Select Committee on Public Accounts Sixty-First Report


Conclusions and recommendations


1.  More than half of single living accommodation and over 40% of accommodation for families does not meet the Department's definition of high-quality accommodation and is therefore substandard. The Department needs to prioritise upgrades to the 138 houses at the lowest Standard 4 and then to the 2,000 Standard 3 houses, irrespective of location. Occupants should be offered the opportunity to move to other accommodation for the duration of works, including rented accommodation. The Department should not allow any more housing to fall into Standard 4.

2.  Poor accommodation for single personnel and for families has a negative impact on retention but the impact on retention rates of upgrading accommodation is poorly understood. The Comptroller and Auditor General concluded in previous work that it is more cost-effective to retain personnel than to recruit and train replacements.[2] The Department should investigate the relationship between the quality of accommodation and retention rates, to assess how far extra investment to achieve a swifter improvement in the condition of housing could be expected to be offset by savings in recruitment and training costs.

3.  Service personnel and their families who are living in the worst accommodation do not know when their housing will be upgraded. As it works to improve substandard accommodation, the Department should publish detailed programmes of the houses and single living spaces it intends to upgrade well in advance to give Service personnel and their families more information.

4.  There are significant gaps in the Department's understanding of the cost of its estate and it still has no effective way of knowing where funding is needed most. The Department should improve its understanding of the costs of maintaining and running its estate. In particular, it should:

¯  develop a deeper knowledge of the costs which lie with the three Services and other internal customers, including funding for Minor New Works and the overheads of Customer Estate Organisations and Site Estate Representatives; and

¯  implement Integrated Estate Management Plans for all defence sites, compiled according to a standardised methodology.

5.  The Department had to spend an additional £20 million in its contract with Modern Housing Solutions after underestimating the work required to maintain family accommodation. With better management information, the backlog could have been identified earlier, and the cost would almost certainly have been less.

6.  In 2006-07 £13.5 million of planned maintenance work was deferred in response to budget cuts, whilst the resurfacing of tennis courts and the construction of sports pitches went ahead. If the Department has to make cuts to the budget for the defence estate in future, it should consider planned maintenance together with other projects and target cuts at the lowest priority work. The Department should develop a funded plan for the completion of the deferred work, so it can hold contractors to their contractual obligations on the overall condition of the estate, and avert long-term damage to the buildings.

7.  Defence Estates and the centre of the Department received almost no advance warning of the Minor New Works projects that the three Services and other internal customers ordered in 2006-07. As a result, expenditure on the estate could not be planned, prioritised and programmed in an effective way. The three Services and other internal customers of Defence Estates should develop funded lists of Minor New Works well in advance of each financial year to allow Defence Estates to prioritise these projects effectively, and to build sensible and cost-effective programmes of work.

8.  The Department employs only 56% of the safety works staff and 57% of the quantity surveyors that it needs on its estate. The Department is exposing itself and its employees to significant Health and Safety risks whilst the lack of quantity surveyors impairs the scrutiny of project contracts. The Department should:

¯  establish the specific risks arising from current skills shortages and put in place measures to mitigate these risks;

¯  see how other public and private sector organisations overcome similar skills shortages and adopt successful practices; and

¯  allow sufficient pay flexibility to attract appropriately skilled staff to fill the empty posts.

9.  The Department's pilot project at RAF Kinross showed that implementing energy saving measures at its defence sites would bring environmental benefits and recurring financial savings of more than £2 million annually. The Department should implement energy-saving measures on the sixteen sites it has already identified as soon as possible and should roll out similar work at all its other sites, starting with those that consume the most energy.


2   C&AG's Report, Recruitment and Retention in the Armed Forces, Vol. 1, HC (2005-06) 1633-I, para 18 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 29 November 2007