Select Committee on Public Accounts Twentieth Report


3  Managing implementation and ensuring that the systems meet the needs of the NHS

20. The Programme is a combination of national and local projects, with local implementation organised in five regional clusters (Figure 3). Each cluster has a Local Service Provider which is responsible for delivering services within the cluster, working in conjunction with the Strategic Health Authorities and local NHS organisations within the cluster.[51]

Figure 3: The five regional clusters and their current local service providers

Source: National Audit Office

21. The scale, specialisms and fragmentation of existing IT systems has made the delivery and implementation at each NHS site more complex than other IT implementations, and the Programme is being implemented against a background of change in the configuration of the NHS.[52] The Department told us that although procurement had been carried out centrally, implementation was local through each NHS organisation. Every local implementation had its own characteristics and needed to be locally tailored.[53] It had established a system where the chief executives of the new strategic health authorities that came into operation on 1 July 2006 were accountable for overseeing implementation in their local NHS.[54] Within each organisation, the chief executive was responsible, and at both levels, chief executives should be supported by a chief information officer.[55] If anything went wrong in a particular implementation, the strategic health authority would intervene, and NHS Connecting for Health would intervene if the programme was going wrong on too big a scale.[56] It is unclear how much the localising of responsibility will help unless local Trusts are also given flexibility in the choice of systems so that local needs can be taken into account.

22. The procurement of the systems was based on an "Output Based Specification", a statement of the functions that the system was intended to perform. Development of the specification began in February 2002, and drew on information from various sources, including specifications developed by NHS bodies for their own patient record services and consultation with NHS staff. The specification was initially published for consultation in July 2002. Following further revisions, it was issued to potential suppliers in May 2003. After contracts had been placed, clusters also established clinical advisory groups to obtain clinical input as specific systems were developed.[57]

23. An appraisal commissioned by the National Audit Office of the development of the specification found that it was developed after engagement with a broad spectrum of NHS stakeholders but that there was no recorded link between the detailed items in the specification and the person or group making that contribution.[58] The Department's explanation was that NHS Connecting for Health had not had the resources to record the attributions individually.[59] Dr Nowlan told us that in his view this explanation for the lack of documented validation was not credible.[60] Professor Hutton also told us that there was no good audit trail for clinical input into the production of the specification, and that key decisions were taken in the early period of the Programme without proper clinical input.[61] He and Dr Nowlan also both told us that they felt that clinicians and the local NHS were not taken into account and did not have sufficient say.[62] The Comptroller and Auditor General told us that "the approach from the top down had not permitted the full degree of consultation".[63]

24. The Department commented that hundreds of people had input to the design process. Not only had there been clinical input in the original specification, but as the Programme had proceeded clinicians and other users had been involved in much more detail. For example 470 clinicians had recently been involved in looking at the national requirement to support e-prescribing, although this appears a very late point at which to do so, since the specification of the solution and the terms of the contract had been set before it began.[64] Other action had included establishing the Care Record Development Board to strengthen patient involvement, and the appointment of national clinical leads.[65] In their examination of NHS information technology our predecessors stressed the need to involve end users, noting that getting the commitment of everyone is crucial to successful implementation of complex IT projects.[66]


51   C&AG's Report, para 3 Back

52   Q 94; C&AG's Report, para 1.8 Back

53   Q 10 Back

54   Q 8 Back

55   Qq 96-97 Back

56   Qq 100-101 Back

57   C&AG's Report, paras 2.10-2.13, 4.3 Back

58   Q 26; C&AG's Report, paras 2.11-2.13 Back

59   C&AG's Report, para 2.13 Back

60   Ev 29 Back

61   Q 18 Back

62   Q 59 Back

63   Q 218 Back

64   Qq 63, 205, 209 Back

65   Q 26 Back

66   Committee of Public Accounts, The 1992 and 1998 Information Management and Technology Strategies of the NHS Executive, HC (1999-2000) 406, para 33 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 11 April 2007