3  Through life costs were not rigorously assessed

19. Successful procurement involves planning and managing projects on a through-life basis, covering feasibility, research, development, production, bringing into service, maintenance, and eventually disposing of equipment. Bowman is a complex system designed to provide a wide range of equipment and functionality and consequently requires an extensive range of support services for maximum benefit to be derived from the system. The Department failed to plan adequately for the full range of costs associated with introducing Bowman.[24]

20. When the programme was approved the Department's expectation was that support costs would be broadly in line with the equivalent costs for Clansman. But the Bowman CIP system comprises between two and three times as many major components as the Clansman radio that preceded it. It is difficult to get an accurate assessment of support costs for new equipment until it is brought into service, and some support costs associated with Bowman were initially under-estimated. Support costs have also increased as equipment is deployed on operations in difficult conditions such as those experienced in Iraq. For the longer-term, the Department is looking at a built-in through life support system for Bowman CIP consistent with the partnerships envisaged in the Defence Industrial Strategy.[25]

21. The Department's assumption that training costs should be no higher than those for using Clansman was clearly unrealistic. The training requirement to ensure that users make use of all the capabilities of the Bowman system will be significantly higher than the equivalent for the much simpler Clansman radio. Training costs were not fully assessed in the early stages. In particular, Bowman requires not just initial training but also regular continuation training. It is also an evolving system and, as new capabilities are added, further training is needed.[26] The Department acknowledges that the training budget was well short of what was needed and agrees that in future it makes sense to think in terms of acquiring not just a radio system but a radio system with through-life support built in.

22. In December 2004 it became clear to all parties that the Bowman CIP programme was over- ambitious and needed substantial revision. The Bowman radio accepted into service was subject to ongoing provisos and CIP failed to meet its expected In Service Date. Following a detailed review and negotiations between the Department and the contractor a recast programme was agreed resulting in a further £121 million of funding and a two year extension in the timescale. The Department and General Dynamics UK have different views on how much of the £121 million represents new or changed customer requirements and how much represents cost increases in delivering the capability originally contracted for. The Department described it as "regrettable additional expenditure". The Department's view is that the basic capability requirement is unchanged but that changes in the means of meeting it had to be made in order to deliver the programme.[27]

23. Overall the cost overrun equates to 5% of the initial programme cost, although on a unit cost basis the overrun is clearly larger because the scale of the Bowman CIP programme has been reduced. This outturn cost equates to an average £52,000 per radio installation.[28] If the additional £200 million estimate for the cost of deleted capabilities (paragraph 32), proves correct this would be a further 8% overrun on the original programme cost.[29]


24   Q 156 Back

25   Qq 50-51, 114-115; C&AG's Report, para 3.13 Back

26   Qq 7-8, 43, 82 Back

27   Q 46 Back

28   Ev 21 Back

29   Q 83 Back


 