CHAPTER 2: THE COST OF HS2
Cost of construction
21. The Government has made allowance in its
projections for public spending for construction of HS2 of £21.4
billion for Phase One, £21.2 billion for Phase Two and £7.5
billion for rolling stock, a total of £50.1 billion (2011
prices, excluding VAT).[28]
The cost of constructing each phase of the line including contingencies
is set out in the Strategic Case: Table
1: HS2 total allocated funding (£ billion)
| Phase One
| Phase Two
| Rolling stock
| Total
|
Target cost | 17.16
| n/a |
| |
Estimated cost | 15.65
| 12.5 | 5.8
| 33.95 |
Contingency[29]
| 5.75 | 8.7
| 1.7 | 16.15
|
Total
| 21.4
| 21.2
| 7.5
| 50.1
|
Source: Strategic Case, Figure 7.1. Figures in
2011 prices, excluding VAT.
22. The total funding allocated for the construction
of HS2 and purchase of rolling stock of £50.1 billion includes
£16.15 billion contingency as shown above.[30]
Contingency is lower for Phase One as the route is more defined,
enabling a more accurate estimate of the cost. David Prout
of the Department for Transport told us that the Chancellor had
made clear that "the budget is the budget" and that
costs could not exceed the funding envelope of £50 billion.[31]
23. We asked the Rt Hon. Patrick McLoughlin MP,
Secretary of State for Transport, to provide the costs for HS2
in 2014 or 2015 prices. He told us that "in order to ensure
consistency across the programme, we are maintaining the prices
for programme delivery in 2011 prices."[32]
The Department for Business, Innovation and Skills publishes Tender
Price Indices, which measures the movement of prices in tenders
for public sector construction contracts in the UK. This showed
that the cost of public sector construction contracts increased
by 13 per cent between the first quarter of 2011 and the first
quarter of 2014 (the last date for which figures were available).[33]
Applying this increase to the £50.1 billion cost of HS2 would
give a figure of £56.6 billion in 2014 prices.
24. We note that Mr Prout told us that costs
of construction could not exceed the funding envelope of £50
billion. It is not clear whether this refers to the costs in 2011
prices and the funding envelope will expand with inflation, or
whether the cost should not exceed £50 billion in absolute
terms. The Government should make clear whether the absolute
limit for the construction of HS2 will increase in line with inflation.
25. Rt Hon. Lord Adonis, former Secretary
of State for Transport, argued that HS2 was not a £50 billion
project but "a £28 billion project with a 50% contingency";[34]
he suggested that quoting the cost as £50 billion was misleading.
Sir David Higgins, Chairman of HS2 Ltd, cautioned however
that while "you should not assume that contingency will be
spent", it was included for a reason and he did not want
to "suddenly declare that I had found savings." He noted
that use of contingencies would be "rigorously enforced"
in the same way that it had been for the Olympics[35]
and Crossrail projects. In the case of the Olympics:
"It was very clearly set out what those
contingencies were, force-majeure risks or government taxation
policy, or whatever
in the end £1 billion of that
contingency was never spent on the delivery of the venues and
the infrastructure."[36] Box
2: What is the cost of HS2?
In this report we refer to two figures for the cost of HS2:
· £50.1 billion: This figure refers to the expected cost to construct HS2 in 2011 prices and purchase rolling stock (see Table 1) including all contingency.
· £31.5 billion: This figure refers to the net cost of HS2 to the Government of HS2 after 60 years of operation of the full line and includes the cost of construction, operating costs and revenue. The figure is derived by adding the capital cost (£40.5 billion) to the operating cost (£22.1 billion) and subtracting the expected revenue income (£31.1 billion). These figures are present value figures and have been discounted as is standard practice to reflect that people prefer to receive goods and services now rather than later.
|
IS £50 BILLION A REALISTIC ESTIMATE?
26. Some witnesses expressed scepticism that
the cost of constructing HS2 could be kept within £50 billion
(2011 prices). Professor Stephen Glaister noted that
"There are lots of things that may happen between now and
Royal Assent to the hybrid Bill that will change these numbers,
typically, I suspect, adversely."[37]
Dr Richard Wellings of the Institute of Economic Affairs,
also thought there was a "massive cost risk" because
of "interest group pressures" leading to changes to
routes and increases in cost. He estimated that HS2 would cost
a total of £80 billion, which took account of other factors
including "the economic activity that is suppressed by the
extra taxation needs flowing from HS2".[38]
27. The Secretary of State told
us that the Department for Transport had proved it could deliver
projects without cost overruns: "Crossrail has been a fantastic
achievement; it has been delivered on budget and within the estimations
for the next two years on time. That has shown that we have some
tremendous advantages in the delivery on costs."[39]
Sir David Higgins and Simon Kirby, Chief Executive of
HS2 Ltd, were brought in to ensure that the project was delivered
successfully.
28. Sir David Higgins agreed that
"HS2 is a lot of money. We have to prove that we spend it
very wisely." He said that the Construction Leadership Council,
which he co-chaired, had set itself the objective to be achieved
by 2025 of "reducing both the time of construction and the
cost of construction, in each case by 25 per cent in real terms".[40]
Lord Deighton said that Sir David Higgins had been
given the task of looking at how to reduce the cost of construction
of HS2, including by learning from examples from abroad.[41]
Redevelopment of Euston station
29. Several witnesses used the progress of plans
for the redevelopment of Euston station as an example of how costs
were already at risk of running over budget, although no money
has yet been spent on the redevelopment. HS2 Action Alliance
told us that there had been reports that the estimated cost of
the redevelopment of Euston had risen to £7 billion from
the £2 billion quoted in the Economic Case for HS2.[42]
Mr Prout said that the development of Euston was not over budget:
"We are simply taking time to reflect on
what we are proposing to make sure that what we are doing forms
part of a bigger jigsaw puzzle for the whole of Euston station
if a decision is taken in due course to rebuild the rest of the
station."[43]
30. An HS2 station at Old Oak Common, located
in West London three miles west of Paddington station, has been
proposed as part of plans for HS2 to provide an interchange between
HS2 and Crossrail. It has been suggested that the possibility
of overruns at Euston has led to consideration of terminating
HS2 at Old Oak Common.[44]
This would avoid the cost of developing Euston station and of
a tunnel from Old Oak Common to Euston. When we put this suggestion
to Mr Prout he said that terminating at a central London station
was "an essential part of driving demand on HS2. The capital
investment required would not justify terminating [at] a station
out at Old Oak Common."[45]
Alison Munro, Managing Director of Development, HS2 Ltd, said
that one-third of HS2 passengers travelling to London would choose
to use Old Oak Common so "If you stopped the trains at Old
Oak Common that would be a disbenefit to two-thirds of people."[46]
31. The Government should estimate the overall
reduction of cost to HS2 of terminating the line at Old Oak Common
(in the London Borough of Hammersmith and Fulham), including any
necessary redesign of the station at Old Oak Common to make this
possible, and calculate the effect on the cost benefit analysis.
32. We consider other options for the terminus
in London in Chapter 6.
LEARNING FROM ABROAD
33. The cost of construction of high speed lines
in France has been much lower than the construction costs expected
for HS2. A report of the French Cour des Comptes (the French equivalent
of the National Audit Office) on the construction of high speed
lines in France said that: "In 2014, the French TGV network
is 2,036 km long and was developed for a cost of over 23
billion [in 2010 prices]."[47]
The report collated the information on construction and length
of TGV lines in France: Table 2: Cost
of construction of main high speed lines in France
Line
| Date completed
| Length (km)
| Cost (m, 2010 prices)
| Cost per km (m, 2010 prices)
| Cost per km (£m, 2010 prices)[48]
|
LGV Paris-Lyon | 1983
| 380 | 2,079
| 5.5 | 4.7
|
LGV Atlantique | 1990
| 285 | 2,972
| 10.4 | 8.9
|
LGV Nord | 1993
| 350 | 3,767
| 10.8 | 9.3
|
L'interconnexion Nord-Sud
| 1996 | 102
| 1,579 | 15.5
| 13.3 |
LGV Rhône-Alpes |
1994 | 106
| 1,425 | 13.4
| 11.5 |
LGV Méditerranée
| 2001 | 250
| 4,929 | 19.7
| 16.9 |
LGV East | 2007
| 299 | 4,702
| 15.7 | 13.5
|
LGV Rhin-Rhône |
2011 | 148
| 2,588 | 17.5
| 15.0 |
Source: Cour des Comptes, La Grande Vitesse Ferroviaire:
un modèle porté au-delà de sa pertinence
rapport public thématique, pp 19-21
34. Taking the target price of Phase One (there
is no target price for Phase Two) of £17.16 billion (excluding
contingency, 2011 prices) and its length as the commonly reported
192 kilometres, HS2 Phase One will cost around £90 million
per kilometre.
35. Mr Prout told us that for HS2 the Government
have targeted cost of "£43 million per mile".[49]
The cost of construction for HS1 (the Channel Tunnel to Kings
Cross link) in 2011 prices was £37.6 million per mile.[50]
A direct comparison with costs in other countries such as France
is not straightforward as HS2 requires expensive tunnelling and
includes the cost of a new station at Birmingham and renovation
of Euston station while no stations are included in the French
costs. Sir David Higgins suggested to the House of Commons Transport
Select Committee that the UK could not "hide behind the idea
that our country is much more densely populated than France"
as the reason for why it was more expensive to build high speed
lines in the UK.[51]
36. We asked Sir David Higgins why
costs of construction were lower in France and what could be learned
from experiences abroad to reduce the cost of constructing HS2.
He told us that access to the track and planning constraints were
"the reason the costs here are substantially higher."
Sir David said that a team had considered the lessons from
the construction of the Tours to Bordeaux TGV line in France.
They had found that "rigorous planning, just in time construction
where you look at the logistics and you plan for that in advance,
can deliver substantial savings in all construction sectors."[52]
37. The expected cost of construction per
mile of HS2 is up to nine times higher than the cost of constructing
high speed lines in France. This is too high. Were HS2 proceeded
with, we welcome the Government's and Sir David Higgins'
commitment to learning from international examples to reduce this
cost.
The UK construction industry
38. The state of the UK railway construction
industry was also cited by Sir David as a reason why constructing
railway lines in the UK was so expensive. He described the industry
as "fragmented, low-cost, low-margin, buying on the lowest
common denominator, not investing in long-term skills". This
was in contrast to "the big Spanish, German or French multidiscipline
contractor companies that have strong revenue streams from owning
airports or telecommunications companies" who invested in
research and development and skills.[53]
39. The Department for Transport acknowledged
in their written evidence that the UK had "a skills gap in
railway engineering and advanced construction" and that a
recent report had identified "a need to substantially increase
the supply of engineers in the UK." They said that an HS2
skills college would be set up to complement existing work to
meet the skills gaps and help to deliver a UK workforce equipped
for the future.[54]
40. HS2 Ltd told us in written evidence how this
college would focus on "designing and delivering the high
level skills needed for high speed rail, and other major engineering
projects of the future." They said that their contractors
had already given more than 700 graduate trainees or apprentices
the experience of working on HS2 and expected that HS2 would lead
to a further 2,000 apprenticeships in construction alone. This
would "create a lasting legacy for the UK as a country that
can deliver major infrastructure projects." [55]
41. Other witnesses were not so confident that
UK industry would be the main beneficiary of the construction
of HS2. HS2 Action Alliance said that as the UK had "no indigenous
high speed rail industry" much of the technology required
for the railway would be imported from foreign manufacturers.[56]
William Avery, a private individual, agreed that "the UK
construction industry is reaching full capacity so the only effect
of HS2 will be the importation of resources to achieve the construction
and mostly focused in the south east which needs it the least."[57]
42. We are concerned to learn that the UK
construction industry does not have the capability to deliver
a project of the scale of HS2. A national transport strategy that
envisages steady investment in the UK's transport infrastructure,
whatever the project, may help the UK develop a construction industry
capable of delivering large infrastructure projects and competing
internationally.
Cost of complementary projects
43. HS2 could prompt a number of complementary
transport projects designed to maximise the benefits of HS2, which
are not included within the anticipated cost. Witnesses suggested
that these projects meant that the budget that would be funded
by the Government and local authorities would be far higher than
the funding announced for the construction of HS2.
CROSSRAIL 2
44. Crossrail 2 (a new line proposed to run from
north to south across London) was cited as a project which was
separate from HS2 but would be required if HS2 was built. Michèle Dix,
Managing Director, Planning, at Transport for London, told us
that Crossrail 2 "needs to be in place before phase two of
HS2 is completed" as "we will need additional Underground
capacity in the form of Crossrail 2 to help with that dispersal."
However, she made clear that Crossrail 2 was needed regardless
of HS2, so was being progressed independently. The total cost
of Crossrail 2 was expected to be £27 billion including rolling
stock and contingency.[58]
OTHER COMPLEMENTARY PROJECTS
45. Mr Prout told us that the costs for
HS2 included "All the infrastructure that is required to
allow HS2 to run on the dedicated line and the train-service specifications
for the classic lines" and deliver all of the economic benefits
set out in the economic case.[59]
In response to our question about what the total cost of HS2 and
all complementary projects would be, Lord Deighton said that:
"The existing justification of the business
[case] is based on what is in the budget. When we talk about all
these other things we are simply saying, 'We have a strategy.
HS2 is part of the strategy. There will be many other components
to the strategy that will need funding too', and it clearly makes
sense when you spend money in the future to link it to the things
you already have. So I think it is slightly dangerous to try to
create an accumulated cost."[60]
46. Rt Hon. Cheryl Gillan MP,
Member of Parliament for Chesham and Amersham, told us that "the
cost of regional economic and transport spending necessary to
realise the wider benefits should also be included in the BCR
[benefit-cost ratio] but it is not."[61]
Councillor Martin Tett, Leader of Buckinghamshire County
Council and speaking on behalf of the 51M Alliance, said that
"If you just substitute for 'realising the benefits', 'additional
costs because of', then you actually have the reality behind it."[62]
47. Other witnesses noted that these additional
projects brought their own benefits which were not included within
the cost-benefit analysis of HS2. Jim Steer of transport
consultancy Steer Davis Gleave said that "all of this will
also bring its own benefits
You need a really efficient,
bigger-capacity transport system, which is what HS2 provides,
and you need these other things too; they create joint benefits."[63]
Professor Roger Vickerman, Professor of European Economics,
University of Kent, acknowledged that defining how to classify
the costs and benefits of these related projects was problematic:
"how much of that is part of the cost of the project and
how much is the benefits?"[64]
The effect of speed on the cost
48. HS2 will be built to accommodate trains travelling
at a maximum speed of 400 kilometres per hour (250 mph), although
it is initially expected that trains will only run at a maximum
of 360 kph (225 mph) on the line. This compares to a maximum speed
of 300 kph (185 mph) on HS1.[65]
Tables 3 and 4 shows the maximum speed of high speed trains in
the UK and other countries. Table 3:
Maximum speed of high speed trains in UK
| HS1 (Channel Tunnel to Fawkham Junction)
| HS1 (Ebbsfleet to St Pancras)
| HS2 (planned)
|
Speed (kph) | 300
| 225 | 400[66]
|
Source: Letter from David Prout to the Chairman,
7 January 2015 Table 4: Maximum
speed of high speed trains in selected countries (kilometres per
hour)
| China
| France
| Germany
| Italy
| Spain
| Japan
| US
|
In operation | 350[67]
| 320 | 300
| 300 | 300
| 320 | 240 (300)[68]
|
Source: UIC High Speed Department, High Speed Lines in the World
(September 2014):
http://www.uic.org/IMG/pdf/20140901_high_speed_lines_in_the_world.pdf
49. Several witnesses argued that the proposed
ultra-high speed of HS2 added a great deal to the cost. Stop HS2
said in written evidence that the "unjustified design speed
reduces both connectivity and capacity, and removes the
possibility to run heavy freight on the new line. It also
means the line has to be straighter than a conventional railway,
increasing the effect on communities, woodlands and habitats."
It continued "a conventional speed railway would mean lower
cost to build and run, greater connectivity, more freight paths,
greater versatility."[69]
Witnesses also suggested that a lower speed would allow for a
different route configuration. This is explored in further detail
in Chapter 5.
50. Other witnesses argued that the line should
be built with the flexibility to take advantage of future advances
in technology. Mr Steer described it as a "bit of a
non-issue" and asked "Why would you not build in a bit
of flexibility for uplift in technologies?"[70]
Bridget Rosewell of Volterra Consultants agreed that if the
line was not built to accommodate higher speeds to provide the
flexibility if required "technology regret is where you might
end up. The East Coast Main Line electrification was done about
30 years ago and it was done on the cheap, and as a result we
are regretting it."[71]
51. Mr Prout told us that "the additional
cost of designing to a 400 kilometres per hour capacity as opposed
to conventional railway is roughly 9 per cent." He did not
accept that designing for a lower speed might allow a different,
lower cost route:
"The alignment that we have chosen is to
minimise the environmental impact of the railway
Where
you save money on slower speeds is on things like tunnel size,
because as a train goes through a tunnel if it is going fast it
generates a lot of heat and you have to have a bigger tunnel.
But I do not accept the premise that you would necessarily have
a different alignment."[72]
52. Sir David Higgins explained to
us that considerable work had been undertaken to ensure that design
changes were made when accommodating a lower maximum speed would
lead to savings:
"The tunnels will not be designed for 400
kilometres per hour, or areas where there is a premium cost on
doing that in terms of the tunnel. They will be designed for 360;
some of the approaches and the curves as we go into particularly
the Eastern leg of phase 2 will not be designed for 400; it would
just be too expensive."[73]
53. Sir David Higgins did not agree
that substantial further savings could be made by reducing the
maximum design speed: "I have heard all the stories that
we can save a huge amount of money9 per cent of the whole
project costby cutting the speed down by 50 kilometres
an hour. The answer is that I do not believe that; I do not believe
you can save that money."[74]
54. The Government should review opportunities
to reduce the cost of constructing HS2 through a change in the
design of the scheme to one with a lower maximum speedsuch
as that used on continental railwaysand publish the results
of this exercise. This should include an assessment of the effect
a lower speed would have on journey times, which is likely to
be small.
Cost of disruption
55. Witnesses suggested that the cost of constructing
HS2 did not include the cost of disruption caused by the building
of HS2. This could include the disruption to passengers from stations
under development, delays to road users because of the major construction
work required, and connecting HS2 to the existing network.
56. Joe Rukin of Stop HS2 said that "HS2
Ltd completely ignores the disruption that HS2 will cause, even
on the railways".[75]
He said that HS2 would cause "massive disruption for everywhere
that has trains coming into Euston" and at locations where
the HS2 track would cross the West Coast Main Line.[76]
Professor Henry Overman, Professor of Economic Geography,
London School of Economics, argued that the monetary cost of disruption
through building HS2 should have taken into account.[77]
57. Paul Plummer, Group Strategy Director, Rail
Delivery Group and Network Rail, wrote to the Chairman explaining
how disruption had been calculated for the strategic alternatives
to HS2:
"The investigation of Strategic Alternatives
conducted by Network Rail in 2013 included an allowance for disruption
averaging 10% of the cost of each scheme. This was an estimate
based on potential payments that might be incurred under Schedule
4 of the track access contracts between Network Rail and train
operators. This sets out the compensation arrangements for both
fare revenue losses and costs such as those associated with running
replacement buses."
58. He noted, however, that this method of calculating
the costs disruption was based on experience of projects lasting
"weeks or months rather than the years required for the construction
of schemes required to deliver the strategic alternatives."
He said that the damage to the rail brand caused by years of weekend
closures was not easily assessed and the calculations did not
take account of the economic effect of the disruption felt by
cities on affected routes. [78]
59. When asked about the cost of disruption for
HS2, the Secretary of State told us that "There will be some
disruption in certain areas while HS2 is being built, certainly,
but nowhere in the lines of the amount of disruption would that
be required for an upgrading of the West Coast."[79]
60. The Secretary of State clarified in a letter
to the Chairman that "HS2 cost estimates include an allowance
for disruption". He explained that the detailed information
required to apply the method of assessing disruption used by the
Office of Rail Regulation was not held at the time of writing
the business case: "Instead we have adopted an approach which
approximates the ORR methodology, recognising interactions between
construction of the infrastructure and the existing rail network."[80]
He noted that a qualitative assessment of disruption was included
in the Strategic Case. This is considered in Chapter 5.
61. The Government should make clear the full
cost of disruption as a result of HS2 by publishing the expected
costs of disruption from building HS2 separate from the overall
construction cost, and the monetary value of disruption to rail
passengers and road users caused by the construction.
Expected net cost of HS2 to the
Government
62. We asked the Government for its prediction
of the net cost of HS2 taking account of total capital and operating
costs and deducting revenue. Lord Deighton wrote to the Chairman
providing details of the expected present value of the cost of
HS2 over 60 years:[81] Table
5: Expected net cost of HS2 (£ billion over 60 year period)
Capital cost
| Operating costs
| Revenue income
| Net cost to Government
|
£40.5 | £22.1
| £31.1 | £31.5
|
Source: Letter from Lord Deighton to the Chairman,
5 December 2015
63. Lord Deighton also explained that HS2
was expected to generate an additional premium to the taxpayer
of around £0.3 billion a year: "This comprises an operating
surplus for HS2 services of around £2.8 billion and an additional
subsidy of classic services of around £2.5 billion (owing
to classic customers moving over to HS2)."[82]
64. We asked the Secretary of State
and Lord Deighton whether the £0.3 billion annual premium
could be considered as contributing towards the paying off of
the £31.5 billion net cost of HS2. Mr Prout wrote to
the Chairman following our evidence session and explained that
the two figures were not directly comparable because the revenues
which contribute to the net cost calculation "are significantly
discounted compared to the construction costs incurred earlier
in the appraisal period."[83]
The prediction of a £0.3 billion operating annual premium
therefore does not take account of repaying the capital cost of
building HS2.
WHO WILL PAY FOR HS2?
65. The Government has committed to reducing
the dependence of the rail network on public subsidy. The 2012
command paper, Reforming our Railways, said that: "We
must also help to reduce the demand on taxpayer subsidy, ensuring
that the railways are financially sustainable in the longer term
and can contribute towards the country's economic growth and environmental
goals."[84]
66. The Office of Rail Regulation report,
2013-14 Annual Statistical Release: Rail Finance, described
how "Government support to the rail industry increased in
2013-14 for the third year in succession but remains lower than
the highest level of Government support which was during 2006-07."[85]
The total level of Government support for the rail industry in
2013/14 was £5.3 billion. The highest level of support was
£6.3 billion in 2006/07.[86]
67. The net cost of HS2 to the Government will
be met by the taxpayer, but business travellers are forecast to
derive the most benefit from the project (70 per cent of the net
transport benefitssee Chapter 8). Some witnesses
suggested those who benefitted from HS2 should pay for the cost
of its construction. Stephen Plowden, a private individual,
said that "Business or other travellers who valued the time
they would save by switching from conventional rail to HS2 should
also pay for it themselves."[87]
Aberdeen and Grampian Chambers of Commerce noted that "some
regions will see greater economic benefits from HS2 than others.
Nevertheless, tax revenues from businesses in Aberdeen and Grampian
will disproportionately help pay for the project."[88]
68. Ticket pricing would be one way in which
the cost of HS2 could be shifted to the users, by charging premium
prices to recoup costs. We consider in Chapter 3 the Government's
assumption that fares on HS2 should be in line with fares on the
rest of the network.
69. The Government should explain how the
£31.5 billion net cost to the taxpayer of building and running
HS2 can be reconciled with their objective of making rail less
dependent on public subsidy.
70. The Government should consider the fairness
of the large taxpayer subsidy required to fund the construction
of HS2 as many taxpayers will derive no benefit from the project.
The Government should look for opportunities to reduce the burden
on the taxpayer, including by charging higher prices so those
that receive the benefits of HS2 pay for more of the cost of its
construction.
Chapter 2: Conclusions and recommendations
71. The Government should make clear whether
the absolute limit for the construction of HS2 will increase in
line with inflation. (Paragraph 24)
72. The Government should estimate the overall
reduction of cost to HS2 of terminating the line at Old Oak Common
(in the London Borough of Hammersmith and Fulham), including any
necessary redesign of the station at Old Oak Common to make this
possible, and calculate the effect on the cost benefit analysis.
(Paragraph 31)
73. The expected cost of construction per mile
of HS2 is up to nine times higher than the cost of constructing
high speed lines in France. This is too high. Were HS2 proceeded
with, we welcome the Government's and Sir David Higgins'
commitment to learning from international examples to reduce this
cost. (Paragraph 37)
74. We are concerned to learn that the UK construction
industry does not have the capability to deliver a project of
the scale of HS2. A national transport strategy that envisages
steady investment in the UK's transport infrastructure, whatever
the project, may help the UK develop a construction industry capable
of delivering large infrastructure projects and competing internationally.
(Paragraph 42)
75. The Government should review opportunities
to reduce the cost of constructing HS2 through a change in the
design of the scheme to one with a lower maximum speedsuch
as that used on continental railwaysand publish the results
of this exercise. This should include an assessment of
the effect a lower speed would have on journey times, which is
likely to be small. (Paragraph 54)
76. The Government should make clear the full
cost of disruption as a result of HS2 by publishing the expected
costs of disruption from building HS2 separate from the overall
construction cost, and the monetary value of disruption to rail
passengers and road users caused by the construction. (Paragraph 61)
77. The Government should explain how the £31.5
billion net cost to the taxpayer of building and running HS2 can
be reconciled with their objective of making rail less dependent
on public subsidy. (Paragraph 69)
78. The Government should consider the fairness
of the large taxpayer subsidy required to fund the construction
of HS2 as many taxpayers will derive no benefit from the project.
The Government should look for opportunities to reduce the burden
on the taxpayer, including by charging higher prices so those
that receive the benefits of HS2 pay for more of the cost of its
construction. (Paragraph 70)
28 Strategic Case, p 139 Back
29
Contingency for Phase One and Phase Two is measured at a 'P95'
level of certainty. This is the additional contingency required
to give a 95% degree of confidence that the project can be delivered
at that cost with no change in scope. Back
30
Q231 Back
31
Q64 Back
32
Letter from Secretary of State to the Chairman, 12 February 2015 Back
33
Department for Business, Innovation and Skills, Quarterly Construction
Price and Cost Indices: January to March 2014, June 2014:
https://www.gov.uk/government/statistics/bis-quarterly-construction-price-and-cost-indices-january-to-march-2014
[accessed February 2015] Back
34
Q117 Back
35
Sir David was Chief Executive of the Olympic Delivery Authority
from 2005 to 2010. Back
36
Q236 Back
37
Q42 Back
38
Q91 Back
39
Q231 Back
40
QQ236,237 Back
41
Q231 Back
42
Written evidence from HS2 Action Alliance (EHS0037) Back
43
Q231 Back
44
'HS2 "slowly dying" as Euston terminus plan grinds to
a halt', Daily Telegraph, 22 November 2014 Back
45
Q77 Back
46
Q77 Back
47
Translated from French. Cour des Comptes, La Grande Vitesse Ferroviaire:
un modèle porté au-delà de sa pertinence
rapport public thématique, October 2014, pp 19-21: https://www.ccomptes.fr/Publications/Publications/La-grande-vitesse-ferroviaire-un-modele-porte-au-dela-de-sa-pertinence
[accessed February 2015] Back
48
Calculated using average exchange rate for 2010 of 0.8585 £
to . Back
49 Q231 Back
50
Q231 Back
51
Oral evidence taken before Transport Select Committee, 17 November
2014 (Session 2014-15), Q20 (Sir David Higgins) Back
52
Q236 Back
53
Q253 Back
54
Written evidence from the Department for Transport (EHS0021) Back
55
Written evidence from HS2 Ltd (EHS0057) Back
56
Written evidence from HS2 Action Alliance (EHS0037) Back
57
Written evidence from William Avery (EHS0014) Back
58
QQ192,193 Back
59
Q231 Back
60
Q235 Back
61
Written evidence from Cheryl Gillan MP (EHS0040) Back
62
Q91 Back
63
Q31 Back
64
Q1 Back
65
Letter from David Prout to the Chairman, 7 January 2015 Back
66
Although HS2 will be built to accommodate speeds of up to 400
kph, trains will initially run at a maximum speed of 360 kph. Back
67
Speeds vary across lines. The highest speed is shown. Back
68
Planned maximum speed of line under construction. Back
69
Written evidence from Stop HS2 (EHS0049) Back
70
Q32 Back
71
Q32 Back
72
Q232 Back
73
Q237 Back
74
Q237 Back
75
Q81 Back
76
Q81 Back
77
Q56 Back
78
Letter from Paul Plummer to the Chairman, 2 February 2015 Back
79
Q220 Back
80
Letter from the Secretary of State to the Chairman, 12 February
2015 Back
81
Letter from Lord Deighton to the Chairman, 5 December 2014 Back
82
Ibid. Back
83
Letter from David Prout to the Chairman, 7 January 2015 Back
84
Department for Transport, Reforming Our Railways: Putting Customers First,
March 2012 (Cm 8313), p 11 Back
85
Office of Rail Regulation, 2013-14 Annual Statistical Release:
Rail Finance, August 2014, p 5: http://orr.gov.uk/__data/assets/pdf_file/0007/14497/rail-finance-statistical-release-2013-14.pdf
[accessed February 2015] Back
86
Ibid., p 7 Back
87
Written evidence from Stephen Plowden (EHS0073) Back
88
Written evidence from Aberdeen and Grampian Chambers of Commerce
(EHS0022) Back
|