Select Committee on Environment, Food and Rural Affairs Written Evidence


Memorandum submitted by Ewan Larcombe (FL 128)

SUMMARY

  1.  The Environment Agency is currently unwilling or unable to ensure that existing watercourses and flood defences are maintained, thus increasing the probability of flooding.

  2.  Create a new independent Flood Defence Agency (using existing EA/Defra employees whose work is currently primarily flood related.)

  3.  Give the Agency the legal duty to maintain the Thames for flood defence purposes, with appropriate powers as required.

  4.  Change the culture and ensure that higher ranking employees are properly qualified and have a good understanding of Applied Fluvial Geomorphology or similar. Reintroduce "Flood Defence".

  5.  Existing river and flood defence maintenance to be the priority, with new flood defence schemes taking second place.

  6.  The Agency must be honest, transparent and accountable for their actions/inactions. When things go wrong, action should be taken against responsible individuals.

  7.  Ensure that consultations are easy to understand and receive wide publicity.

  8.  Create the position of Ombudsman for Flood Defence.

  9.  Place a duty on local Parish and Town Councils to regularly monitor and record the condition of all elements of their flood defences, to communicate with geographically adjacent authorities, and report potential problems to appropriate authorities.

SUBMISSION

  1.  Over recent years, the Environment Agency has taken over responsibility for thousands of miles of Critical Ordinary Watercourse from the local authorities. These watercourses are not being maintained by the riparian owners or the Environment Agency, leading to reducing capacity and increasing probability of flooding over time. Any maintenance that does take place is cosmetic and superficial. Trees are trimmed, paths cleared and fences repaired and painted. Local authorities have lost both the resource and the experience. The Environment Agency appears unwilling to use their powers to ensure that riparian owners fulfil their obligations towards watercourses and flood banks. I can give examples of flood banks that have been eroded or deliberately deconstructed, subsiding and failing banks, and watercourses with near zero flow due to bed-rise that the Environment Agency will not permit to be cleared or re-graded. In my opinion, the Environment Agency is currently unwilling or unable to ensure that existing watercourses and flood defences are maintained, thus increasing the probability of flooding.

  2.  Today the Environment Agency suffers from an internal conflict of interest. Previously the National Rivers Authority would ensure that that watercourse capacity was maintained, but now the Environment Agency will produce a long list of reasons why a watercourse cannot be dredged. I believe we need to create a new independent Flood Defence Agency (using existing EA/Defra employees whose work is currently primarily flood related) whilst simultaneously removing the barriers to flood defence maintenance.

  3.  The Environment Agency has a duty to maintain the River Thames for navigational purposes, but only the responsibility to maintain the Thames for flood defence purposes. The reality is firstly that the primary purpose of the Thames for thousands of years is that of a drain, and any commercial or recreational use is a bonus. Secondly (and more importantly) nobody else is willing or able to take the actions necessary to maintain the capacity of the Thames. Over time, the capacity of the Thames has reduced and the water level has risen. I recommend a significant reduction in the Standard Headwater Level of the Thames. There is a need to record the entire catchment existing watercourse capacities, and to compare actual capacities with the model capacities required in order to reduce the probability of flooding. There is a need to give the Agency the legal duty to maintain the Thames for flood defence purposes, with appropriate powers as required.

  4.  The National Rivers Authority (and prior to them the Thames Conservancy) had employees in Wellington boots with considerable experience and thorough understanding of the watercourses. With the arrival of IT, Environment Agency employees believe they can control the elements from the safety of a remote keyboard in a warm, dry office. The practice of "Flood defence" has been replaced by "Flood Risk Management" and the probability of flooding is increasing. We need to change the culture and ensure that higher ranking employees are properly qualified and have a good understanding of Applied Fluvial Geomorphology or similar.

  5.  Much existing river and flood defence maintenance has been abandoned. In my opinion it is pointless producing new flood defence schemes when existing defences are not working properly. Water causes flooding because it is trapped and unable to escape. The ancient watercourses both natural and manmade need continuous monitoring and regular maintenance. In particular, the bed of the Thames has risen since dredging for flood defence purposes was abandoned. Local dredging now only takes place on receipt of complaints that boats are scraping the bottom.

  6.  The £110 million Jubilee River scheme is still awaiting repair and unable to carry its design capacity. On first use at only 66% of capacity in January 2003, hundreds of homes suffered flooding for the first time since 1947. The Environment Agency had no right to divert floodwater onto undefended villages. Sub-standard design, construction and operation led to structural damage, £4 million repairs and a £2.75 million out-of-court settlement. The Agency "closed ranks" with consultants and contractors (all with incestuous pecuniary interests and protecting each other) to deny liability. These people are all paid with public money, and we the public are also their customers. Environment Agency employees are no longer capable of determining whether their consultants or contractors are giving good advice or service. I believe that the Agency must be honest, transparent and accountable for their actions/inactions, and this behaviour starts from the top. When things go wrong, and members of the public are affected or disadvantaged, action should be taken against responsible individuals.

  7.  Environment Agency consultations are very complex and poorly publicised. In particular, the EA will notify a Borough Council about a consultation, who themselves then fail to respond or to pass on the information. It would be easy to notify all parish and Town Councils by e-mail, thus ensuring that consultations are easy to understand and receive wide publicity.

  8.  There is a need for an independent authority to consider complaints against the Environment Agency. Create the position of Ombudsman for Flood Defence.

  9.  The local people have a vested interest in flood defence maintenance. They are best placed to know and understand local flood defences, to recognise shortcomings and the need for maintenance, and the implications of changes. We should place a duty on local Parish and Town Councils to regularly monitor and record the condition of all elements of their flood defences, to communicate with geographically adjacent authorities, and to report potential problems to appropriate authorities.

Ewan Larcombe

October 2007





 