Memorandum submitted by Construction Design Practice Ltd

BRITISH WATERWAYS REGENERATION PROJECT— MAYOR'S BOAT YARD, WIGAN.

EXECUTIVE SUMMARY:

  Construction Design Practice is currently working collaboratively with British Waterways on a scheme in Wigan, referred to as Mayors Boatyard, involving the restoration of buildings and site areas fronting the Leeds and Liverpool Canal within the Wigan Pier Quarter Conservation Area.

  CDP have developed proposals for the site and buildings in collaboration with BW in line with the desire by BW for the buildings to be restored and brought back into sustainable use, whilst conserving and maintaining the historical significance of the site.

  The value of the works is expected to be of the order of £1.2 million.

  The Partnering Arrangement with BW was the result of a tendering and interview process, whereby the Proposals for the conservation of the site were weighted alongside commercial interest.

  Throughout the design development British Waterways have been able to offer their invaluable input to the scheme in terms of technical solutions, appropriateness of design and coordination between the interested parties and the local authority.

  British Waterways have taken the lead in presenting the scheme to Interested "User Groups" and have set up the vital communications for applications for Grant Aid.

  The scheme was submitted for Planning Approval on 29th February 2008.

1.  INTRODUCTION

  Construction Design Practice Ltd is an Engineering Consultancy Practice, based in the north west of England.

  Construction Design Practice is currently working collaboratively with British Waterways on a scheme in Wigan, involving the restoration of buildings and site areas fronting the Leeds and Liverpool Canal within the Wigan Pier Quarter Conservation Area.

  The site is referred to as Mayors Boatyard.

2.  PROJECT PARTNERING ARRANGEMENTS IN WIGAN:

  CDP develop proposals for the site and buildings in collaboration with BW in line with the desire by BW for the buildings to be restored and brought back into sustainable use, whilst conserving and maintaining the historical significance of the site.

  The buildings will be developed for B1 commercial use and with the boat user being relocated within the site.

  CDP will act as developer and provide a significant element of funding required for refurbishing the main part of the site, in exchange for a long-term lease.

  The Partnering Arrangement with BW was the result of a tendering and interview process, whereby the Proposals for the conservation of the site were weighted alongside the commercial interest.

3.  SCHEME DETAILS:

  The site area contains 3 buildings, referred to as buildings A, B and C respectively.

  Building A is currently in a dilapidated state and is unused.

  Building B is currently in a dilapidated state and is unused.

  Building C is in a dilapidated state but is used as a dry storage area.

  The site area is currently used for the benefit of boat users for the loading of canal barges. This function will be relocated within the site.

  Historically, the site has been used as a fabrication and maintenance facility for wooden canal boats since 1880. The last canal boat being launched in 1952.

  The facility closed in 1959, since which time there have been different uses for the site, but one the main buildings were vacated; there has been an escalating scale of dilapidation.

  It is proposed to upgrade to a high specification, the buildings and site to bring the site back into commercial use as Class B1 Business Use: office space/light industrial/technical.

  It is proposed to improve the character of the Site through a mixture of hard and soft landscaping and by sensitive restoration of the buildings, which will include modifying the footprint and alteration of the façade to Building C.

  The redevelopment will provide restored high quality buildings of character, with levels of comfort and servicing fit for the 21st century.

  External works will include improved off street parking and significant landscaping enhancements.

  The scheme was submitted for Planning Approval on 29th February 2008.

4.  COLLABORATIVE WORKING ARRANGEMENTS:

  Throughout the design development Construction Design Practice [CDP] have kept constant dialogue with British Waterways, who have been able to offer their invaluable input to the scheme in terms of professional advice, technical solutions, appropriateness of design and coordination between the interested parties and the local authority.

  British Waterways have been particularly active in presenting the scheme to Interested "User Groups" and have set up the vital communications for applications for Grant Aid.

  British Waterways are very proactive in ensuring the regeneration process happens, and happens quickly, and must be commended on their initiatives and networking to bring this project to fruition.

  In conclusion, I would request that the Committee gives British Waterways their active support and encouragement to continue its work in this field.

Construction Design Practice Ltd

March 2008






 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 1 July 2008