces very heavily with our services—we look after the building then throughout its life, during the maintenance period as well. We do a lot of offsite construction for reasons which we may turn to in due course.

  Q789  Chairman: We are going to start this morning by going over ground that we have been over before, and you will have heard some of the responses given. This is about the data relating to the amounts of construction waste from materials, et cetera. The first question is do we have enough data? Who are the greatest contributors of waste and does it come from new builds, demolition or refurbishment? What is your take on the difference between, let us say, civil engineering and construction as contributors? So a wide range of questions you might not all wish to answer, but who would like to start?

  Mr Sexton: My Lord, in terms of the data—and I think hitherto the data has not been particularly good—I think there has only been a requirement to report hazardous data and there have been no regulatory mechanisms for measuring waste data, and some of it has relied on visual estimates and so on. As you heard in the previous session, even the site waste management plans do not require that waste data to be reported upwards and outwards at the moment, although we would be quite happy if it was. The answer to your first question, my Lord, is that hitherto the data has been weak and we are certainly going forward undertaking benchmarking exercises so that in the future we will know very accurately what our waste data is going forward, but I am afraid looking backwards the picture is slightly opaque.

  Q790  Chairman: So we are around about year zero plus one?

  Mr Sexton: I think we are slightly better than that in that we started this process a few years ago, but it is very much the start of the journey, I think.

  Q791  Lord Bhattacharyya: There are some reports which suggest that as much as 30% of the total weight of materials on site is wasted. Is it an accurate figure? Is it credible?

  Mr Sexton: I think that the 30% does not refer to the total waste from a site and that figure is likely to be much lower. But we do not have the completely accurate data yet.

  Q792  Lord Bhattacharyya: So these reports are not very credible then?

  Mr Sexton: I do not think the 30% figure is correct.

  Q793  Lord Howie of Troon: Good man! Well done!

  Mr Bailey: I would like to analyse waste in a slightly different way, ways which the Committee may wish to take up or may not. We talked about the sources of waste in the analysis from demolition, construction and refurbishment and so on. The analysis I propose would be to do with what I initially called construction error—to do with over ordering, damage in transit, damage on site, the errors that people make on site; secondly, poor planning, which happens before site, which is to do with inadequate planning and incomplete design, and that leads to quite different sorts of waste through work ripped out then put in again in some different form, over-engineering, poor use of innovation, inadequate time to do proper planning logistics—for example all kinds of areas of waste there. Thirdly, what I call lifetime impacts to do with, for example, if one was to very poorly manufacture or construct a building it might be highly draughty and the need for air tightness testing would dramatically improve the energy performance of that building over its life, for example. Finally, packaging waste is of a different order altogether—that is caused by manufacturers—and that would be the fourth category of waste and it seems to me that one needs to analyse the causes of waste quite carefully in order really to understand how to solve these problems.

  Q794  Lord Bhattacharyya: So if you are taking the total system from beginning to end what would be your estimate regarding waste?

  Mr Bailey: I am not going to give you an overall estimate for each of those areas; I have some data on some areas and in terms of the areas I am most interested in—and which you may consider this panel most expert in—is the area of planning and design. We have undertaken a project recently in which—and this is definitely in the status of an art and not a science at this stage—it seems to me highly possible to reduce by orders of magnitude the amount of time it takes to construct projects. I have one very good example of a couple of large hospitals with which we are involved, where by accident the time table to commencement of the project was two years longer than necessary—about two years longer than originally planned, I should say. That was caused by delays to a PFI project—the kind of delays one might be very familiar with—and we decided not to just park the project but to continue with design, which, looking back, we are very pleased we did. We were very fortunate to be in this chain, which was highly supportive, highly integrated, and the result was a project for which we lost 40% labour on site and completed nine months early. I think that was an example of huge waste in process which I would put substantially down to poor planning and poor design. If they are done properly substantial costs can come out.

  Ms Seymour: Taking civil engineering waste, which is the area that I studied. We found very little public information, and taking Lord Howie's point the classification of construction and demolition waste, once you break down those numbers and look at that demolition waste there is a high percentage of reuse incorporated in that 30%. I think if we talk about waste in construction we should be clear about the reuse component that people are already taking forward and what they are doing. Certainly there is a lack of data in terms of what other panel members have talked about. Site waste management plans I think are going to help with that, but the knock-on effect of that is there is a lack of benchmark data; so, say, per metre squared of road construction or bridge construction, of that type of order. I think in setting targets we probably need to look more at the process and what is a realistic target rather than setting an arbitrary target based around the feel good factor number around reducing waste, because in some projects the 20% reduction could be quite innovative and in other projects it could be quite simple.

  Q795  Lord Howie of Troon: I repeat that I am a Fellow of ICE and in the past I have been well acquainted with Arup, Buro Happold and Laing's. I do not know where O'Rourke came from! I was a designer when I used to work. To what extent do architects, designers and engineers work together to consider waste reduction? They did not do it in my day—I am talking about now?

  Mr Sexton: Picking up on the point that my colleague Mr Bailey made before, there is the whole process from design through to decommissioning and in my view the opportunities for reducing and managing waste are very heavily weighted at the start. So in answer to your question we do get together now with clients and designers; we have a scheme called Building Constructive Relationships, of which some of my colleagues here are a part, to get together, to get contractors, designers and the client all together, and that gives you the really big opportunities to design out the waste. If I might say so, in the previous session there was a lot of concentration of what happens when you get on to the site. The die is to a certain extent cast by that stage and there are numerous things which you can do jointly at the design stage to design out waste, and Mr Bailey has mentioned one of them, which is offsite manufacture. If you can design all the components of whatever you are building offsite and manufacture them offsite and then move them to the site then many of the causes of waste which you heard about earlier, such as the logistics, storing too many things, damage to things on site and so on and so forth, simply do not occur; and in my view that is where we should be focusing our attention, at the front end.

  Mr Zimmann: I am from a design background so I completely agree with that. I would like to make a point rather about site waste management plans as well. The wording of that suggests that it actually starts on site but the intention was to start at planning and pre-design stage to get the clients thinking about it and getting a vision out for reducing waste and being resourceful. The work that we have done together with waste with Arup on plasterboard, for instance, has shown that by involving the whole design team the architects and the suppliers of materials is where you get the maximum benefit in terms of reducing waste in the design process. So it is an integrated profile rather than an individual profile.

  Ms Seymour: The Institution of Civil Engineers prepared a demolition protocol that has been used that is very much at the early planning stages, and we do often forget the demolition part of the contract which is quite an important bit to add in.

  Q796  Lord Haskel: The Sustainable Development Commission suggests that the use of construction materials is characterised by what they call a linear process: extraction, manufacture, assembly, construction, maintenance, refurbishment, demolition and then disposal. In many industries now they have what they call a "cradle to cradle" approach, a closed-loop approach where by the time the use has come to an end you can recycle it. Is there any approach made in construction to try and convert this linear process into a cradle to cradle progress?

  Mr Zimmann: I think we are progressing towards that development by trying to set our secondary material markets, which I think is one of the key elements. We talked about take- back schemes where multiple suppliers are looking at producer responsibility and actually bringing it back into the production cycle to have actually a closed-loop approach. But that also obviously means that clients, developers, designers who specify materials have to actually select materials that have a certain amount of recycled content in them to create the demand for those sorts of materials, which are better for the environment ultimately. Then we also need to have enough invested in the infrastructure to create and take out this secondary arm of the waste chain and then supply them back into the production cycle. So it is a multi-factorial approach to this supply and demand model really.

  Q797  Lord Haskel: Are technologies being developed to facilitate all of these things?

  Mr Zimmann: I think there is a lot of work being done to increase awareness, educate people who specify materials, and clients, to set up protocols to encourage people to produce materials, which is a product specifying its quality requirements. Where we are lacking at the moment is whether we actually have enough processing capacity to create that and the availability of markets for those products. The previous panel mentioned treatment hubs, for instance—it has been thought through for contaminated soils, but equally that could be done for secondary aggregate, and that would, I think, also help the SMEs to take some of their materials and actually get the mixed waste and sort it and separate the materials out again, which can be done with high efficiency.

  Q798  Lord Haskel: So it is a matter of will rather than technology?

  Mr Zimmann: I think the technology is there, that is not the problem here.

  Ms Seymour: The point I want to make on that is the chain of responsibility as to it not being linear; it has to be looped as well. That is something they are trying to produce for the site waste management plans, that everybody takes responsibility and that responsibility carries on down through that process rather than stopping with the first person and not handed on. So I think that is something that we really need to consider. Equally, I have seen site waste management starting to become a dominant service provision, so there are actually groups and organisations that are setting themselves up purely to manage on site waste and getting involved with trying to do trying to do resource efficiency, and to my mind they seem to be very successful in it, so certainly people are making a market opportunity, both out of innovation and taking responsibility across various different sections.

  Mr Sexton: The short answer to your question is that it does not have to be linear, and this rather goes back to the previous point about the design stage being absolutely critical. My colleague mentioned specification. At Heathrow Terminal 5 we used 80,000 tonnes of recycled aggregates and 30% of the concrete used pulverised fuel ash, which is a substitute for cement. We have a PFI hospital up in Staffordshire where all the kerbstones are being made not of concrete but recyclable material. This just plays back into the previous thing, that the opportunities to make it a non-linear process are all up in the design stage.

  Q799  Earl of Selborne: The new eco-towns offer the opportunity to conduct whole system design and so remove, reduce and recycle construction waste in ways that would not be available to single build projects. What techniques might be available to use in these projects and what would need to be in the specification to encourage such waste reduction?

  Mr Bailey: Can I take that from an energy point of view, but I am not completely convinced that the Committee wishes to view energy as a type of waste? To me if you heat a building once why does it not stay hot—every time you heat it or cool it thereafter you are wasting energy, and energy is clearly part of a global loop, a planetary loop, looked at holistically. Looking at this from an energy point of view I would suggest that this is an opportunity to build, if you are building a huge project, greater varieties of energy sources and reduce reliance on the grid, to recycle water, for example, to recycle high grade heat, low grade heat within swimming baths and domestic hot water, for example—huge opportunities to consider eco-towns as single loops for energy. And whilst not the total story—we are not talking about materials that much at all—but I think it is a very significant opportunity from an energy point of view. Also to add to the security of energy supply, that is going to become an issue in the UK, we believe, and obviously to obtain energy from various sources, not purely the grid, for example. I will let my colleagues talk about materials.

  Mr Sexton: Eco-towns I think offer fantastic opportunities to start a town from scratch, which is something that we do not normally have because they normally emerge, and opportunities for collaboration. I think there are some challenges as well. For instance, how you plan and lay down the base infrastructure for the town, how you do that commercially is something which I think is not yet clear. But the sorts of opportunities and benefits which could arise are the ability to recycle waste between different projects in the same town, where you are cutting and filling, you can balance that around the whole of the town so that the net arisings are nil. You can specify common materials around the whole of the towns and that will cut down your waste because what you did not use on one you could use on the other. I think if we were involved in it, again the modern methods of construction and offsite manufacture would feature very largely, so we would produce the components for this eco-town offsite and then bring them on to site, reducing labour, reducing plant, reducing time, reducing noise and so on and so forth. So I think there is a bit of a way to go yet but there are huge opportunities in eco-towns.

  Ms Seymour: My thoughts are probably more based around the actual construction activity of the eco-towns whilst they are under development, and I take a point that was made earlier; I think that if you delimited the whole site as being a waste free zone so that nothing goes off the site, effectively, in terms of landfill, that might be a good approach to start with, thinking from that concept that in the construction activity you can constrain it. Thinking about the tender packages—this is before you get to site—it would be foolish not to link some of the tender packages so that the pre-construction works and the post-construction works were linked so there was opportunity to cross transfer waste between demolition and construction activities. Certainly you would need to set aside space on the site for that sort of work to go on, and certainly you would need different types of requirements from the planning body in order to store waste material on the sites for reuse, so the consideration would be needed at quite an early holistic stage to turn them into true eco-towns from their construction. But I think it is all doable.

  Mr Zimmann: I am currently involved in the bidding for an eco-town development as part of a collaborative approach for a developer and I think that eco-towns should be exemplars really for resource efficiency and should be used as such. There are a few points that we discussed earlier, starting with an earlier vision in the master planning process of actually saying, "Waste actually matters, we want to design it out, and the amount that we cannot design we have to manage in a very sustainable way." I think it needs a team of clients, developers, architects, designers, constructors, that share this vision and actually set objectives and targets for reducing waste, for reuse and recycling and also commit themselves to monitor that through the whole process and see how things are going. In terms of modern methods of construction, I think without that it would be a failure from the start, really. Also looking at constructional logistics, how materials are delivered to the site and having a construction consolidation centre, for instance, that will assist during the construction phase, but later on when it becomes operational to use that as well as a facility. Clearly having some way of processing the materials will need to be at those construction consolidation centres as well. So it is a fantastic opportunity to realise something in the country where you have, as was said, a blank canvas to start from, more or less.



 