Select Committee on Defence Written Evidence


Supplementary memorandum from the Ministry of Defence

ANSWERS TO THE HOUSE OF COMMONS SELECT COMMITTEE'S FOLLOW UP QUESTIONS ON THE GOVERNMENT RESPONSE TO THE MINISTRY OF DEFENCE 2007-08 SPRING SUPPLEMENTARY ESTIMATES

1.   At what point in FY 2007-08 did it become clear that there was going to be a more offensive campaign in Afghanistan in that FY that would require more expenditure than was envisaged at the time of the WSE?

  The additional manpower deployment required to increase operational tempo in Afghanistan was approved by Ministers towards the end of July 2007. This was too late to be included with any certainty in July forecasts, upon which the WSE resource request was based. The increased operational tempo was sustained until December 2007. The forecast costs for operations for the SSE were based on end November estimates which included the costs for the increase in the campaign.

2.   At what point in FY 2007-08 did it become clear that increased buildings and vehicle protection in Iraq would be required in that FY and which would require more expenditure than was envisaged at the time of the WSE?

  The estimates for the cost of operations in Iraq for WSE were based on end July forecasts; those for the SSE were based on end November forecasts. The costs for the increased buildings protection in the central operating base were established in November. The costs for the increased vehicle protection were identified as part of the Capability Review held in September 2007.

3.   Is the MoD content that the forecasts in the WSE for the Direct Resource and Capital costs of Iraq/Afghanistan operations would have proved robust had not the unexpected requirements outlined in questions 1 and 2 above materialised?

  The forecasts in the WSE represented the best estimate of the likely costs of Iraq and Afghanistan when the Estimate was submitted. As we explained in the Government response to HC140, the Defence Committee's report on the Spring Supplementary Estimates 2007-08, operational costs are difficult to forecast and sensitive to changes in operational policy and the operational context. There is always likely to be a variation between the forecasts used to inform Winter Supplementary Estimates and those to inform Spring Supplementary Estimates.

4.   Given the volatility of operations in Afghanistan and Iraq, is the MoD content that it has the correct procedures in place to assess and quantify changes in forecast costs as quickly as possible?

  The Department is always seeking to improve its processes. As we reported in the Government response to the Committee's report on SSE we have introduced a new methodology for capturing the non-cash costs of operations. In addition we have made enhancements to the existing reporting system to enable more effective monitoring of UOR expenditure and set up a specialist working group, which will enable the Department to track costs more robustly. We will continue to improve our reporting systems.

5.   Has any thought been given by the MoD to providing interim data, between Estimates, to Parliament or to the Defence Committee setting out an outline of likely changes in forecast costs should changes in operational tempo/stance occur?

  In practice, forecasts of the costs of operations are passed to Parliament in Winter Supplementaries in November and Spring Supplementaries in February. A further forecast could be provided to the Committee between Supplementaries if the Committee would find that helpful.

5 June 2008





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 7 July 2008