3 Procedural issues and implications
22. Our consideration of this first Development Consent
Order under Special Parliamentary Procedure has thrown up several
procedural problems which arise from anomalies in the statutory
framework within which we work. We urge the Government to rectify
these anomalies as a matter of priority, and in doing so, they
should consult the relevant authorities in the two Houses. We
will draw our Report to the attention of the Leaders of the two
Houses and to the two Procedure Committees.
INCOMPATIBILITY OF THE PLANNING ACT
2008 AND THE STATUTORY ORDERS (SPECIAL PROCEDURE) ACT 1945
23. The Statutory Orders (Special Procedure) Act
1945 sets out the powers and procedures of Parliament in relation
to Special Procedure Orders. It provides for the receipt of petitions,
the certification of petitions as proper to be received and the
period during which either House can resolve to annul the Order
as well as the remit and powers of joint committees to consider
petitions against the Order. Crucially, the Act makes provision
for Parliament to consider the whole Order, and neither
House has procedures in place which would allow them to annul
only some elements of the Order.
24. By contrast, the natural interpretation of section
128(2) of the Planning Act 2008 is that it limits the Special
Parliamentary Procedure to the provisions of the Development Consent
Order authorising the compulsory acquisition of special land.
After all, it would seem rather inconsistent if Parliament were
to conduct a full re-hearing of the issues in respect of some
Development Consent Orders, given that all DCOs, including
those subject to Special Parliamentary Procedure, are subject
to appeal by judicial review. However, as explained above, the
provisions of the 1945 Act apply to the Order as a whole, and
since the 2008 Act did not amend the 1945 Act, we now have a statutory
framework which is internally contradictory.
25. This incompatibility between the 1945 and the
2008 Acts is particularly critical for the two remaining stages
in the Special Parliamentary Procedure process. Firstly, the 1945
Act provides only for consideration and decision of the whole
Order, and the Standing Orders of both Houses simply mirror the
framework provided by the Act. Neither House has any procedural
instrument by which debate on a resolution to annul the Order,
tabled within the 21 day resolution period, could be limited to
certain elements of the Order only, nor does either House have
any means of annulling only some elements of the Order. It must
therefore be the incontrovertible right of each House to debate
any aspect of a Development Consent Order subject to Special Parliamentary
Procedure and, if it so chooses, to reject the Order in its entirety
on the basis of opposition to elements which, according to the
intention of the 2008 Act, ought not to be subject to any part
of Special Parliamentary Procedure.
26. The other stage at which the discrepancy between
the provisions of the 1945 Act and the intentions of the 2008
Act become critically important is in the scope of consideration
of petitions by a joint committee. The Agents for the unitary
councils argued forcefully at our hearing that, once a petition
has been certified as proper to be received and referred to a
joint committee, all aspects of that petition, whether or not
they relate to the compulsory purchase of special land, should
be considered by the committee.
27. We do not agree with this 'key to the door' interpretation,
but we acknowledge that the lack of legislative consistency muddies
the waters very seriously. We do not have the power to direct
any committee to opt for one interpretation or another. Only the
Houses can do that, should they so choose. Given the inconsistencies
of the current statutory framework, it must be the prerogative
of any committee to decide for itself how widely or narrowly it
wishes to interpret its remit in relation to the petitions before
it. We would, however, encourage any joint committee to seek to
be consistent with section 128 of the Planning Act 2008 by focusing
their work on the issues of compulsory purchase of special land;
but it is clear that whilst the statutory inconsistencies remain,
joint committees may reach different conclusions about the appropriate
breadth of their inquiries, and further inconsistencies of practice
are therefore probable. This is unsatisfactory.
In the 2012 Budget, the Government announced that
it will
"remove duplication in the consenting regime
for major infrastructure development by bringing forward legislation
to adjust the scope of Special Parliamentary Procedure, and will
shortly publish draft revised guidance to make the regime clearer
and easier to use".[8]
28. At this stage, it is unclear precisely what duplication
the Government intends to remove, and indeed whether it will address
the problems we have identified above. We
urge the Government to amend either the Statutory Orders (Special
Procedure) Act 1945 or the Planning Act 2008or bothso
as to ensure a consistent statutory framework for the consideration
of future Development Consent Orders subject to Special Parliamentary
Procedure. In drawing up revised provisions, the Government will
need to consult with the relevant authorities of the two Houses.
In the meantime, no further orders of this type should be laid
before Parliament until the statutory framework has been amended
to resolve these inconsistencies.
COMPLIANCE WITH EUROPEAN DIRECTIVES
29. A further legal issue was brought to our attention
by the Secretary of State for Energy and Climate Change less than
a week before our hearing on the Rookery South (Resource Recovery
Facility) Order 2011 on 8 March 2012. In a written submission
summarising the arguments that would be made on behalf of the
Secretary of State at the hearing, it was suggested that, in a
case such as this which relates to the approval of new electricity
generating capacity, the Special Parliamentary Procedure would
be incompatible with Article 7 of EU directive 2009/72/EC (concerning
common rules for the internal market in electricity and gas) if
it led to the annulment of the order, or a decision by the joint
committee that the order be not approved.[9]
The Directive provides that Member States are obliged to provide
a route of appeal for applicants in cases where an application
to construct additional generating capacity is rejected. We were
urged to opt for a narrow interpretation of locus standi
in order to minimise the risk that a joint committee would be
persuaded to report that the Order be not approved under section
5(2) of the 1945 Act.
30. We sought clarification on these points both
at our hearing on 8 March, and subsequently by correspondence
(which is published in Appendix A). In his letter, the Minister
states that "Both Parliament and the Executive have a duty
to secure compliance, in so far as they can, with the UK's international
obligations, for example under EU Treaties." The Minister
also suggests in his letter that through a series of procedural
manoeuvres it would not be "impossible to secure compliance
by one means or another", including the possibility that
an annulment motion may "not be selected for debate".
This view of Parliamentary procedure is mistaken as there are
no powers of selection in the Lords and the powers granted to
the Speaker in the Commons do not extend to motions of this type.
Furthermore, under the 1945 Act, either House has the right to
pass a resolution to annul the Order (a decision the Minister
concedes would be incompatible) and the joint committee has a
statutory right to reject the Order if it sees fit to do so.
31. It is clear from the Minister's response that
the Government considers that it would be incompatible with Directive
2009/72/EC for Parliament to annul an order granting development
consent where, as in this case, the order related to a new electricity
generating station. The same must apply where a joint committee
decided that such an order should not be approved. Given this
point of view, we find it very difficult to see any justification
for maintaining the legislation in a form that allows these things
to happen. In our view, it cannot be right for legislation to
confer powers on Parliament in relation to development consent
orders for new electricity generating stations if there are no
circumstances in which those powers can be exercised compatibly
with EU law. We therefore
urge the Government to amend the statutory framework under the
Statutory Orders (Special Procedure) Act 1945 to ensure that all
outcomes available under the statutory framework, and as a result,
the Standing Orders of the two Houses, are compliant with EU legislation.
In drawing up revised provisions, the Government will need to
consult with the relevant authorities of the two Houses. In the
meantime, no further orders of this type engaging Article 7 of
Directive 2009/72/EC should be laid before Parliament.
8 HM Treasury, Budget 2012, HC 1853 (2010-12),
para 1.236, p 44 Back
9
Submission from the Secretary of State for Energy and Climate
Change, 1 March 2012, paras 45-50 Back
|