Chapter 8: The UK's regulatory system
192. The Better Regulation Task
Force defined five principles of good regulation in 1997.[403]
The principles, endorsed by the present Government,[404]
state that any regulation should be "transparent, accountable,
proportionate, consistent and targeted". This chapter will
consider the effectiveness of the regulatory regime for shale
gas in the UK.
The UK regulatory regime: shale
gas exploration and appraisal phases
193. In December 2013, DECC published
a "Regulatory Roadmap" to help operators understand
the regulatory process for onshore oil and gas exploration and
appraisal in the UK.[405]
A diagram from the Roadmap that explains the process in detail
is at Appendix 4. The main regulatory bodies involved are DECC,
local Mineral Planning Authorities, the Environment Agency and
the Health and Safety Executive. The responsibilities of each
are outlined below.[406]
DECC
Issue of petroleum exploration and development
licences (PEDLs)
194. The Crown has the exclusive
right for searching and boring for and getting petroleum in Great
Britain.[407] DECC
issues production licences (known as 'petroleum exploration and
development licences' (PEDLs)) to operators through licensing
rounds. These licences grant exclusivity to an operator within
a certain area. As part of the licensing process, DECC assesses
operator competency, safety management systems, well examination
schemes and financial capability.[408]
The licence does not grant any right to drill a well but exploratory
work through seismic investigations may begin.[409]
Environmental risk assessment
195. Where hydraulic fracturing
is planned, DECC requires an environmental risk assessment (ERA)
to be carried out. This is an overview that assesses environmental
risks over the full cycle of the proposed operations with the
participation of stakeholders, including local communities. DECC
recommends it as a starting point for early engagement by operators
with local authorities and other regulators as it can subsequently
inform other required assessments.[410]
Approval and consent
196. Under the terms of the PED
licence, operators are required to submit to DECC for approval
a hydraulic fracturing plan that demonstrates a full understanding
of the risks involved. Operators also need to evaluate the historical
and background seismicity, describe faults in the proposed area
and identify the risk of activating any fault through hydraulic
fracturing activity. Traffic light monitoring systems are required
to enable operators to mitigate induced seismicity.[411]
197. Operators are required to seek
consent from DECC to drill and consent to fracture once all permissions
and permits from other bodies discussed below have been granted.
Operators can make the requests for drilling and fracturing consent
together.[412]
LOCAL AUTHORITIES / MINERAL PLANNING AUTHORITIES
Planning permission
198. Operators require planning
permission from the relevant Minerals Planning Authority (MPA)
to conduct both exploratory and appraisal work.[413]
County councils or unitary authorities usually exercise MPA
duties. The MPA will determine applications in accordance
with planning law. Permission is granted for the location of any
wells and wellpads and conditions may be imposed to ensure that
the impact on the use of the land is acceptable.[414]
If an MPA refuses permission for the proposed development,
operators can appeal to the Secretary of State for Communities
and Local Government.[415]
199. The focus of the planning system
is on whether the development is environmentally acceptable. Key
issues may include site location, traffic volumes, noise, groundwater,
induced seismicity and waste.[416]
Guidance from DCLG states that Mineral Planning Authorities should
"use appropriate planning conditions, having regard to the
issues for which they have responsibility, to mitigate
any adverse environmental impact."[417]
The guidance recognises that a number of issues are covered by
other regulatory regimes and MPAs
"should assume that these regimes
will operate effectively
as they can rely on the assessment
of other regulatory bodies. However, before granting planning
permission they will need to be satisfied that these issues can
or will be adequately addressed by taking the advice from the
relevant regulatory body."[418]
Environmental Impact Assessment (EIA)
200. The MPA considers whether
a proposal requires an Environmental Impact Assessment (EIA).
If the project is likely to have significant environmental effects,
the operator is required to complete an EIA.[419]
Operators can request a decision from the MPA as to whether
an EIA is needed in advance of any planning application. The EIA
assesses the likely significant environmental effects of the proposed
development. Operators are expected to draw upon the content of
the environmental risk assessment required by DECC. Once the EIA
is complete, the results are presented in an environmental statement
submitted with the planning application. Professor Mair considered
that the EIA played a "crucial role" and "should
be mandatory for all shale gas operations
if [it] is done
properly
the whole path will be much smoother."[420]
201. Mr Figueira told us that
once the planning application is made together with the environment
statement, the MPA will "place and advertise and consult
for usually around 21 days, and then the planning permission would
normally take 16 weeks if it involved an environmental impact
assessment, and, if it did not, around 13 weeks."[421]
The Environment Agency is a statutory consultee to the planning
process.
Agree plan for site restoration
202. Operators are required to present
plans for restoration of the planned development site to the MPA.
The MPA is responsible for ensuring proper restoration and
aftercare of the site when operations terminate.[422]
ENVIRONMENT AGENCY
Notice of intention to drill
203. Operators are required to serve
notice on the Environment Agency (EA) before drilling a borehole.
A detailed statement needs to be submitted with information on
well drilling, well casing, storage of substances including fuel
and chemicals and a proposed plan for dealing with waste.[423]
Environmental permits
204. Operators may require environmental
permits for:[424]
· Groundwater activity[425]
· Mining waste activity[426]
· Industrial emissions activity[427]
· Radioactive substances activity[428]
· Water discharge activity[429]
· Groundwater investigation
consent[430]
· Water abstraction licence[431]
· Flood risk consent[432]
Dr Grayling told us that "the
number of permits and consents that are required
will depend
on the site in question, its geology and what activities are actually
proposed."[433]
As some of the technical documentation supporting operators' planning
and environmental permit applications may need to be submitted
to the EA and to the MPA, the EA "strongly recommend
'parallel tracking' of environmental permits and planning applications."[434]
205. Lord Smith said that the EA
aims to issue permits within a 13-week period but "that,
however, has to include a period for public consultation. If it
is a matter of high public interest, the consultation period might
have to be a slightly extended one, which might push the timetable
a bit beyond the 13-week period."[435]
Draft technical guidance from the EA says that "given the
current level of public interest in unconventional gas and oil
exploration, it's likely that we treat such sites as being of
high public interest
For a bespoke permit application where
there is a lot of public interest, determining a permit may take
four to six months from where the application is duly made."[436]
206. The Secretary of State for
the Environment, Food and Rural Affairs told us that the Government
planned "to reduce the timescales
with the intention
of there being a standard permit."[437]
Dr Grayling thought that the EA would be able to issue these
"within two to three weeks" and they would be available
in early 2015.[438]
We heard from the Secretary of State for the Environment and
from the Environment Agency of plans for standard permits to be
issued on reduced timescales. We consider that changes on these
lines would be highly desirable but doubt if they will happen
without the changes we recommend to simplify the regulatory framework.
HEALTH AND SAFETY EXECUTIVE
Well design and integrity
207. The Health and Safety Executive
(HSE) monitors onshore oil and gas operations for well integrity
and site safety. Prior to the start of drilling, the operator
must notify the HSE of the well design and operation plans.[439]
The design of wells is regulated by the Offshore Installations
and Wells (Design and Construction, etc.) Regulations 1996 (DCR).
These regulations include specific requirements for all wells,
whether onshore or offshore, and include well integrity provisions
which apply throughout the life of wells.[440]
208. The regulations also require
a well operator to provide HSE with regular reports of any activities
on the well and to appoint an independent well examiner to undertake
regular assessments of well integrity. In addition to the well
examiner scheme, Mr Peter Baker, Director, Hazardous Installations
Directorate at the HSE, told us that wells will get "independent
inspection by HSE well specialists."[441]
HSE and the Environment Agency have agreed jointly to inspect
future hydraulic fracturing operations.[442]
HSE wrote that "for new and first time shale gas operators,
HSE and the Environment Agency will meet and advise them of their
duties under the relevant legislation; and conduct a joint inspection
of the key operations, such as cementing."[443]
The two regulators have a memorandum of understanding which sets
out a framework for how they work together and planning interventions.[444]
Dr Grayling told us that it was "particularly critical
from the point of view of environmental protection that the well
is properly constructed and sealed".[445]
Regulatory regime for shale gas
production phase
209. The regulatory roadmap produced
by DECC covers only the exploration and appraisal phases of shale
gas development. The same permissions and permits described above
will have to be applied for again if operators wish to move into
production.
Effectiveness of the UK regulatory
regime
210. Mr Figueira told us that
in the UK "we certainly have the capability and the regulatory
structure in place to enable the exploratory phase to proceed
in line with industry expectations."[446]
Mr Smith of Shell said that the UK has "a world class
set of regulations".[447]
Mr Dorner from the International Energy Agency (IEA) said
that "internationally, the UK regime as it stands is very
highly regarded".[448]
The IEA published a report in 2012 that set out seven principles
for the development of shale gas that "can allow policymakers,
regulators, operators and others to address these environmental
and social impacts."[449]
Mr Dorner said he "suspected" that the UK regime
already incorporates those principles. Professor MacKay and
Mr Lambert pointed out that drilling for and production of
onshore oil had successfully occurred in the UK at Wytch Farm
for many years.[450]
211. Some witnesses made comparisons
between the UK and US regulatory regimes. The UK Onshore Operators'
Group wrote that the UK regime is "different and significantly
more stringent" than the US regime.[451]
Policy Exchange stated that "much of the regulation of shale
gas in the US occurs at the state level, meaning there can be
significant variations in environmental compliance."[452]
Professor Stevens said that many shale gas operations in
the US have been done with "little environmental impact assessments."[453]
However, Cuadrilla disagreed that regulation was weaker in the
US: "contrary to the popular view, American regulation in
this sector is extremely experienced, intensive and confident."[454]
SLOW PROGRESS OF EXPLORATION TO DATE
212. Mr Egan told us that "physically,
we could drill tomorrow
the thing that takes the longest
time, is the planning and permitting process."[455]
Mr Austin told us that "the level of consultation and
engagement, and the time spent considering applications, has been
considerably longer than what would otherwise have been looked
at as industry best practice."[456]
Dr Grayling told us that since the Government moratorium
on hydraulic fracturing ended in December 2012,[457]
"the Environment Agency have not yet received any permit
applications to undertake hydraulic fracturing."
213. The Committee Clerk wrote to
Mr Egan to ask why Cuadrilla had not submitted any applications
for permits since December 2012. Mr Egan replied that permit
applications for hydraulic fracture and flow test exploration
wells (the appraisal phase) were made in August 2012. These applications
were delayed as Cuadrilla undertook an Environmental Impact Assessment
(EIA) as part of the planning process.[458]
Dr Grayling said there was "no disagreement" with
Cuadrilla on this matter, "an Environmental Impact Assessment
may reveal issues material to our permitting decisions
permitting need not delay operations if operators make
sure that they align their permit applications and submit new
ones."[459]
214. Cuadrilla withdrew the original
permit applications and is expected to submit new ones, alongside
planning applications, for several sites in north-west England
later this year.[460]
In Mr Egan's view it was "perhaps not wholly unsurprising"
that "the timescale involved in delivering these very first
permits of their kind in the UK has been very lengthy."[461]
Dr Grayling told us that the Environment Agency is "going
through a learning exercise as an agency, while the industry was
also going through a learning exercise on how to apply for the
appropriate permits."[462]
215. There is no indication as to
how long the whole regulatory process would take. DECC's regulatory
roadmap explicitly states that "the roadmap does not define
timescales for the planning and permitting process or individual
steps within it."[463]
It advises operators to contact the relevant regulatory authorities
to establish indicative timelines. The table below summarises
the timescales that we have been made aware of for each stage:
TABLE 2
Indicative Timescales
Stage
| Length of time
|
DECC
|
Issue of PED licence
| Granted through licensing rounds
|
Environmental risk assessment
| No indication given
|
Approval of hydraulic fracturing plan
| No indication given
|
Consent to drill
| No indication given
|
Local authorities
|
Planning permission[464]
| 21 day consultation[465]
16 weeks if EIA required, 13 weeks if not[466]
|
Environmental Impact Assessment (EIA)
| |
Agree plan for site restoration
| |
Environment Agency
|
Notice of intention to drill
| Served 1 month prior to drilling[467]
|
Environmental permits[468]
| 13 weeks to 26 weeks[469]
|
Health and Safety Executive
|
Notice of intention to drill
| Served 21 days prior to drilling[470]
|
216. Table 2 above lists the stages
in the regulatory process that are described above and provides
indicative timescales where available. As no operator has been
through the whole process since the publication of the regulatory
roadmap, it is not clear how long the various stages, or the whole
process, would take in practice. There could also be delays if
planning and permitting decisions where subject to legal challenge.
217. Figure 13 below shows how the
regulatory process looks to industry. It outlines Cuadrilla's
view of the expected timescales for certain stages, including
the requirements of Environmental Impact Assessments.
FIGURE 13
Cuadrilla's view of key steps
and associated timelines
Key Steps and Timeline in Securing Approvals to Drill, Hydraulically Fracture and test the flow rate from a Shale Gas Exploration Well
The high level timeline tabulated below is for securing a Planning Consent only and assumes that an exploration site has already been identified.
In parallel with applying to the County Council for a Planning Consent the applicant will also apply to the Environment Agency for up to 8 or 9 separate Environmental Permits required for the drilling, hydraulic fracturing and testing the flow of gas from an exploratory shale well. It is assumed that from a timing perspective this is carried out within the minimum 16 month period outlined below required to secure a Planning Consent.
Activity
Duration
Commentary
1) Complete all surveys required for an Environmental Impact Assessment (EIA), e.g. Newts, Wintering Birds, Bats, Traffic, Noise etc.
Approx. 6 months
Certain surveys can only be carried out at particular times of year (e.g. Wintering Birds)
2) Complete EIA and associated Planning Application (including getting an EIA Scoping Opinion from the County Council and carrying out pre-application consultation with local communities and stakeholders)
6 months (some overlap possible with step 1 above, incremental time assumed to be 3 months)
EIA Scoping opinion from Council typically 5 to 6 weeks. Pre application consultation process typically 3 to 4 months
3) Submit Planning Application and associated EIA to County Council. Council consults with statutory consultees and decides.
Minimum of 4 months for an EIA planning application.
Council should respond in 16 weeks from application but can take longer.
4) Fulfil any associated planning conditions (if application approved)
Typically 1 month
Conditions could include widening road access or other such provisions
5) Prepare Exploration site (foundation, drainage, security etc.) and mobilise drilling equipment
2 months
Start Drilling
16 months later
Note: it is possible that a successful Planning consent and/or Environmental Permit application could be subjected to a Judicial Review (JR) challenge. The JR process could add approx. 12 months to above timeline, post the completion of step 3.
|
Source: Cuadrilla Resources Limited
IS THE UK REGULATORY REGIME EFFECTIVE?
218. Asked whether he would invest
in the UK at the moment, Mr Wright said that "if you
had rigorous but crisp and clear environmental regulations, and
you had a way to align the community and move quickly, I would
do it in a heartbeat, but that is not there today
If the
business climate was here, it would happen."[471]
He said that "certainty to move quickly" was required.[472]
Mr Egan said that if the UK was to move into a production
phase, the regulatory regime "will require a step change
in the pace and scale of operation."[473]
219. Mr Hughes said "objectively
the regulation regime
is probably okay"; but local
residents did not have confidence because "the industry has
done a lousy job of providing the reassurance that is necessary
the industry is not gaining the benefit of the doubt
the regulatory machine probably has to go beyond what is objectively
required in order to win that confidence back."[474]
He told us that there is "probably a need for a step up in
the regulatory regime, and one that is communicated in such a
way that it will reassure them."[475]
220. The UK's regulatory framework
for onshore exploration and production applies to conventional
as well as shale gas and oil. There is no special regime for shale
gas and oil, except that extra rules govern hydraulic fracturing.
Applicable regulations in the UK are rigorous and thorough and
address the environmental and health risks. We heard that they
are well respected internationally. We were also told of measures
to improve coordination in the system so as to deal more effectively
with development of shale gas and oil.
221. The regulatory framework
is however unnecessarily complicated, with responsibilities shared
between various Departments and agencies. Wytch Farm apart, it
has no track record of dealing with large scale onshore operations.
Bureaucratic complexity and diffusion of authority are not the
best basis for clear and effective regulation of a new and fast-evolving
industry. It is not clear how long the whole regulatory process,
or its various stages, would take. We set out recommendations
below to reduce the complexity and increase the transparency of
the regulatory regime.
Reducing the complexity and increasing
the transparency of the regulatory regime
REDUCING THE COMPLEXITY OF THE REGULATORY REGIME
222. The Royal Society and Royal
Academy of Engineering report into shale gas recommended that
a single body should take the lead for regulatory responsibilities
relating to shale gas.[476]
Professor Mair told us that at present, "there is DECC,
there is HSE, there is the Environment Agency. We said that there
should be one organisation that oversees the whole process."[477]
Duarte Figueira said that DECC set up the Office of Unconventional
Gas and Oil in March 2013 to "provide exactly the sort of
coordinated approach that was recommended in the Royal Society
report, so there was clarity on the roles and responsibilities
of different regulators".[478]
The Minister for Energy told us that following the publication
of the regulatory roadmap in December 2013, "the system is
now crisp and clear."[479]
Regrettably, however, that is not the case.
223. Despite the introduction of
the Office of Unconventional Gas and Oil and the regulatory roadmap,
responsibilities are still fragmented. For example, DECC must
approve operators' plans to mitigate the risk of induced seismicity;[480]
the Environment Agency approve operators' plans for air emissions
to mitigate the risk to public health;[481]
and the Health and Safety Executive monitor well integrity that
mitigates the risk of groundwater contamination.[482]
Although the Environment Agency and Health and Safety Executive
intend to carry out joint well inspections; the EA will be assessing
the risk to the environment, the HSE the risk to health and safety.[483]
224. There are also significant
levels of duplication. For example, operators must discuss plans
to mitigate the risk of groundwater contamination in four different
contexts:
· the environmental risk assessment
required by DECC;[484]
· the Environmental Risk Assessment
required by the Minerals Planning Authority;[485]
· an application to the Environment
Agency for a groundwater permit;[486]
· and the Health and Safety
Executive will ultimately review the design of wells to ensure
that nothing can escape into aquifers.[487]
225. Some witnesses questioned whether
the individual regulators had sufficient resources to manage when
activity increases. Mr Parr said his question was "whether
they have the capacity to manage the sort of expansion that is
being proposed and to develop whole new areas of understanding
and expertise".[488]
The Environment Agency was of particular concern. Mr Bennett
told us that "there are already very significant concerns
about a lack of capacity within regulators like the Environment
Agency to even deliver on their current expectations".[489]
Professor Smythe wrote that "the weakest point of the
regulatory process concerns the Environment Agency" and said
they appear to have "insufficient in-house expertise".[490]
It was reported earlier this year that the total number of staff
at the Environment Agency was to be reduced from 11,250 to around
9,700 by October 2014.[491]
226. The Minister for Energy said
that "we are always looking to see, in the regulatory process,
where there is the possibility to reduce intervals and to streamline
and avoid overduplication."[492]
However, he did not believe that setting up a new body would make
regulation easier.[493]
His concern was "not just the time that it would take to
set it up, but that people might feel that it was completely pro
any kind of development."[494]
INCREASING THE TRANSPARENCY OF THE REGULATION REGIME
227. As discussed in Chapter 7,
groundwater contamination through a failure of well integrity
is a significant risk for all onshore oil and gas drilling. That
risk is low as long as wells are properly constructed and sealed
and the regulations on well design and integrity are rigorously
enforced.[495] Mr Cronin
said that "we have a very strict regime for well integrity
in this country. It is sufficiently more stringent than the US's."[496]
Discussing well integrity, Mr Austin told us that "the
UK has gold standards throughout the North Sea, which
are
the same standards that are applied onshore
So this is
not us policing ourselves but a well established regulatory system
that is being applied to an established industry".[497]
228. However, Ms Rothery told us
that "there are no actual onshore regulations
[the
regulations that apply] are based on offshore regulations."[498]
Mr Michael Hill wrote that "there is a clear need of
specific onshore industry specific regulations. At present there
are none."[499]
Mr Petts disagreed, "I think it is wrong to say that
there are no onshore regulations
It is covered through
lots of our existing legislation."[500]
Describing the Offshore Installations and Wells (Design and Construction,
etc.) Regulations 1996, he said "it is a mistake in the way
the regulations were titled
there is a lot of regulation
out there
it is just a bit clunky and disjointed, or appears
that way to people who are not familiar with it."[501]
Wytch Farm, for example, is an outstandingly successful large
onshore oilfield regulated under the existing system.
229. Mr Hill told us that the
Offshore Installations and Wells (Design and Construction, etc.)
Regulations 1996 were "aimed at offshore development"
and the Borehole Sites and Operations Regulations 1995 were introduced
prior to high volume hydraulic fracturing.[502]
Professor Riley said that
"the entire approach to oil and
gas has been focused on offshore. Recalibrating for onshore will
be a major task
The problem is not the focus on fracking
but the traditional oil and gas problems: security of the wellhead
and ensuring that flow-back waters cannot seep into the ground.
All this is known to the regulators, but we have never had to
deal with it on any scale onshore."[503]
230. The Offshore Installations
and Wells (Design and Construction, etc.) Regulations 1996 only
require the well operator and well examiner to take account of
the risk to "the health and safety of persons" when
designing and examining a well.[504]
They are not required to take account of the risk to the environment
which is likely due to the original focus of the Regulations on
offshore development. The Royal Society and Royal Academy of Engineering
report recommended that the scheme "should be widened so
that well integrity is also considered from an environmental perspective.
Wider expertise within or outside the oil and gas sector may need
to be drawn upon."[505]
231. We agree with the Royal
Society and the Royal Academy of Engineering that a single body
to regulate onshore development of shale gas and oil would be
desirable in principle. We fear, however, that the necessary reorganisation
would cause delays. We therefore recommend a more coordinated
and responsive regulatory approach within the existing framework,
with a lead regulator identified by the Government, following
the five principles of good regulation advocated by the Better
Regulation Task Force and adopted by the present Government:
Transparent
"Regulators should be open and
keep regulations simple and user-friendly"[506]
We recommend that the Government
should consolidate the applicable provisions in the confusingly
titled and potentially misleading Offshore Installations and Wells
Regulations and Borehole Sites and Operations Regulations into
one clearly labelled set of regulations for onshore oil and gas
operations.
As recommended by the Royal Society
and Royal Academy of Engineering, the consolidated regulations
should specify that well integrity is to be considered from an
environmental perspective as well as a health perspective. The
Environment Agency and Health and Safety Executive should make
it much clearer to the industry and the public exactly how and
when they would inspect well sites.
Accountable
"Regulators must be able to justify
decisions, and be subject to public scrutiny
There should
be well-publicised, accessible, fair and effective complaints
and appeals procedures"[507]
The Government should provide a single,
clear appeals process for operators in the event that an application
for planning permission is refused by a local authority.
Proportionate
"Regulators should only intervene
when necessary. Remedies should be appropriate to the risk posed,
and costs identified and minimised
Policy solutions must
be proportionate to the perceived problem or risk and justify
the compliance costs imposed"[508]
Operators are often required to submit
the same information to different regulators. The Office of Unconventional
Gas and Oil should provide a single point for data input to remove
duplication and reduce costs for operators.
Consistent
"Government rules and standards
must be joined up and implemented fairly"[509]
The Government should ensure that
operators are able to make all the required planning and permit
applications in parallel, in order to speed the process. There
is room for much greater coordination, particularly in relation
to information sharing between local authorities and the Environment
Agency.
Targeted
"Regulation should be focused on
the problem, and minimise side effects"[510]
A targeted approach by the regulators
should include a clear timetable for decision-making, agreed beforehand
with the operators.
INDEPENDENT WELL EXAMINERS
232. The Offshore Installations
and Wells (Design and Construction, etc.) Regulations 1996 require
the design and construction of onshore wells to be examined by
an "independent and competent person".[511]
This well examiner is commissioned and paid for by the operator.
The Regulations do not prohibit the well examiner being an employee
of the well operator's organisation."[512]
233. The Royal Society and Royal
Academy of Engineering report recommended that the guidelines
should be clarified to ensure that the well examiner is independent
of the operator.[513]
Professor Mair told us they "expressed strong views"
on this in the report: "In some cases, under existing practice,
that well examiner can be an employee of the operator's organisation.
We felt that that was undesirable and that the well examiner should
be truly independent."[514]
Ms Rothery said of the well examiner scheme that "to us that
is not regulation; that is self-regulation."[515]
234. Mr Baker said "it
is right that operators have the option of using someone they
directly employ
it does not necessarily follow that having
your own people do third-party verification is a bad thing."[516]
The Secretary of State for the Environment, Food and Rural Affairs
thought that the existing regime had already proved itself, "we
should not devalue what we have achieved."[517]
235. We recommend that regulations
should make explicit that the well examiner for onshore oil and
gas operations should be independent of the well operator.
ABANDONED WELLS
236. Following abandonment of a
well, mineral planning authorities are responsible for ensuring
proper restoration and aftercare of a site through imposition
of suitable planning conditions.[518]
Operators are required to notify the Health and Safety Executive
of the abandonment. The HSE would receive weekly reports of the
abandonment process and it would be reviewed by the well examiner.
Unless there is unusual or adverse development during the abandonment
process, no subsequent monitoring is required. The operator remains
liable for the well and is expected to remedy any subsequent problems.[519]
237. The main risk from an abandoned
well arises from a subsequent sealing failure that allows methane
or other contaminants to enter groundwater. Dr Grayling said
that operators have to develop a "closure and rehabilitation
plan and they have to implement it before they can surrender their
environmental permits to us."[520]
The Secretary of State for the Environment, Food and Rural Affairs
said that "Permits will not be issued if there is an unsatisfactory
programme at the end of the life of the well
there is absolutely
no question of cutting corners at the end of a well's life".[521]
He confirmed that he thought concerns over abandoned wells were
"groundless."[522]
238. Professor Davies said
that the UK had around 2,100 wells onshore already, drilled from
1902 to the present day: "we have gone looking for the wells,
and you cannot physically put your hands on about 65 per cent
of them. That means they would be difficult to monitor."[523]
Operators today are required to submit plans for well abandonment
and DECC has a database that documents the location of wells.[524]
However, once a well has been abandoned there are currently no
requirements for continuous monitoring arrangements. The Royal
Society and Royal Academy of Engineering report said that
"monitoring arrangements should
be developed to detect possible well failure post abandonment
continuous ground gas monitoring and aquifer sampling could
be similar to that carried out before and during fracturing operations
Monitoring would be at a reduced frequency, perhaps every
few years."[525]
239. Sir David King said that
the "major problem" was the "orphaned wells for
which no company is responsible any longer."[526]
The Royal Society and Royal Academy of Engineering recommended
that "consideration should be given to establishing mechanisms,
such as a common liability fund, to ensure funds are available
to respond to well failure post-abandonment in the case that the
operator can no longer be identified."[527]
Dr Grayling said that there were "live discussions between
the Office of Unconventional Gas and Oil and the industry to develop
appropriate arrangements."[528]
240. We recommend that, as proposed
by the Royal Society and Royal Academy of Engineering, rules should
be introduced to monitor wells abandoned in future, and a common
liability fund established by the industry in case of default
by an operator.
European developments
EUROPEAN COMMISSION UNCONVENTIONAL HYDROCARBONS INITIATIVE
241. The European Commission recently
reviewed the European legislative framework for unconventional
hydrocarbon extraction which includes shale gas. This legislative
framework comprises a number of environmental Directives which
are already applicable in the UK. Mr Alan Seatter, Deputy
Director General, Environment, European Commission, told us that
the Commission's objective
"is to enable the safe production
of shale gas by addressing two factors. The first is the degree
of public acceptance
the second
does the framework
provide a clear and predictable framework for investors in this
industry
Those are the objectives that we have put forward
consistent
with our overall climate change objectives."[529]
He said that there was "a public
perception
of a certain number of risks
our legislation
already covers those
we have to be very clear to the public
about whether those risks can be managed adequately by this legislation
so that people feel reassured that it is possible to have safe
extraction of shale gas."[530]
242. The Commission adopted a Recommendation[531]
in January 2014 which sets out a number of minimum principles
that Member States are "invited to give effect to."[532]
On the whole, the UK regulatory regime appears to incorporate
the minimum principles. A possible exception is Recommendation
9.2(e) which says Member States should ensure that operators,
"ensure well integrity through
well design, construction and integrity tests. The results of
integrity tests should be reviewed by an independent and qualified
third party to ensure the well's operational performance, and
its environmental and health safety at all stages of project development
and after well closure."[533]
As discussed above, well examiners in
the UK do not have to be independent of the operator and the current
regulations only take account of the risk to health and not the
environment.[534] That
is why we recommended at paragraph 235 above that regulations
should make explicit that the well examiner for onshore oil and
gas operations should be independent of the well operator.
243. The Secretary of State for
the Environment, Food and Rural Affairs told us that he thought
in respect of the minimum principles, the UK is "well covered."[535]
In an explanatory memorandum setting out DECC's position on the
Recommendation, the Minister for Energy said that "we already
in the UK practice or require much of what is recommended."[536]
244. Before publication of the Recommendation,
there were fears from Government and the industry that the Commission
would propose new legislation. The Minister for Energy said that
"We have been arguing very strongly that there is no need
for further European legislation in this area".[537]
Mr Figueira told us that "we must ensure that EU action
is proportionate and does not result in new regulation in the
industry that is not required
we want to get the exploration
phase away as soon as possible".[538]
Mr Cronin said that the UK industry "does not really
want any further regulation
additional regulation will
not improve public perception but the enforcement of the current
regulation will."[539]
245. Mr Seatter told us that
"we have never had in mind coming out with some beautifully
comprehensive thing that is going to take a very long time to
discuss and decide
we are talking about principles and
standards, not detailed provisions".[540]
However, the Recommendation said that the Commission will review
its effectiveness in 18 months and as part of that review, "will
decide whether it is necessary to put forward legislative proposals
with legally-binding provisions on the exploration and production
of hydrocarbons using high-volume hydraulic fracturing."[541]
DECC thought that the 18 month timetable was "likely to be
insufficient to enable the Commission to undertake an evidence-based
assessment."[542]
ENVIRONMENTAL IMPACT ASSESSMENT DIRECTIVE
246. The Environmental Impact Assessment
Directive requires environmental impact assessments to be carried
out for projects that are likely to have significant effects on
the environment. The Commission proposed a revision to the Directive
in 2012.[543] The main
objectives of the revision were to simplify the assessment process
and enable the process to reflect emerging challenges like climate
change. The European Parliament used the opportunity of the revision
to propose an amendment that would add shale gas operations to
the list of projects requiring a mandatory assessment.[544]
A blocking minority of Member States in the Council of the EU
(including the UK) would not agree to the Parliament's amendment
and were successful in December 2013 in preventing the amendment.[545]
247. We agree with the Government
that there is no need for new European legislation on shale gas.
248. The regulatory framework
governing development of shale gas in the UK is dauntingly complex
and largely untested. Industry, public and even regulators seem
uncertain how it would apply in practice. No single body has clear
lead responsibility. We do not believe there is any trade off
between speed and rigour in the regulatory process; complexity
does not increase the quality of regulation. Unless the Government
act to streamline the system so that regulation is effective as
well as rigorous, the UK will be unable to take full advantage
of the economic opportunity offered by shale gas.
403 Better Regulation Task Force (2003) Principles
of Good Regulation. Back
404
See https://www.gov.uk/government/policy-teams/better-regulation-unit
Back
405
DECC (2013) Onshore oil and gas exploration in the UK: regulation
and best practice, 17 December. The roadmap does not cover
the production phase. Back
406
This chapter outlines the regulatory regime for England since
this is where exploration is expected to take place first. DECC
have produced separate roadmaps for the regulatory regimes in
Scotland, Wales and Northern Ireland. The Roadmap for each regime
is available here: https://www.gov.uk/government/publications/regulatory-roadmap-onshore-oil-and-gas-exploration-in-the-uk-regulation-and-best-practice
Back
407
Petroleum Act 1998, section 2(1) and 2(2). In Northern Ireland,
ownership of petroleum is vested in the Ministry of Commerce under
the Petroleum (Production) Act (Northern Ireland) 1964, section
1(1). Back
408
DECC (2013) Onshore oil and gas exploration in the UK,
Op, Cit. Back
409
Most local authorities do not consider that seismic investigations
require planning permission. Operators must notify landowners,
planning authorities and DECC if they plan to conduct seismic
surveys in the licence area. Back
410
DECC (2013) Onshore oil and gas exploration in the UK,
Op, Cit. Back
411
Ibid. Back
412
Ibid. Back
413
Separate applications are required for each stage. Applications
for both stages can be made within one application. Back
414
Department for Communities and Local Government (2014) Planning
Practice Guidance: Minerals, 6 March. See http://planningguidance.planningportal.gov.uk/blog/guidance/minerals/
Back
415
Town and Country Planning Act 1990, section 78 Back
416
DECC (2013) Onshore oil and gas exploration in the UK,
Op, Cit. Back
417
Department for Communities and Local Government (2014) Planning
Practice Guidance, Op, Cit. Back
418
Department for Communities and Local Government (2014) Planning
Practice Guidance, Op, Cit. Back
419
Ibid. Back
420
QQ 72-73. Back
421
Q 159. Back
422
Department for Communities and Local Government (2014) Planning
Practice Guidance, Op, Cit. Back
423
Environment Agency (2013) Onshore oil and gas exploratory operations:
technical guidance, Consultation Draft August 2013. Back
424
DECC (2013) Onshore oil and gas exploration in the UK,
Op, Cit. Back
425
Unless the EA is satisfied that there is no risk of inputs to
groundwater. Back
426
Likely to apply in all circumstances. Back
427
When the operator intends to flare more than 10 tonnes of gas
per day. Back
428
Likely to apply in all circumstances. Back
429
If surface water runoff becomes polluted. Back
430
To cover drilling and test pumping where there is the potential
to abstract more than 20m3/day in the production process. Back
431
If the operator plans to abstract more than 20m3/day
for own use rather than purchasing water from a public water supply
utility company. Back
432
If the proposed site is near a watercourse or main river. Back
433
Q 272. Back
434
Environment Agency (2013) Onshore oil and gas exploratory operations,
Op, Cit. Back
435
Q 155. Back
436
Environment Agency (2013) Onshore oil and gas exploratory operation',
Op, Cit. Back
437
Q 272. Back
438
Q 273. Back
439
Borehole Sites and Operations Regulations 1995, section 6. Back
440
Health and Safety Executive. Back
441
Q 162. Back
442
Health and Safety Executive. Back
443
Ibid. Back
444
Q 154. Back
445
Q 181. Back
446
Q 156. Back
447
Q 110. Back
448
Q 107. Back
449
International Energy Agency (2012) Golden Rules for a Golden
Age of Gas. Back
450
Q 204 & Q 212. Back
451
UKOOG. Back
452
Policy Exchange. Back
453
Professor Paul Stevens. Back
454
Cuadrilla Resources Limited. Back
455
Q 76. Back
456
Q 77. Back
457
Q 159 and see paragraph 75. Back
458
Cuadrilla - Supplementary correspondence with Committee Clerk. Back
459
Environment Agency - Supplementary correspondence with Committee
Clerk. Back
460
Q 273. Back
461
Cuadrilla - Supplementary correspondence with Committee Clerk. Back
462
Q 273. Back
463
DECC (2013) Onshore oil and gas exploration in the UK,
Op, Cit. Back
464
Operators are encouraged to make parallel applications for planning
permissions and environmental permits. Back
465
See paragraph 201. Back
466
Ibid. Back
467
Environment Agency (2013) Onshore oil and gas exploratory operations,
Op, Cit. The EA recommends that drilling should not begin
until one month after notice is served. If the EA does not consider
the information received with the notice to drill sufficient,
it can serve a notice on the operator requesting more information. Back
468
Ibid. Back
469
See paragraph 205. Back
470
DECC (2013) Onshore oil and gas exploration in the UK,
Op, Cit. The HSE must be satisfied by the proposed design
of the well. Back
471
Q 231. Back
472
Q 233. Back
473
Q 202. Back
474
Q 202. Back
475
Q 201. Back
476
Mair, R. et al (2012) Shale gas extraction in the UK: a review
of hydraulic fracturing, Royal Society and Royal Academy of
Engineering. Back
477
Q 73. Back
478
Q 154. Back
479
Q 256. Back
480
See paragraph 196. Back
481
See paragraph 204. Back
482
See paragraph 207. Back
483
See http://www.hse.gov.uk/aboutus/howwework/framework/aa/hse-ea-oil-gas-nov12.pdf
for the November 2012 memorandum of understanding between the
Environment Agency and the Health and Safety Executive. Back
484
See paragraph 195. Back
485
See paragraph 200. Back
486
See paragraph 204. Back
487
See paragraph 207. Back
488
Q 36. Back
489
Q 37. Back
490
Professor David Smythe. Back
491
BBC News (2014) 'UK flooding: Environment Agency to cut hundreds
of jobs', 3 January. Back
492
Q 258. Back
493
Q 259. Back
494
Ibid. Back
495
See paragraphs 144 to 147. Back
496
Q 62. Back
497
Q 82. Back
498
Q 193. Back
499
Michael Hill. Back
500
Q 193. Back
501
Ibid. Back
502
Michael Hill. Back
503
Q 7. Back
504
Offshore Installations and Wells (Design and Construction, etc.)
Regulations 1996, section 13(1)(b). Back
505
Mair, R. et al (2012), Op, Cit. Back
506
Better Regulation Task Force (2003), Op, Cit. Back
507
Better Regulation Task Force (2003), Op, Cit. Back
508
Ibid. Back
509
Ibid. Back
510
Better Regulation Task Force (2003), Op, Cit. Back
511
Offshore Installations and Wells (Design and Construction, etc.)
Regulations 1996, section 18(2). Back
512
Ibid, section 18(7). The examiner must only be "sufficiently
independent" of a management system which bears or has borne
any responsibility for any aspect of the operations subject to
examination. Back
513
Mair, R. et al (2012), Op, Cit. Back
514
Q 72. Back
515
Q 193. Back
516
Q 162. Back
517
Q 274. Back
518
Department for Communities and Local Government (2014) Planning
Practice Guidance, Op, Cit. Back
519
Q 165. Back
520
Q 276. Back
521
Ibid. Back
522
Ibid. Back
523
Q 129. Back
524
Mair, R. et al (2012), Op, Cit. Back
525
Ibid. Back
526
Q 211. Back
527
Mair, R. et al (2012), Op, Cit. Back
528
Q 277. Back
529
Q 240 Back
530
Ibid. Back
531
Recommendations of the European Commission are non-binding on
Member States Back
532
2014/70/EU: Commission Recommendation of 22 January 2014 on minimum
principles for the exploration and production of hydrocarbons
(such as shale gas) using high-volume hydraulic fracturing. Back
533
Ibid. Back
534
See paragraphs 232 to 235. Back
535
Q 274. Back
536
DECC Explanatory Memorandum on Commission recommendation of 22.1.2014
on minimum principles for the exploration and production of hydrocarbons
(such as shale gas) using high volume hydraulic fracturing, February
2014. Back
537
Q 260. Back
538
Q 173. Back
539
Q 61. Back
540
Q245 and Q249. Back
541
2014/70/EU: Commission Recommendation of 22 January 2014, Op,
Cit. 16.4. Back
542
DECC Explanatory Memorandum on Commission recommendation of 22.1.2014,
Op, Cit. Back
543
See http://ec.europa.eu/environment/eia/review.htm for details
of the review of the Environmental Impact Assessment Directive. Back
544
Q 238. Back
545
Q 248 and see
http://www.europarl.europa.eu/news/en/news-room/content/20131220IPR31634/html/Environmental-impact-assessment-directive-agreement-reached-with-EU-ministers
Back
|