Select Committee on Public Accounts Twentieth Report


4  Securing the benefits of the Programme

25. One of the conclusions of our predecessors' examination of the 1992 and 1998 Information Technology Strategies for the NHS was that getting ownership of developments by clinicians, general practitioners and other healthcare staff was essential.[67] However, although there was support for what the Programme was seeking to achieve among NHS staff, there were also significant concerns, for example that the Programme was moving slower than expected, and that deployment plans had been unreliable.[68] Professor Hutton told us that the Department did not adequately engage the medical community, and surveys of staff by Medix indicated that support for the Programme had fallen between 2004 and 2006 (Figure 4).[69] The Department's own Ipsos MORI surveys of NHS staff also showed a decline between 2005 and 2006 in favourability towards the Programme so far, with reasons given for unfavourable ratings including not enough input or communication with the people that would be using it, and poor organisation and planning.[70]

Figure 3: Support for the Programme has fallen amongst GPs and other Doctors

Source: C&AG's Report, 4.13

26. In the case of the Programme, the Department decided to conclude the bulk of procurement activities before focusing on communicating with and engaging NHS staff.[71] Wider consultation on the Programme with NHS staff did not commence until the procurement phase had concluded at the end of 2003, working initially through the clusters.[72] Leadership in securing support from NHS staff and organisations has changed several times over the life of the Programme: at the time of our examination, responsibility for this task had passed between six Senior Responsible Owners.[73]

27. The Department told us that some systems, such as the new network connections, had been well received by clinicians, but that clinicians found it more difficult to assimilate systems that were more disruptive to their working practice.[74] While it was necessary to recognise that a Programme of this scale would cause a degree of controversy and dissent, the Department said thousands of clinicians were already using the system and quietly getting on with it.[75] The Department had been working to establish further support for the Programme through the Care Record Development Board, for example in building a consensus over the last year on the content of the clinical record.[76] It said it had engaged clinicians, but recognised that there was very much more to be done.[77]

28. One issue causing concern among GPs was the future of their IT systems.[78] Under the General Medical Services contract, Local Service Providers were required to offer a choice of systems to GPs, but had only been contracted to provide two and it very quickly became apparent that one of these was not being delivered.[79] The Department had now attempted to address this problem through an initiative called GP Systems of Choice.[80] The development and implementation of the scheme was subject to discussions with suppliers.[81]

29. Another issue that has prompted concerns amongst doctors and others is the protection of patients' confidentiality, where Dr Nowlan told us that the most important issue was the arrangements for governance and trust, and compliance with these arrangements.[82] The Department told us that the security systems in place will be more secure than the Chip and PIN arrangements utilised by credit and debit cards in the UK. It was also supporting the Information Commissioner in his demands for higher penalties for information abuse.[83]

30. When the main contracts for the Programme were let in 2003 and 2004, the Department announced that they would cost £6.2 billion.[84] Subsequent estimates of the cost of the Programme reportedly attributed to the Department have ranged up to £20 billion, but the Department clarified that this figure relates to total IT expenditure within the NHS during the life of the Programme and that it expected the cost of the Programme itself to be £12.4 billion.[85] Amongst other things, this higher figure includes, on top of the cost of the original contracts, central expenditure; contracts and projects added to the scope of the National Programme; additional services to be purchased beyond the scope of the original national core contracts; extrapolation of costs beyond the terms of the existing contracts; and an estimated £3.4 billion local NHS expenditure.[86]

31. The estimate of local expenditure on the Programme of £3.4 billion dated from the time the contracts were let and the actual level of ongoing local NHS expenditure on the Programme was not systematically monitored.[87] Further costs have arisen for the local NHS Trusts where they have been required to pay suppliers a total of £24 million in order to be released from contractual obligations to provide staff to help suppliers develop the systems.[88] Delivery delays have also had an impact on local NHS expenditure, with a number of Trusts having had to renew their own patient administration systems, for example because they were time expired, or upgrade them to make them compliant with the National Data Spine. Deploying such interim systems would affect both costs and benefits.[89] The Department was providing some financial support to Trusts for upgrading, and where new systems came in, Trusts did not have to pay for the old system anymore.[90]

32. In the business cases for the various elements of the Programme, the Department sought to put a financial value on the benefits of the Programme where it could.[91] Its main aim with the Programme, however, was to improve services to patients rather than reduce costs, and there was a gap between the estimated financial value of the benefit of the Programme and its costs.[92] The Department was unable to give a full statement on the extent of this gap but said that the business case for the computer accessible X-rays contract had identified cash savings of £682 million against a contract cost of £1.3 billion.[93]

33. The Department believes that the patient safety benefits achieved through the Programme's successful implementation could be worth many billions over ten years, for example from reductions in preventable fatalities arising from medication errors; the number of patients requiring treatment as a result of medication errors; and in the amount paid by the NHS each year to settle clinical negligence claims. No detailed analysis had been carried out in order to substantiate these estimates.[94] The Department also predicts that the Programme will result in further savings by improving staff efficiency, by for example reducing the amount of time spent repeatedly taking patients' medical histories and demographic details.[95] The Programme would also help standardise practice and allow people to move between employers without re-training, improve information available when patients were referred to hospitals, and improve resource use and efficiency.[96]

34. The Local Service Providers were contracted to deliver Local CRS systems to NHS organisations in three phases. Phases 2 and 3 are the key to the delivery of clinical benefits and were the core of the business case for the high cost LSP contracts. Phases 2 and 3 provide the NHS with functionality that would enable organisations to support integrated clinical care processes (scheduling, investigating, prescribing, treating, assessing, etc.) by healthcare staff no matter in what organisation (hospital site or GP practice) or in what care setting (primary, mental health, community, tertiary). Phase 1, the least important from a clinical point of view because it contains mainly administrative functionality, is already late with no published dates for its completion. The implementation of Phases 2 and 3, may, therefore, scarcely have begun by the time the Local Service Providers were originally contracted to have implemented completely all three Phases to all hospitals and Trusts in England.



67   Committee of Public Accounts, The 1992 and 1998 Information Management and Technology Strategies of the NHS Executive, HC (1999-2000) 406, para 9 (v) Back

68   C&AG's Report, paras 5k, 4.14 Back

69   Qq 19, 31; C&AG's Report, para 4.13 Back

70   A Baseline Study on the National Programme for IT, MORI, 9 September 2005; Wave 2 Study on the National Programme for IT, Ipsos MORI, 20 July 2006. Back

71   C&AG's Report, para 4.2 Back

72   C&AG's Report, para 4.3 Back

73   Qq 168-175, 200 Back

74   Q 31 Back

75   Q 62 Back

76   Q 217 Back

77   Q 205 Back

78   C&AG's Report, paras 3.27-3.28 Back

79   Q 64 ; C&AG's Report, para 3.28 Back

80   Q 64-65 Back

81   C&AG's Report, paras 3.27-3.28 Back

82   Q 28; C&AG's Report, paras 2.17-2.18; Appendix 3 Back

83   Q 89 Back

84   C&AG's Report, para 1.20 Back

85   Qq 47-48 Back

86   C&AG's Report, paras 1.20-1.28 Back

87   Qq 15, 47, 123-124, 130; C&AG's Report, paras 5r, 1.26, 1.33 Back

88   Qq 234-247; DoH note on Qq 242, 247  Back

89   Ev 97 Back

90   Q 128-129 Back

91   C&AG's Report, para 1.29 Back

92   Q 153; C&AG's Report, para 1.29 Back

93   Qq 15, 153-159 Back

94   C&AG's Report, paras 1.29-1.32 Back

95   C&AG's Report, para 1.4 Back

96   Qq 8, 66-70, 99 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 11 April 2007