2 Delivering the systems
7. The patient clinical record is to be delivered
through a combination of a central system called the Spine and
local systems delivered by Local Service Providers. The central
and local systems work together to operate the National Care Records
Service, which, in addition to the clinical record, holds non-clinical
information on patients through the Personal Demographics Service,
controls access to many of the Programme's service and handles
the transmission of information between systems (Figure 2).[17]
Figure 2: NHS Care Records Service
Source: C&AG's Report, paras 5m, 1.8, 1.12;
Figure 3
8. The Spine first went live in June 2004 as scheduled
but the achievement of later milestones for increasing its functionality
was delayed by up to ten months. By the time of our examination,
the Personal Demographic Service held 72 million live records,
375,000 patient searches were being conducted every day and over
240,000 users had been registered, although this is only a small
part of the overall scheme.[18]
9. The patient clinical record itself, however, had
not yet been deployed at any location. It was due to be available
in pilot form in late 2006, and in full form a year later, two
years later than originally planned.[19]
The Department told us that the decision to delay had been taken
because some suppliers were having difficulty in meeting the timetable
and because clinicians wanted to pilot the scheme. It hoped to
have implemented most of the system by 2010, but the scale of
the implementation and the risks associated with it needed to
be recognised.[20]
10. At the time of our hearing in June 2006, some
13 acute Trusts had had their Patient Administration System (PAS)
replaced, which itself provides no care record functionality beyond
what they already had. In those regions where iSOFT is the main
software supplier, the replacement has been an old iSOFT PAS which
pre-dates the Programme because the PAS element of the new system,
Lorenzowhich is being developed for the Programme and which
the company stated was available from early 2004[21]is
not yet available. In those areas in which GE/IDX was originally
contracted as the main software supplier but has now been replaced
by Cerner, there are delays in anglicising the Cerner product.
A considerable number of Primary Care Trusts and mental health
Trusts who previously had no corporate patient administration
system at all have been supplied with iSOFT's old PAS. No published
plans exist for implementing shared electronic patient clinical
records in line with the original vision for the Programme.
11. The other projects making up the Programme have
made varying degrees of progress.[22]
The New National Network (N3) was three months ahead of schedule.[23]
Choose and Book, the electronic system to enable patients to book
first outpatient appointments, had been deployed to over 7,600
locations by April 2006, but accounted for only 20% of referrals
from GPs to first consultant outpatient appointments in the week
preceding our examination.[24]
The Department accepted that some GPs had not had a good experience
of using the system, which it believed was often attributable
to local implementation issues or to the hospital's patient administration
system not being up to date.[25]
12. Deployment of the electronic prescription service
and the computer accessible X-ray systems had been slower than
anticipated, but the Department believed that later deployment
targets would be met.[26]
It reported that many other local systems had been deployed, including
13 acute hospital patient administration systems.[27]
Two thirds of people had access to services that were dependent
on services delivered by the Programme, and the Department said
that would move to 100% over the next twelve months.[28]
However, in June 2006 the Department told us that it would deliver
at least 22 new Patient Administration Systems (PAS) to NHS Acute
Trusts between June and October 2006. But even by the end of February
2007, only a further five had been deployed, suggesting that the
Programme is still unable to meet short term targets.[29]
13. The experience of PAS systems that have been
delivered has been patchy. Some Trusts have experienced problems
including inability to report activity statistics,[30]
missing patient records[31]
and extended shut-down of some systems.[32]
Clinical consequences have included waiting list breaches[33]
and significant delays in providing inoculations to children.[34]
14. Plans published by NHS Connecting for Health
in January 2005 indicated that by April 2007, 151 acute hospital
Trusts would have implemented Patient Administration Systems of
varying degrees of sophistication.[35]
As of February 2007 only 18 had been deployed.[36]
Such delays can cause considerable cost and disruption to Trusts,
since they may have to replan expected live dates and spend money
on preparing for expected dates that are not met. Mr Brooks told
us in his submission that in his view there was no evidence that
Local Service Providers have added any value to the National Programme
and a cluster wide contract has not delivered any identifiable
benefits.[37]
15. Total expenditure on the Programme to the end
of March 2006 was £1,542 million.[38]
This comprised £654 million on the contracts with suppliers
against expected expenditure of £1,448 million; and a further
£888 million on new projects added to the scope of the Programme,
additional services, non-core projects, National Programme support
for local NHS implementation, expenditure by local NHS organisations,
and central administration.[39]
The shortfall in expenditure on the contracts with suppliers reflected
the slower than planned delivery of some systems and contractual
provisions that suppliers would only be paid once services were
delivered and working.[40]
The Department told us that although it retained a timescale risk,
it had transferred finance and completion risk for the most part
to the suppliers.[41]
However, the Department told us it also made advance payments
to suppliers covered by a letter of credit from a bank or a charge
on the company's assets of at least an equal value. By 31 March
2006 the Department had paid £443 million in forward payments
to Local Service Providers and by December 2006 this figure had
risen to £639 million.[42]
16. The Department told us that central expenditure
on the Programme between the end of March 2006 and 31 December
2006 had risen by £532 million from £1,083 million to
£1,615 million.[43]
The Department had no information on expenditure by local NHS
organisations after 31 March 2006, but even counting in local
expenditure only to that date, total cumulative expenditure on
the Programme to the end of December 2006 is not less than £2,074
million; and because of the unknown amount of local expenditure
must in practice have substantially exceeded this amount.
17. The Department had brought in resources from
abroad, though with poor results for some suppliers which were
requiring close attention.[44]
The Department regularly assessed the financial capacity and fitness
of its prime suppliers in conjunction with Partnerships UK, whose
most recent review had confirmed that all the key suppliers had
sufficient financial capacity to fulfil their liabilities and
continue to discharge their obligations under the contracts.[45]
18. However, continuing financial problems with key
suppliers including iSOFT have been widely reported.[46]
Shares in iSOFT lost more than 90% of their value after a series
of profit warnings and the discovery of alleged accounting irregularities.[47]
The company is now under investigation by the Financial Services
Authority, while its former directors and former auditors are
under investigation by the Financial Reporting Council's disciplinary
body, the Accountancy Investigation and Discipline Board.[48]
Although iSOFT has received loan support from its banks, there
is a continuing risk to the National Programme if it is overly
dependent on the future stability of a small number of suppliers.
19. In September 2006, the Department, Accenture
and CSC announced that Accenture was to transfer its responsibility
as local service provider for its two clusters to CSC by 8 January
2007, further reducing the supplier base, though Accenture would
retain its responsibility for computer accessible X-ray systems
in these clusters.[49]
Commedica, the PACS supplier in the North West and West Midlands
cluster, has also been replaced, and IDX has been replaced by
Cerner as the main software supplier for the Southern and London
clusters.[50]
17 C&AG's Report, paras 5m and 1.11-1.12; Figure
3 Back
18
Qq 6, 233; C&AG's Report, para 5m Back
19
On 19 July the Department announced that the first phases of the
patient clinical record would be introduced in a small number
of locations from early 2007, with wider roll out during 2008
(Department of Health Press Release 2006/0265, 19 July 2006). Back
20
Qq 1-7, 233; C&AG's Report, para 5m Back
21
iSOFT Group PLC 2005, Annual Report and Accounts, page
6 Back
22
C&AG's Report, Figure 3 Back
23
C&AG's Report, paras 3.17-3.19 Back
24
Q112; C&AG's Report, para 1.13 Back
25
Qq 112-113 Back
26
C&AG's Report, para 5m Back
27
Qq 226-228 Back
28
Q 118 Back
29
Ev 52-54, NHS Connecting for Health website Deployment statistics Back
30
Ev 93 Back
31
Loc. cit. Back
32
e-Health Insider, 1 August 2006 Back
33
Ev 93 Back
34
CDR Weekly Volume 16 Number 25 page 11. Published by Health Protection
Agency, 22 June 2006 Back
35
NHS Care Record Service: Indicative Deployment Plan-January 2005 Back
36
NHS Connecting for Health website Deployment statistics Back
37
Ev 100 Back
38
Ev 55 Back
39
Loc. cit., C&AG's Report, para 1.22 Back
40
C&AG's Report, para 5q Back
41
Q 117 Back
42
Qq 150-152, Ev 55-58 and 81-82 Back
43
Ev 81-82 Back
44
Qq 53-54 Back
45
Qq 12-14, 53, 121-122 Back
46
Qq 42-43 Back
47
http://www.isoftplc.com/corporate/investor_centre/share_info.asp;
http://www.isoftplc.com/corporate/news_media/2633.asp Back
48
http://www.isoftplc.com/corporate/media_files/Interim_Results_111206.pdf Back
49
Accenture, CSC and NHS Connecting for Health press notices, 28
September 2006 Back
50
C&AG's Report, Figure 3; Q 46 Back
|