Select Committee on Public Accounts Sixty-First Report


2  Prioritising work on the estate

9. The Department faces the challenge of balancing the budgetary demands of maintaining and improving its estate with other important aspects of defence expenditure. Following the Comprehensive Spending Review 2007, the Department's financial position will remain tight, and so funding will have to be targeted at the areas of the estate which need it most.[21] In an effort to release more funds for estate work, the Department has reduced staff costs and overheads in Defence Estates by £21 million over four years, and by realising the benefits of more efficient, long-term and large-scale prime contracts, it released £22 million in 2006-07. The Treasury and the Department have also allowed some receipts from the disposal of surplus land and buildings to be reinvested in the estate, as with some sites in London.[22] Since the publication of the Comptroller and Auditor General's report, the Department has decided to implement projects to reduce energy at sixteen more sites following the example of a pilot at RAF Kinloss.[23] This investment should release more than £2 million annually, for a one-off cost of around £2.3 million.

10. At times, however, the Department is faced with developments which may affect its financial position at short notice, and which require adjustments to avoid breaching its budget. Traditionally, the maintenance and upkeep of the estate have been among the first areas reduced to address financial shortfalls.[24] The creation of Defence Estates as an internal expert body on estate matters and the introduction of new, long-term contracting arrangements were intended to reduce the defence estate's particular vulnerability to in-year budget cuts.[25] In 2006-07, the Department was not prepared for the sudden increase in the cost of fuel. It faced a £70 million shortfall and was forced to make cuts to planned expenditure during the year.[26] Defence Estates' budget was cut by £15 million, representing over 20% of the total shortfall, despite the estate representing less than 4% of the Department's total operating cost.

11. The Department lacked adequate management information to be able to target the cuts at the least important estate work. Work to the value of £13.5 million was removed from the five Regional Prime Contracts which are responsible for maintaining and improving the working estate and living accommodation for single personnel across Great Britain. The cuts included key work such as re-roofing projects, repairs to buildings at Munitions Centres and redecoration programmes. Deferring these projects for one year has implications for the condition of defence assets. Under their contracts, most Regional Prime Contractors are obliged to ensure that there is no deterioration in the estate they manage over the lifetime of their contracts. The Department cannot hold its contractors to account for fulfilling these terms if it does not identify funds to pay for most, if not all, of the work for which it has previously withdrawn funding.[27]

12. The Department could instead have made cuts to other estate work. Projects to the value of at least £45 million were ordered at short notice by Defence Estates' internal customers—principally the three Services—to be carried out by Regional Prime Contractors in addition to their core works. Known as Minor New Works, these projects included at least £1.6 million for the construction and refurbishment of sports facilities, such as tennis courts and all-weather pitches.[28] The Department now accepts that its decision to carry out some of these projects while cancelling essential maintenance work seems questionable in hindsight.[29] The decision was taken by high-level representatives of the three Services and other internal customers of Defence Estates.[30] Some packages of the deferred work were then reinstated later as Minor New Works.[31]

13. The Defence Management Board has almost no advance knowledge of the likely level of expenditure on Minor New Works before the beginning of each financial year. The Department therefore lacked key information when deciding how to apportion the £15 million funding cut in 2006-07.[32] No system exists to allow Minor New Works projects to be prioritised routinely alongside one another, or against other kinds of expenditure on the estate such as upgrades to houses. The Department told us that such a system is now being developed.[33] Likewise, there is no effective process by which opportunities to bring together similar projects into coherent programmes of work—for instance numerous separate projects to repair and replace toilet and shower facilities—can be identified.

14. The Department has been pursuing the same strategy for its estate since 2000 but it has yet to determine what this strategy will mean in practice for much of its land and buildings, and it still has no evidence-based way of determining where expenditure is needed most. Integrated Estate Management Plans are intended to address this vacuum by providing detailed priorities for the development of each defence site. The site occupants had initially been tasked to complete the first version of these plans three months before detailed guidance had been produced, although the deadline was later extended to September 2007.[34]


21   Q 21 Back

22   Qq 22-23, 27, 53-55; C&AG's Report, Box 3, p 20 Back

23   Q 86 Back

24   Q 41 Back

25   Qq 4-5, 9, 41 Back

26   Q 12 Back

27   Q 20 Back

28   Qq 12, 40; C&AG's Report, para 1.17, appendix 5 Back

29   Q 13 Back

30   Q 13 Back

31   Q 46 Back

32   Q 71 Back

33   Qq 47, 71 Back

34   Q 82 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 29 November 2007