Select Committee on Public Accounts Fifty-Second Report


2   Managing programme costs

12. The first academies have cost an average of £27 million to build where there is an entirely new building. The average for all academies including those with a remodelling or only a partial rebuilding is £24 million. Academies have therefore cost more than other new secondary schools. Limited data indicate that other schools typically cost between £20 million and £22 million, though the costs are not directly comparable with the costs of academies because of differences in the number of pupils, site constraints and local construction prices. Some academies were granted budgets that exceeded the benchmarks used for other schools, for example to overcome site problems.[29] Cost overruns on 17 of the first 26 academies, averaging £3.2 million, have further raised the overall cost.[30] The Department considers that the cost differences are not likely to have given academies a significant advantage over other schools.[31]

13. The Department's Academies Group oversees around 200 major academy projects, with its 'project leads' each responsible for leading between five and eight projects. The detailed project management of academy set up and building is contracted out to external project managers.[32] While some project management has been good, elements of the formal feedback given by the Department to project managers indicated instances of poor cost control and failures to notify the Department early about cost overruns. In 2005 the Department introduced a system to monitor the performance of the project managers.[33] Previously there were insufficient controls to make sure that project managers were managing costs and projects effectively.[34]

14. The Department calculates the annual funding of open academies so that it is equivalent to that received by other local schools. In addition, the Department provides start-up funding for up to four years after opening, which so far has averaged £1.6 million in total for each of the first 12 academies. This start-up funding is an additional benefit that academies receive compared with other schools.[35] By comparison, Fresh Start secondary schools received an average of £750,000 of additional revenue funding to meet their start-up costs.[36]

15. The Department has expected most sponsors of academies to donate 10% of the building costs, up to a total of £2 million. Under new arrangements, sponsors' financial contributions will instead be available for academies to use once they have opened. By September 2006, the sponsors of four of the first 27 academies were behind schedule on the contributions, by an average of around £200,000.[37] The Department believes that all sponsor payments are fully up to date, but does not yet have documentary evidence because it is still with the individual academies.[38]

16. If an academy were to favour suppliers associated with its sponsor by letting contracts to them outside an appropriate procurement process, it would be breaking public procurement law. The Department would normally expect academies to use a tendering process. It monitors and reviews academies' accounts, which should declare any such related party transactions, but does not sign off contracts let by academies. In the early days, sponsors were involved in developing the programme because of their expertise. Progressively, the Department has developed guidance to academies on compliance with the contracting rules.[39]


29   C&AG's Report, paras 4, 3.23-3.24; Q 91 Back

30   C&AG's Report, para 4 Back

31   Q 61 Back

32   C&AG's Report, paras 3.2-3.4 Back

33   C&AG's Report, paras 3.6-3.7; Q 81 Back

34   Q 45-46 Back

35   Qq 3-4, 34 Back

36   C&AG's Report, paras 6, 3.43 Back

37   C&AG's Report, paras 3.31, 3.33 Back

38   Q 64 Back

39   Qq 27-33, 124; Ev 19 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 18 October 2007