Select Committee on Environment, Food and Rural Affairs Written Evidence


Memorandum submitted by The Cotswold Canals Trust

  1.  Executive Summary—The Cotswold Canals Trust (CCT) deplores the way in which British Waterways (BW) has withdrawn from the Cotswold Canals Partnership. Its action has put £30 million of funding for the Cotswold Canals restoration project at severe risk and is seen as a betrayal by those interested in Britain's unique national waterway network. The current situation highlights some deep seated problems in the direction that BW has been going in recent years. CCT wants to see BW re-engage with the Cotswold Project but we also believe that BW needs to be made fit for purpose with a clear focus that concentrates on the well being of our waterways in an inspirational way so that confidence can be restored.

  2.  The Cotswold Canals Trust, a registered charity, is the largest canal restoration society in the UK with over 5200 members. Its primary objective is to bring about the restoration of the historic Stroudwater Navigation and Thames & Severn Canals which together link the River Thames to the Severn. The Trust is a key member of the Cotswold Canals Partnership.

  3.  The restoration of the Cotswold Canals is ranked near the top, if not at the top, of the priority list by waterway bodies and enthusiasts alike. Its strategic place as the missing link between England's two greatest rivers is unique.

  4.  BW's involvement as lead partner provided confidence to both funders and the local community with the result that expectations of early progress and success were raised. The project successfully secured an increasingly rare major Heritage Lottery Fund (HLF) grant of £12 million which enabled a funding package worth a total of £35 million to be assembled.

  5.  BW's withdrawal at the beginning of February was without notice to most of the other Partners, including CCT, and has accurately been described as a "betrayal" and "a kick in the teeth". One of our members made the following analogy: "It's akin to the government saying " You know what, I don't think I want to do the Olympics now, let's just not bother"—after all the hard work, deals struck, funding secured and already paid out—it's just not do-able in any sense. Yet that is exactly what BW is trying to do."

  6.  In pulling out, BW have shown a reckless disregard for businesses that have assumed that the project will happen and have invested on that basis, the aspirations of the local community for the restoration itself and resulting economic regeneration and the views of canal supporters throughout the country (many of whom have been campaigning for BW's own grant to be safeguarded).

  7.  The other Partners are resolved to continue the project and there is little doubt that both the technical and financial capability exists to do this. However, in withdrawing and saving themselves perhaps £3 million of their own money, BW has put the other £30 million funding of the project in severe jeopardy. BW signed the agreement with HLF as lead partner and we have been told that is not possible to simply swap them for a new one. HLF have indicated that they will require a new grant application. The delay and uncertainty that this would cause could easily compromise the other funding and set off a domino effect resulting in the loss of the project.

  8.  BW has used the cost of repairing the breach on the Mon & Brec Canal and the government reduction in their funding as excuses to pull out of the Cotswold Project. CCT does not accept these excuses for the following reasons.

    (a)  Even assuming that BW could not have borrowed money, they have many assets, particularly property related ones, and could have chosen to sell a small part of these to overcome the Mon & Brec problem.

    (b)  BW seemed to be all too ready to pull out of the Cotswold Project without fully exploring alternative funding sources for the Mon & Brec problem.

    (c)  Long before the DEFRA funding cuts and the Mon & Brec problem, BW had been showing signs that they were not wholeheartedly committed to the Cotswold Project.

  9.  BW became involved with the Cotswold Canals project hot on the tail of several spectacularly successful but very challenging restoration projects including the Huddersfield Narrow Canal, the Rochdale Canal and the Millennium Link (including the Falkirk Wheel) in Scotland. David Fletcher was Chief Executive and BW was a confident "can do" type organisation with high staff morale, inspirational leadership and the ability to attract third party funding and partners for both restoration and commercial projects.

  10.  Following changes at the top of BW, the attitude started to change. Whist still supporting the Cotswold project publicly, investment in the all important project management side of things frequently bordered on the non-existent. CCT warned Robin Evans, in a meeting called for the purpose, of our concern that a project of this complexity would degenerate into a mess without proper project management but this warning went unheeded.

  11.  Coupled with inadequate project management came a near obsession with risk and an unwillingness to get the project moving. The minutes of BW Board Meetings in 2005 show that they were anticipating the real possibility of pulling out even then. This was averted by CCT demonstrating that it had project managed the successful delivery of a road bridge using contractors at a cost of £360,000 as against a BW consultant's previous estimate of £830,000 (adjusted to 2005 prices). BW then conducted an internal review of their previous costings and concluded that the project could be delivered after all.

  12.  In January 2006, HLF confirmed their grant to the Cotswold Canals Project and the works were expected to be complete in 3 years. Incredibly, no project manager was put in place until January this year; the same month BW decided to withdraw. Instead, the intervening two years were occupied by yet more risk reviews either centred around engineering costs or lower potential property development returns whilst a small number of relatively junior BW engineering staff struggled to get the project going in the face of little support from senior management.

  13.  Running in parallel with these problems, BW has frequently failed to take advantage of the availability of volunteers offering professional expertise in many areas as well as those prepared to help in physical works. Although volunteers often receive praise, the reality is that BW does not seem to understand the Third Sector nor the considerable contribution that it can make.

  14.  The attitude towards financial management of the project has been poor. Concepts like value for money and not treating contingency money as just another part of the ordinary budget seem alien. In October 2005, CCT was told that putting work at Oil Mills Bridge (the first one in the project) out to tender was not possible because of the shortage of time so a BW Omnibus contractor would have to do the job. The project actually started in October 2007.

  15.  Delays in the project have wasted about £3 million in inflation costs alone. For a long time now, the biggest risk to the project has been the constant review of risk resulting in the failure to get on with the job. The delays have also put other time related third party funding at risk.

  16.  The Cotswold Canals Project remains entirely viable, technically deliverable and remains highly desirable. CCT and Stroud District Council working together are determined to see the project through and it won't be hard to make a better job of it. The biggest problem we face is keeping the funding package intact. BW is perceived as the national body with all the expertise needed to successfully restore, operate and maintain canals; their withdrawal from any project can therefore have catastrophic consequences. There is already evidence that future funders have already been put off by BW's actions.

RECOMMENDATIONS:

  1.  Confirm to BW that restoration projects, with the huge benefits they bring, are a core part of what BW are expected to deliver.

  2.  Given the risk of losing £30 million of other funding if they withdrawal, BW should be instructed by the Government to re-engage properly with the project. It should be made clear that they cannot simply decide to walk away from their prior commitments, including signed agreements, in the way they have.

  3.  There needs to be a massive change of culture within BW to make it the inspirational, efficient organisation championing the waterways of Great Britain it was becoming rather than the risk averse, low morale, "can't do" organisation that it has become. This is unlikely to be possible without some changes in leadership.

  4.  BW needs to be able to engage with the Third Sector and will reap financial benefits by doing so. A Board level appointment of someone with attributes which include a background of involvement in the waterway restoration movement would help provide do this.

  5.  An urgent look at the way that navigation authorities are funded should take place which takes into account the benefits that waterways bring in terms of regeneration, public health and economic activity which fall beyond the normal remit of DEFRA.

The Cotswold Canals Trust

March 2008






 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 1 July 2008