SUPPORTING OPERATIONS AND RECUPERATION
46. The DE&S Business Strategy, April 2007, states
that:
Support to current and future operations will remain
our highest priority. This includes all aspects of support, from
delivery of logistics and Urgent Operational Requirements to current
operations through to the management of investment projects supporting
future activity.[59]
47. Up until December 2007, 796 Urgent Operational
Requirements (UORs) had been approved to a value of £2.4
billion. A total of 219 UORs were approved in 2006-07 (124 for
Afghanistan and 95 for Iraq) at a value of £793 million.[60]
We have examined the MoD's performance in delivering UORs in several
of our inquiries. In our Defence Procurement 2006 we concluded
that:
The Defence Procurement Agency is to be congratulated
for its performance, to date, in procuring Urgent Operational
Requirements for UK Forces deployed on operations. We consider
that there are some important lessons which can be learned from
the procurement of Urgent Operational Requirements and applied
to mainstream equipment procurement, and we expect the MoD to
ensure that this is done.[61]
48. Supporting current operations was CDM's main
concern because it "is our primary aim and that is where
things will go wrong and, if they are to go wrong, they will have
the greatest impact".[62]
We asked what the feedback had been from the military customer.
CDM said that commanders in theatre were very supportive. The
feedback from one senior Army officer was that he had never been
in a theatre of operations where he had seen so much new and outstanding
kit coming through.[63]
49. The UOR process has generally been a success
story. However, there have been many reports in the media claiming
that our Armed Forces on operations had not always received what
they had requested. Lieutenant General Applegate explained the
process of articulating the requirement identified in theatre
and getting this approved for UOR funding. Once this was done,
the MoD had to go into the market to see what was available. He
emphasised that the lead time for some of these requirements was
significant.[64] He said
that:
there is a time lag
. even for things like heavy
machine guns and general purpose machine guns which one might
think would be common. For a heavy machine gun there is a six-month
lag; for a general purpose machine gun there is a 12-month lag
in the market place because it is not there.[65]
The MoD had received a lot of support from the US
to bring the Mastiff vehicle in on an accelerated timescale.[66]
50. The
UOR process has delivered substantial amounts of vital equipment
to our Armed Forces operating in Afghanistan and Iraq. We commend
DE&S for the speed at which it is getting urgently needed
equipment into theatre, the procurement of Mastiff vehicles being
a good example of this.
51. We asked about the funding for supporting equipment
procured as UORs. Lieutenant General Applegate said that:
At the moment the funding we have is enough to keep
them for the period of a UOR; in other words, the UORs last for
a year and you must make a decision then as to whether to bring
them into the core programme, that is, find new money or get rid
of them.[67]
He told us that some of the UORs had been brought
into the core programme and that "some of the decisions this
year are about what else we should bring into the core programme".[68]
Mr Gould added that if UORs were brought back into the core programme,
it came out of the Equipment Programme and was "separate
from and additional to the £2.4 billion".[69]
52. Following our evidence session the MoD provided
us with updated information on UORs. As at January 2008, the total
cost of UORs approved for Afghanistan and Iraq was over £3
billion. The MoD explained that equipment procured through the
UOR procedure was brought into the core defence programme, usually
at the end of an operation, if it was "judged that there
is an enduring requirement for the capability and that it is cost-effective
to retain it". To date, the MoD had brought into the core
equipment programme 44 UORs which originally cost some £230
million. The MoD told us that:
Bringing a UOR into core does not cost anything or
require money to be taken from other equipment programmesthe
only impact on MoD budgets is the future support and disposal
costs for the capabilities. To date, UOR approvals have had no
impact on the forward programme of equipment.
The MoD said that there has been no reluctance to
approve UORs and the Treasury continued to pay for 100% of "up
front UOR costs".[70]
53. We examined support for operations in our UK
land operations in Iraq 2007 report. One of the concerns raised
in our report was:
that equipment returning from operational theatreswhether
it was procured through the routine acquisition process or as
UORswill require substantial expenditure to repair, refurbish,
support and store, and it appears that no provision has been made
for this in the MoD's budget.[71]
54. The Government Response to this report states
that:
In order to maintain equipment capability and avoid
degeneration, we may repair and overhaul military vehicles used
on operations more often than would routinely have been planned
for in through-life costing assumptions. But the precise impact
of activity on current operations and the subsequent costs of
recuperation to a balanced force are complex issues, which depend
on a range of factors. We have therefore initiated a substantial
study to provide a detailed assessment of these issues, including
the costs relating to operational usage, which will help to inform
future equipment and financial planning.[72]
55. We asked whether the recuperation of equipment
would be funded as a cost of operation or whether it came out
of the core budget. Lieutenant General Applegate said that:
Some of that funding does come out of contingency
funding in order to maintain it. I am less sanguine about the
cost of recuperation
. in other words, at a time when we
do not need that equipment on the operation, or the operation
is closing down, or we are trying to reconstitute a reserve, is
there sufficient money to prepare for a contingency task in five
years' time? That is an issue which the department is looking
at in this [Planning] round.[73]
56. We
note that the MoD has initiated a study to assess the impact of
current operations on equipment, such as vehicles, and the subsequent
costs of recuperation. We see the costs of recuperation as a cost
of operation to be funded from the Reserve and not from the defence
budget which is already under substantial pressure. In its response
to our report, we expect the MoD to set out the terms of reference
for this study and, once the study is completed, to provide us
with a copy of it.
Performance against Key Targets
57. We examined defence procurement issues in our
report Ministry of Defence Annual Report and Accounts 2006-07
and we noted that:
the latest Annual Report and Accounts state that
for the second year running the MoD "met or exceeded its
Public Service Agreement targets for equipment procurement, despite
them being more demanding than those for 2005-06", and that
the Defence Procurement Agency met all its Key Targets in 2006-07
for the second consecutive year. The Defence Procurement Agency
and the Defence Logistics Organisation merged on 1 April 2007
to form Defence Equipment and Support. We hope that the new organisation
will maintain this momentum.[74]
58. In the report we examined the MoD's assessment
of its expected performance in 2007-08 against PSA Target 6"to
deliver the Equipment Programme to cost and time". The MoD's
Autumn Performance Report 2007 assessed PSA Target 6 as "likely
to be partly met".[75]
In 2007-08, the Nimrod MRA4 aircraft programme was experiencing
forecast cost increases and the Type 45 destroyer and A400M transport
aircraft programmes had experienced further in-service date slippage.[76]
59. At the evidence session for our Defence Equipment
2008 inquiry, we asked if DE&S would meet the former DPA Key
Targets for 2007-08. CDM told us that:
We will meet the cost and performance targets but
I do think we will meet the time target.[77]
60. The major project showing cost growth in 2007-08
was Nimrod MRA4.[78]
We examine the progress of this programme later in our report
(paragraphs 124-130). Another major project where the MoD had
some concern about cost growth was the BVRAAM[79]
air-to-air missile. Mr Gould explained that:
The risks there are not so much technicalbecause
the missile programme itself is going quite wellas production
costs. We are signed up for production but the other nations[80]
are not. At the moment they do or do not sign up for production
that will have a major effect on the production costs of the missile.
There was also some concern regarding the integration
cost of Typhoon and "whether or not the Italians come into
that programme will have an effect on that budget".[81]
61. On slippage, CDM confirmed that the position
in 2007-08 would be worse than the position in 2006-07. He said
there were three reasons for slippage:
- "the programme is not
going as fast as we thought it would, and that might be for technical
reasons or whatever;
- the second big factor is that it is an international
project over which we really have no control. A very good example
is A400M and Typhoon. We do not have control over the time of
delivery;
- the third matter is those areas where we have
chosen for one reason or another not to bring something in when
we thought we would. Meteor-BVRAAM is a very good example of that.
For operational reasons we do not need to bring that in when we
originally said we did."[82]
62. Following our evidence session the MoD provided
us with details of the major equipment projects experiencing in-service
date slippage in 2007-08. As at the end of January 2008, of the
20 largest equipment projects which featured in the Major Projects
Report 2007, seven of the 20 projects had reached their in-service
date. The Joint Strike Fighter[83]
does not have an approved in-service date.[84]
Of the remaining 12 projects, seven were reporting in-year in-service
date slippage. Details of the in-service date slippage experienced
by these seven projects in 2007-08 are set out in Table 2.
Table 2: In-service date slippage experienced by major equipment projects in 2007-08